Ad-Hoc HQ Non-Routine / Ad-Hoc Labor and Material Costs
Location: HeadQuarters
| Base Year | | | Option Year #1 | | | Option Year #2 | | | Option Year #3 | | | Option Year #4 | | | 5 Year |
| Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Total |
| Grouping / Labor Category | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | |
| Elevator | | | | | | | | | | | | | | | | |
| Elevator Mechanic | | 1040 | | | 1040 | | | 1040 | | | 1040 | | | 1040 | | |
| Total Elevator Labor | | 1040 | | | 1040 | | | 1040 | | | 1040 | | | 1040 | | |
| Electrical & Lighting Systems | | | | | |
| Electrician Lamper | 4160 | 4160 | 4160 | 4160 | 4160 |
| Maintenance Electrician Day | 2080 | 2080 | 2080 | 2080 | 2080 |
| Total Elec&Light Sys Labor | 6240 | 6240 | 6240 | 6240 | 6240 |
| HVAC/Mechanical | | | | | |
| Project Manager | 2080 | 2080 | 2080 | 2080 | 2080 |
| Chief Engineer | 2080 | 2080 | 2080 | 2080 | 2080 |
| Admin Assist | 2080 | 2080 | 2080 | 2080 | 2080 |
| Plumber / Pipefitter | 4160 | 4160 | 4160 | 4160 | 4160 |
| Operation Engineer | 10400 | 10400 | 10400 | 10400 | 10400 |
| Total HVAC/Mech Labor | 20800 | 20800 | 20800 | 20800 | 20800 |
| Electrical Distribution (Site) | | | | | |
| Project Manager | 2080 | 2080 | 2080 | 2080 | 2080 |
| Electrician Day Supervisor | 2080 | 2080 | 2080 | 2080 | 2080 |
| Electrician Night Supervisor | 2080 | 2080 | 2080 | 2080 | 2080 |
| Admin Assist | 2080 | 2080 | 2080 | 2080 | 2080 |
| Maintenance Day Electrician Day | 10400 | 10400 | 10400 | 10400 | 10400 |
| Electrician Helper | 2080 | 2080 | 2080 | 2080 | 2080 |
| Total Elec Dist (Site) Labor | 28000 | 20800 | 20800 | 20800 | 20800 |
| Cyber Security | | | | | |
| Cybersecurity/Systems Engineer | 2080 | 2080 | 2080 | 2080 | 2080 |
| Application Admin | 2080 | 2080 | 2080 | 2080 | 2080 |
| Senior Tech | 2080 | 2080 | 2080 | 2080 | 2080 |
| Fire Alarm | 4160 | 4160 | 4160 | 4160 | 4160 |
| Total Cyber Security Labor | 10400 | 10400 | 10400 | 10400 | 10400 |
Total Ad-Hoc Labor
| Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Total Mat + |
| Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat OH |
| Ad-Hoc Material Estimate | $3,000,000.00 | | | | $3,000,000.00 | | | | $3,000,000.00 | | | | $3,000,000.00 | | | | $3,000,000.00 | | | | |
| Base | Opt Yr 1 | Opt Yr 2 | Opt Yr 3 | Opt Yr 4 | 5 Yr Total |
| Total Labor&Mat Cost | | | | | | |
| Note: |
| For Ad-Hoc Labor: Contractor is required to use Routine Maintenance labor (at no additional cost to the Gov't) if possible |
| For Ad-Hoc Material: Contractor is required to obtain and submit 3 bids for all material costs. |
Ad-Hoc Rich Non-Routine / Ad-Hoc Labor and Material Costs
Location: Richmond, Va.
