This is a PM SPE Engineering Change Request (ECR) form template used by vendors to request modifications to federal contracts and procurement activities.

The form requires vendors to complete blocks 2-19 and submit to PM SPE. Key information fields include: originator details (name and address); ECR type classification as ECP, RFD, or RFW; severity classification (Critical, Minor, or Major); ECR title; item designation (MCN/NSN and model/design code); procurement activity and baseline affected (Functional, Product, or Allocated); end item nomenclature; contract number and line item; lots/materials affected; reoccurring deviation status with CAR number if applicable; effects on cost/price and delivery schedule; other affected systems/configuration items/interfaces; detailed description of the change; need justification; and corrective actions taken. The submitting activity section requires typed name, title/organization, signature, and date in YYYYMMDD format.

The approval workflow varies by ECR classification: Minor ECRs require Contracting Officer Representative (COR) approval; Major ECRs require both COR/PM SPE Technical Staff approval and Assistant Program Manager (APM) approval; Critical ECRs require approval from all three levels plus PM SPE. Each approval section includes spaces for approval/disapproval selection, signature, and date. The form also includes a PM SPE Justification section (Block 20) and Attachments section (Block 21) for supporting documentation. This is a three-page template with space for continuation of narrative sections on pages 2 and 3.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PM SPE ENGINEERING CHANGE REQUEST (ECR)

(Vendors – Complete Blocks 2 – 19 and Submit to PM SPE)

1. PM SPE CONTROL NUMBER

2. ORIGINATOR 3. ECR TYPE

a. TYPED NAME (First, Middle Initial, Last)

b. ADDRESS (Street, City, State, Zip Code)

RFD

RFW

4. CLASSIFICATION

5. TITLE OF ECR

6. ITEM DESIGNATION 7. PROCUREMENT ACTIVITY

8. BASELINE AFFECTED

a. MCN / NSN b. MODEL / DESIGN CODE

9. END ITEM NOMENCLATURE 10. CONTRACT NUMBER AND LINE ITEM

11. LOTS / MATERIAL AFFECTED

12. REOCCURING DEVIATION (if Yes, Provide CAR# in Block 12 & Status in Block 18)

13. EFFECT ON COST / PRICE

14. EFFECT ON DELIVERY SCHEDULE

15. OTHER SYSTEMS / CONFIGURATION ITEMS / INTERFACES AFFECTED

16. DESCRIPTION OF ECR

17. NEED FOR ECR

18. CORRECTIVE ACTION TAKEN

19. SUBMITTING ACTIVITY

a. TYPED NAME (FIRST, MIDDLE INITIAL, LAST)

c. SIGNATURE

b. TITLE / ORGANIZATION

d. DATE (YYYYMMDD)

PM SPE FORM 1 (ECR), JULY 15 Page 1

PM SPE CONTROL NUMBER

TITLE OF ECR

20. PM SPE JUSTIFICATION

21. ATTACHMENTS

22. COR (APPROVAL AUTHORITY FOR MINOR ECRS) / PM SPE TECHNICAL STAFF APPROVAL / DISAPPROVAL FOR MAJOR OR CRITICAL ECRS)

a. APPROVAL

b. SIGNATURE

c. DATE SIGNED

(YYYYMMDD)

23. APM APPROVAL / DISAPPROVAL (APPROVAL AUTHORITY FOR MAJOR ECRs)

24. PM SPE APPROVAL / DISAPPROVAL (APPROVAL AUTHORITY FOR CRITICAL ECRs)

PM SPE FORM 1 (ECR), JULY 15 Page 2

PM SPE CONTROL NUMBER

TITLE OF ECR

PM SPE FORM 1 (ECR), JULY 15 Page 3

File details come from the government source that posted it. Updated .