This is a Schedule of Items pricing template for the Sand Pond Boardwalk Replacement project on Tahoe National Forest. The schedule outlines seven line items required for the complete project, including mobilization, clearing and grubbing, boardwalk installation (1,100 linear feet), bridge installation, erosion control, removal of existing improvements (existing bridge, 200 linear feet of existing boardwalk, and two lumber debris piles measuring 10' x 10' x 4' each), and delivery and stockpile of crushed aggregate surface course (20 cubic yards). All items are currently priced at zero dollars, indicating this is a blank template awaiting contractor pricing submissions.

The solicitation is issued as a Request for Quotation (RFQ) under NAICS code 237990 with a small business size standard of $45.0 million and is designated as a Total Small Business Set-Aside. The Department of Agriculture Forest Service is the contracting agency. Contractors responding to solicitation number 127EAX26Q0070 must complete this pricing schedule, providing unit prices for applicable line items and calculating total prices accordingly. The project scope encompasses all materials and complete installation for both the boardwalk and bridge components, with work classified as commercial items under FAR Part 12 procedures.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Sand Pond Boardwalk Replacement- Schedule of Items
Item No.DescriptionQuantitiesMethod of
MeasureTotal
QuantityUnit PriceTotal Price
90701MobilizationCQLump Sum1$ -$ -

91203 Clearing and Grubbing CQ Lump Sum 1 $ - $ -

93801 Boardwalk All Materials and Complete Installation CQ Lineal Feet 1100 $ - $ -

96202 Bridge All Materials and Complete Intallation CQ Lump Sum 1 $ - $ -

98202 Erosion Control CQ Lump Sum 1 $ - $ -

98301 Removal of Improvements- Existing Bridge, 200 LF Existing Boardwalk and 2 Lumber Debris Piles (10' x 10' x 4' each) CQ Lump Sum 1 $ - $ -

99101Crushed Aggregate Surface Course, Grading B Delivery and Stockpile OnlyCQCubic Yard20$ -$ -
TOTAL$