| Base Year | | | Option Year #1 | | | Option Year #2 | | | Option Year #3 | | | Option Year #4 | | | 5 Year |
| Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Total |
| Grouping / Labor Category | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | |
| Elevator | | | | | | | | | | | | | | | | |
| Elevator Mechanic | | 250 | | | 250 | | | 250 | | | 250 | | | 250 | | |
| Total Elevator Labor | | 250 | | | 250 | | | 250 | | | 250 | | | 250 | | |
| Electrical & Lighting Systems | | | | | |
| Electrician | 1000 | 1000 | 1000 | 1000 | 1000 |
| Total Elec&Light Sys Labor | 1000 | 1000 | 1000 | 1000 | 1000 |
| HVAC/Mechanical | | | | | | | | | | |
| HVAC Tech | | 480 | | 480 | | 480 | | 480 | | 480 |
| Electrician | | 240 | | 240 | | 240 | | 240 | | 240 |
| Building Automation Systems | | | | | | | | | | |
| Controls Technician | | 240 | | 240 | | 240 | | 240 | | 240 | |
| Sheet Metal Worker | | 240 | | 240 | | 240 | | 240 | | 240 |
| Plumber/Pipefitter | | 240 | | 240 | | 240 | | 240 | | 240 |
| Total HVAC/Mech Labor | | 1440 | | 1440 | | 1440 | | 1440 | | 1440 |
| Electrical Distribution (Site) | | | | | |
| Electrician | 480 | 480 | 480 | 480 | 480 |
| Total Elec Dist (Site) Labor | 480 | 480 | 480 | 480 | 480 |
| Cyber Security | | | | | |
| Cybersecurity/Systems Engineer | 20 | 20 | 20 | 20 | 20 |
| Application Admin | 20 | 20 | 20 | 20 | 20 |
| Total Cyber Security Labor | 40 | 40 | 40 | 40 | 40 |
Total Ad-Hoc Labor
| Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Total Mat + |
| Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat OH |
| Ad-Hoc Material Estimate | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | |
| Base | Opt Yr 1 | Opt Yr 2 | Opt Yr 3 | Opt Yr 4 | 5 Yr Total |
| Total Labor&Mat Cost | | | | | | |
| Note: |
| For Ad-Hoc Labor: Contractor is required to use Routine Maintenance labor (at no additional cost to the Gov't) if possible |
| For Ad-Hoc Material: Contractor is required to obtain and submit 3 bids for all material costs. |
Ad-Hoc New Cumberland Non-Routine / Ad-Hoc Labor and Material Costs
Location: New Cumberland, PA
| Base Year | | | Option Year #1 | | | Option Year #2 | | | Option Year #3 | | | Option Year #4 | | | 5 Year |
| Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Total |
| Grouping / Labor Category | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | |
| Elevator | | | | | | | | | | | | | | | | |
| Elevator Mechanic Inspector | | 200 | | | 200 | | | 200 | | | 200 | | | 200 | | |
| Total Elevator Labor | | 200 | | | 200 | | | 200 | | | 200 | | | 200 | | |
| Electrical & Lighting Systems | | | | | |
| Electrician | 500 | 500 | 500 | 500 | 500 |
| Total Elec&Light Sys Labor | 500 | 500 | 500 | 500 | 500 |
| HVAC/Mechanical | | | | | |
| HVAC Tech | 500 | 500 | 500 | 500 | 500 |
| Plumber/Pipefitter | 500 | 500 | 500 | 500 | 500 |
| Total HVAC/Mech Labor | 1000 | 1000 | 1000 | 1000 | 1000 |
| Electrical Distribution (Site) | | | | | |
| Project Manager | 500 | 500 | 500 | 500 | 500 |
| Maintenance Day Electrician Day | 500 | 500 | 500 | 500 | 500 |
| Total Elec Dist (Site) Labor | 1000 | 1000 | 1000 | 1000 | 1000 |
| Potable Water / Wastewater | | | | | |
| Project Manager | 500 | 500 | 500 | 500 | 500 |
| Operation Engineer | 500 | 500 | 500 | 500 | 500 |
| Total Pot/Wastewater Labor | 1000 | 1000 | 1000 | 1000 | 1000 |
| Cyber Security | | | | | |
| Cybersecurity/Systems Engineer | 20 | 20 | 20 | 20 | 20 |
| Application Admin | 20 | 20 | 20 | 20 | 20 |
| Total Cyber Security Labor | 40 | 40 | 40 | 40 | 40 |
Total Ad-Hoc Labor
| Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Total Mat + |
| Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat OH |
| Ad-Hoc Material Estimate | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | |
| Base | Opt Yr 1 | Opt Yr 2 | Opt Yr 3 | Opt Yr 4 | 5 Yr Total |
| Total Labor&Mat Cost | | | | | | |
| Note: |
| For Ad-Hoc Labor: Contractor is required to use Routine Maintenance labor (at no additional cost to the Gov't) if possible |
| For Ad-Hoc Material: Contractor is required to obtain and submit 3 bids for all material costs. |
Ad-Hoc Col Non-Routine / Ad-Hoc Labor and Material Costs
Location: Columbus, OH
| | Base Year | | | Option Year #1 | | | Option Year #2 | | | Option Year #3 | | | Option Year #4 | | | 5 Year |
| | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Total |
