J-1

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

SPECIAL CONTRACT REQUIREMENTS

Project NP-DEWA 14(18), 121(1)

DELAWARE WATER GAP NATIONAL RECREATION AREA

The following Special Contract Requirements amend and supplement the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14), U. S. Department of Transportation, Federal Highway Administration.

J-2

Section 101. — TERMS, FORMAT, AND DEFINITIONS

101.03(a). Add the following:

DEWA — Delaware Water Gap National Recreation Area

NECA — National Electrical Contractors Association

NFPA — National Fire Protection Association

NPS — National Park Service

101.03(b). Add the following:

dB(A) — a-weighted decibel loudness of sound

Section 104. — CONTROL OF WORK

104.03(c). Delete the first sentence of the first paragraph and substitute the following:

Furnish one full-size (24-inch by 36-inch) paper copy of the plans from the Government-provided electronic plans, and use this set of plans exclusively for as-built drawings.

104.05. Add the following:

When hauling on NPS roads, do not exceed the load restrictions shown in Table 104-1.

Table 104-1 Load Restrictions

Single Units Gross Vehicle Weight, pounds

2 axles 66,000 3 axles 72,000 4 or more axles 80,000

Where the ground is saturated with water or during periods of freezing and thawing, the CO may impose further load restrictions or suspend hauling.

Hauling will only be permitted from the nearest point of public access to the work site.

Minimize hauling over completed pavement.

J-3

Add the following after Subsection 104.05:

104.06 Commercial Vehicle Restrictions. Ensure that all commercial vehicle operators, including the Contractor, Contractor employees, and any subcontractors, have the following documentation or form(s):

(a) Name and address of the company (or independent) owning the vehicle.

(b) Registration of the vehicle, operator's license, and leasing papers if applicable.

(c) Exact location (street address and town or township preferred) of delivery, pickup, or service prior to or immediately following the trip on U.S. Route 209 as documented by one or more of the following:

(1) Bill of lading.

(2) Delivery or pickup order.

(3) Service or work order.

(4) Manifest.

(5) Pay card or sheet.

(6) Trip ticket.

(7) Sales slip.

(8) Route sheets.

(9) Logbook.

(d) Current date. List the dates of the job, for a period of up to one month, if the service will be performed over a period of time on the paperwork. Paperwork will not be accepted for a range exceeding one month or past the date(s) listed.

Do not present handwritten additions to typed documentation.

Obtain documentation form from the CO. Complete documentation form and provide copy of form to the CO.

Keep NPS form “Contractor Template” inside vehicles at all times. Provide documentation when asked by a patrol ranger as proof of authority to access U.S. Route 209 and work inside DEWA. The presentation of this paperwork does not guarantee access to U.S. Route 209 within

DEWA.

J-4

Provide proof of Pennsylvania Department of Agriculture spotted lanternfly permit training and exam. Designate a person to train all workers and maintain a record of who has been trained.

Place a permit in each vehicle, along with documentation to show that inspections and countermeasures are being performed. Submit this documentation to the CO for approval.

Section 105. — CONTROL OF MATERIAL

105.01. Add the following:

Provide the CO a 2-week notice to inspect material and source prior to bringing material on Government property.

Sourcing and movement of materials from spotted lanternfly quarantine areas is prohibited.

Use fill material or topsoil found on-site. If any additional fill material or topsoil is required from outside the project limits, obtain approval from the CO for the source of the material.

Section 107. — LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

107.01. Add the following:

Provide copies of all permit applications and signed permits (with permit conditions) at least one week prior to start of work.

107.02. Add the following to the third paragraph:

Do not remove, injure, or destroy trees or other plants without prior approval from the CO. Do not fasten ropes, cables, or guys to existing trees. Remove roots and branches that interfere with construction only as approved by the CO. Confine all operations to work limits of the project.

Prevent damage to natural surroundings. Minimize ground disturbance to the maximum extent possible. Restore damaged areas. Carefully supervise excavating, grading, filling and other construction operations near trees to prevent damage. Do not perform work within drip area of any tree designated to remain unless approved by the CO.

For the full duration of construction, protect the existing trees that are tagged by the CO in the following manner:

(a) Install and maintain a temporary fence around the perimeter of the root protection area according to Subsection 619.06. The root protection area is defined as an area equal to 10 feet outside the dripline. Do not adjust the alignment of the protection area unless approved by the CO.

