This is a PM SPE Engineering Change Request (ECR) form template used by vendors to request modifications to federal contracts and procurement activities.
The form requires vendors to complete blocks 2-19 and submit to PM SPE. Key information fields include: originator details (name and address); ECR type classification as ECP, RFD, or RFW; severity classification (Critical, Minor, or Major); ECR title; item designation (MCN/NSN and model/design code); procurement activity and baseline affected (Functional, Product, or Allocated); end item nomenclature; contract number and line item; lots/materials affected; reoccurring deviation status with CAR number if applicable; effects on cost/price and delivery schedule; other affected systems/configuration items/interfaces; detailed description of the change; need justification; and corrective actions taken. The submitting activity section requires typed name, title/organization, signature, and date in YYYYMMDD format.
The approval workflow varies by ECR classification: Minor ECRs require Contracting Officer Representative (COR) approval; Major ECRs require both COR/PM SPE Technical Staff approval and Assistant Program Manager (APM) approval; Critical ECRs require approval from all three levels plus PM SPE. Each approval section includes spaces for approval/disapproval selection, signature, and date. The form also includes a PM SPE Justification section (Block 20) and Attachments section (Block 21) for supporting documentation. This is a three-page template with space for continuation of narrative sections on pages 2 and 3.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PM SPE ENGINEERING CHANGE REQUEST (ECR)
(Vendors – Complete Blocks 2 – 19 and Submit to PM SPE)
1. PM SPE CONTROL NUMBER
2. ORIGINATOR 3. ECR TYPE
a. TYPED NAME (First, Middle Initial, Last)
b. ADDRESS (Street, City, State, Zip Code)
RFD
RFW
4. CLASSIFICATION
5. TITLE OF ECR
6. ITEM DESIGNATION 7. PROCUREMENT ACTIVITY
8. BASELINE AFFECTED
a. MCN / NSN b. MODEL / DESIGN CODE
9. END ITEM NOMENCLATURE 10. CONTRACT NUMBER AND LINE ITEM
11. LOTS / MATERIAL AFFECTED
12. REOCCURING DEVIATION (if Yes, Provide CAR# in Block 12 & Status in Block 18)
13. EFFECT ON COST / PRICE
14. EFFECT ON DELIVERY SCHEDULE
15. OTHER SYSTEMS / CONFIGURATION ITEMS / INTERFACES AFFECTED
16. DESCRIPTION OF ECR
17. NEED FOR ECR
18. CORRECTIVE ACTION TAKEN
19. SUBMITTING ACTIVITY
a. TYPED NAME (FIRST, MIDDLE INITIAL, LAST)
c. SIGNATURE
b. TITLE / ORGANIZATION
d. DATE (YYYYMMDD)
PM SPE FORM 1 (ECR), JULY 15 Page 1
PM SPE CONTROL NUMBER
TITLE OF ECR
20. PM SPE JUSTIFICATION
21. ATTACHMENTS
22. COR (APPROVAL AUTHORITY FOR MINOR ECRS) / PM SPE TECHNICAL STAFF APPROVAL / DISAPPROVAL FOR MAJOR OR CRITICAL ECRS)
a. APPROVAL
b. SIGNATURE
c. DATE SIGNED
(YYYYMMDD)
23. APM APPROVAL / DISAPPROVAL (APPROVAL AUTHORITY FOR MAJOR ECRs)
24. PM SPE APPROVAL / DISAPPROVAL (APPROVAL AUTHORITY FOR CRITICAL ECRs)
PM SPE FORM 1 (ECR), JULY 15 Page 2
PM SPE CONTROL NUMBER
TITLE OF ECR
PM SPE FORM 1 (ECR), JULY 15 Page 3