| Grouping / Labor Category | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | |
| Elevator | | | | | | | | | | | | | | | | |
| Elevator Technician | | 120 | | | 120 | | | 120 | | | 120 | | | 120 | | |
| Elevator Inspector | | 80 | | | 80 | | | 80 | | | 80 | | | 80 | | |
| Building Automation Systems | | | | | | | | | | | | | | | | |
| Controls Technician | | 80 | | | 80 | | | 80 | | | 80 | | | 80 | | | |
| Total Elevator Labor | | 280 | | | 280 | | | 280 | | | 280 | | | 280 | | |
| Electrical & Lighting Systems | | | | | | | | | | |
| Electrician | | 360 | | 360 | | 360 | | 360 | | 360 |
| Buildin Automation Systems | | | | | | | | | | |
| Controls Technician | | 240 | | 240 | | 240 | | 240 | | 240 | |
| Total Elec&Light Sys Labor | | 600 | | 600 | | 600 | | 600 | | 600 |
| HVAC/Mechanical | | | | | | | | | | |
| HVAC Tech | | 360 | | 360 | | 360 | | 360 | | 360 |
| Electrician | | 240 | | 240 | | 240 | | 240 | | 240 |
| Building Automation Systems | | | | | | | | | | |
| Controls Technician | | 240 | | 240 | | 240 | | 240 | | 240 | |
| Sheet Metal Worker | | 240 | | 240 | | 240 | | 240 | | 240 |
| Plumber / Pipefitter | | 240 | | 240 | | 240 | | 240 | | 240 |
| Total HVAC/Mech Labor | | 1320 | | 1320 | | 1320 | | 1320 | | 1320 |
| Electrical Distribution (Site) | | | | | | | | | | |
| Electrician | | 360 | | 360 | | 360 | | 360 | | 360 |
| Building Automation Systems | | | | | | | | | | |
| Controls Technician | | 240 | | 240 | | 240 | | 240 | | 240 | |
| Total Elec Dist (Site) Labor | | 600 | | 600 | | 600 | | 600 | | 600 |
| Cyber Security | | | | | |
| Cybersecurity / Systems Engineer | 20 | 20 | 20 | 20 | 20 |
| Application Admin | 20 | 20 | 20 | 20 | 20 |
| Total Cyber Security Labor | 40 | 40 | 40 | 40 | 40 |
Total Ad-Hoc Labor
| Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Total Mat + |
| Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat OH |
| Ad-Hoc Material Estimate | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | |
| Base | Opt Yr 1 | Opt Yr 2 | Opt Yr 3 | Opt Yr 4 | 5 Yr Total |
| Total Labor&Mat Cost | | | | | | |
| Note: |
| For Ad-Hoc Labor: Contractor is required to use Routine Maintenance labor (at no additional cost to the Gov't) if possible |
| For Ad-Hoc Material: Contractor is required to obtain and submit 3 bids for all material costs. |
Ad-Hoc San Joaquin Non-Routine / Ad-Hoc Labor and Material Costs
Location: San Joaquin, CA
| Base Year | | | Option Year #1 | | | Option Year #2 | | | Option Year #3 | | | Option Year #4 | | | 5 Year |
| Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Est. | Total |
| Grouping / Labor Category | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | Labor Rate | # of Hours | Labor Cost | |
| Elevator | | | | | | | | | | | | | | | | |
| Elevator Mechanic | | 250 | | | 250 | | | 250 | | | 250 | | | 250 | | |
| Total Elevator Labor | | 250 | | | 250 | | | 250 | | | 250 | | | 250 | | |
| Electrical & Lighting Systems | | | | | |
| Electrician | 2080 | 2080 | 2080 | 2080 | 2080 |
| Total Elec&Light Sys Labor | 2080 | 2080 | 2080 | 2080 | 2080 |
| HVAC/Mechanical | | | | | |
| HVAC Mechanic | 5880 | 5880 | 5880 | 5880 | 5880 |
| Total HVAC/Mech Labor | 5880 | 5880 | 5880 | 5880 | 5880 |
| Electrical Distribution (Site) | | | | | |
| High Voltage Mechanic | 400 | 400 | 400 | 400 | 400 |
| Total Elec Dist (Site) Labor | 400 | 400 | 400 | 400 | 400 |
| Potable Water / Wastewater | | | | | |
| WW WT Plant Operator | 6240 | 6240 | 6240 | 6240 | 6240 |
| Total Pot/Wastewater Labor | 6240 | 6240 | 6240 | 6240 | 6240 |
| Cyber Security | | | | | |
| Cyber Labor | 380 | 380 | 380 | 380 | 380 |
| Total Cyber Security Labor | 380 | 380 | 380 | 380 | 380 |
Total Ad-Hoc Labor
| Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Est. | Mat. | Est. | Total Mat + | Total Mat + |
| Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat. Cost | OH rate | Mat OH | Mat OH | Mat OH |
| Ad-Hoc Material Estimate | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | $2,000,000.00 | | | | |
| Base | Opt Yr 1 | Opt Yr 2 | Opt Yr 3 | Opt Yr 4 | 5 Yr Total |
| Total Labor&Mat Cost | | | | | | |
| Note: |
| For Ad-Hoc Labor: Contractor is required to use Routine Maintenance labor (at no additional cost to the Gov't) if possible |
| For Ad-Hoc Material: Contractor is required to obtain and submit 3 bids for all material costs. |