(b) Do not perform construction activities within the root protection area unless approved by the CO. Do not store or locate construction materials, vehicles, staging areas, topsoil, J-5 disposal areas, or trailers within the root protection area. Protect the area from flooding, erosion, sedimentation, and potentially harmful materials through run-off or spillage.

(c) Remove all tree protection when approved by the CO.

Penalties for tree damage or destruction will be assessed according to Subsection 107.02A.

107.02. Add the following to the fourth paragraph:

Inform all workers of the criminal penalties for illegally collecting or intentionally damaging any archaeological or historical property, including previously unknown resources potentially uncovered during construction activities. Discuss at the preconstruction meeting the correct procedures to follow once a finding is made. The CO will assess penalties according to the Archaeological Resources Protection Act of 1979, Section 6, found at https://www.nps.gov/archeology/tools/laws/ARPA.htm.

Perform archaeological monitoring according to Subsection 107.02B.

107.02. Add the following to the sixth paragraph:

Notify the CO in writing at least 48 hours in advance of any scheduled utility shutdown, investigation, or any related work.

107.02. Add the following:

Protect soil against erosion and topsoil depletion. Restore staging areas or any disturbed areas to their original condition. At the direction of the CO, restore any turf or trees disturbed during construction according to Sections 625 and 626.

https://www.nps.gov/archeology/tools/laws/ARPA.htm

J-6

Add the following after Subsection 107.02:

107.02A Penalties for Tree Damage or Destruction. Penalties for tree damage or destruction will be assessed according to the following:

(a) Tree destruction. Destruction of a tree will result in a reduction in payment to the Contractor equal to $1,033.00 per square inch of trunk area (determined by area measured by diameter at 5 feet above the ground). If any trees are destroyed, an NPS representative will inspect the damage and take appropriate measures. Destruction of a tree will apply if any of the following occurs:

(1) Any of the buttress root is debarked.

(2) 20 percent or more of the root protection area is impacted by equipment or stockpiled materials.

(3) Wound(s) to the tree trunk measure 20 percent or more of the total circumference of the tree.

(b) Tree damage. Damage of a tree will result in a reduction in payment to the Contractor equal to $25.00 per wound on the trunk below the 7-foot level and $40.00 per wound at or above the 7-foot level. If any trees are damaged, an NPS representative will inspect the damage and take appropriate measures. A tree will be considered damaged if it suffers wounds to the trunk of less than 20 percent of the total circumference of the tree.

(c) Limb or branch damage. Damage of any limbs or branches on a tree will result in a reduction in payment to the Contractor equal to $45.00 per limb and branch. If any limbs or branches are damaged, an NPS representative will inspect the wound and take appropriate measures. A limb or branch will be considered damaged if it suffers wounds to the trunk of less than 20 percent of the total circumference of the branch.

Reduction in payments will be subtracted from the Contractor’s progress payments and will be unrecoverable.

107.10(b). Delete the first paragraph and substitute the following:

Submit a “Spill, Prevention, Control, and Countermeasure (SPCC) Plan” at least 7 days before beginning work according to Subsection 157.04B.

107.10(c). Delete the Subsection and substitute the following:

(c) Dirt, plant, and foreign material. Ensure that all vehicles and equipment entering DEWA are clean of soil, mud, vegetation, seeds, and other debris that could contain or hold seeds; and free from oil leaks. All vehicles are subject to inspection. Clean vehicles and equipment offsite. Show attention to the under carriage and any surface where soil containing exotic seeds may exist like cracks, crevices, and tire treads. These efforts are

J-7 critical to prevent the introduction and establishment of non-native plant species into the project area.

Wash all construction equipment with a high-pressure washing method to thoroughly remove all dirt, plant, and other foreign material prior to entering DEWA. Use a minimum water pressure of 90 pounds per square inch for vehicle cleaning.

Notify the CO at least 2 days prior to moving any equipment into DEWA and the equipment’s most recent operations. Arrange for the CO to inspect each piece of equipment before entering DEWA. The CO will maintain records of inspections. Equipment found operating on the project that has not been inspected, or has oil leaks, will be shut down and subject to citation.

107.10. Add the following:

(e) Noise and acoustics. Perform operations to minimize noise. Perform noise producing work in less sensitive hours of the day or week as directed by the CO. Operate power equipment in accordance with local noise restrictions and according to Table 107-1.

Operating audio devices that exceed 60 decibels is prohibited.

Do not exceed the following dB(A) limitations at 50 feet:

(1) 70 dB(A) for more than 12 minutes in any hour.

(2) 80 dB(A) for more than 3 minutes in any hour.

J-8

Table 107-1 Maximum Permissible Construction Equipment Noise Levels at 50 Feet

Equipment dB(A) Backhoes 75

Compressors 75 Concrete Mixers 75 Concrete Pumps 75

Cranes 75 Derricks Impact 75

Dozers 75 Front Loaders 75

Generators 75 Graders 75

Jack Hammers 75 Pavers, Stationary 80

Pile Drivers 95 Pneumatic Tools 80

Pumps 75 Rock Drills 80

Saws 75 Scrapers 80 Tractors 75 Trucks 75

Vibrators 75

Assess potential effects of construction noise on adjacent neighbors and DEWA visitors in accordance with ASTM E1686. Monitor noise produced from construction operations in accordance with ASTM E1780.

107.11. Add the following:

Do not use DEWA waterbodies and wetlands as a water source for construction activities.

Syphoning is expressly prohibited. Use only potable water from outside DEWA for all project work.

Conduct project operations to ensure the least inconvenience to the NPS employees and DEWA visitors. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.

J-9

Add the following after Subsection 107.11:

107.12 Temporary Fire Protection. Install and maintain temporary fire protection facilities of the types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241 and the following:

(a) Responsible person. Designate a capable and qualified person to be in charge of fire protection. The responsibilities include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.

(b) Smoking. Do not smoke in buildings or within 20 feet of entrances, operable windows, or outdoor air intakes within boundaries of DEWA.

(c) Supervision. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.

(d) Hazard control. Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in structures. Provide adequate ventilation during use of volatile or noxious substances.

(e) Spark arresters. Equip all gasoline or diesel-powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the CO.

(f) Fire extinguishers. Equip each vehicle or piece of equipment with one portable, UL rated fire extinguisher, with class and extinguishing agent as required by location and classes of fire exposers.

107.13 Waste Management. Prepare and implement a waste management plan and submit to the CO for approval. Provide handling, containers, storage, signage, transportation, and other items as required to implement the waste management plan during the entire duration of the contract.

Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

Use construction practices that achieve the most efficient use of resources and materials.

Employ processes that ensure the generation of as little waste as possible due to over packaging, error, poor planning, breakage, mishandling, contamination, or other factors. Reuse, salvage, or recycle as many of the waste materials as economically feasible. Minimize waste disposal in landfills.

Check the job site at the end of each day to remove trash, food, and food related items and dispose of them in an appropriate receptacle.

J-10

Designate a specific area or areas for the operations of each trade to facilitate separation of materials for potential reuse, salvage, recycling, and return.

Stockpile processed materials on-site but away from the construction area without intermixing with other materials. Do not store within the dripline of trees. Store components off the ground and protect from the weather.

Comply with the following:

(a) Recycle. Separate recyclable waste from other waste materials, trash, and debris.

Separate recyclable waste by type at the project site to the maximum extent practical.

Establish contacts with local recycling and reuse companies to set up the lines of responsibility. Coordinate with these companies in terms of identifying materials, pickup schedules, and standard quality for recycled materials. Handle, store, and transport recyclables in a manner that meets the requirements set by the designated facilities for acceptance.

Place waste and recycling bins near each other and close to the point of waste generation but out of the traffic pattern. Keep waste and recycling bins neat and clean. Include a list of acceptable and unacceptable materials at each container and bin. Protect bins during non-work hours from off-site contamination. Periodically check the garbage dumpsters for recyclables being thrown away. Protect materials to be recycled from contamination.

Inspect containers and bins for contamination and remove contaminated materials if found.

Document material and quantities that are recycled and provide the CO with a copy of the documentation.

Materials to be recycled include but are not limited to the following:

(1) Cardboard, paper, packaging;

(2) Clean dimensional wood, palette wood;

(3) Beverage containers;

(4) Land cleaning debris;

(5) Concrete;

(6) Metals, wood trim, rebar, aluminum, copper, zinc, lead, brass, and bronze;

(7) Paint;

(8) Rigid foam; and

J-11

(9) Plastics.

(b) Salvage. Handle materials to be salvaged based on the following:

(1) Clean salvaged items;

(2) Pack or crate items. Identify contents of containers;

(3) Store items in a secure area until installation;

(4) Protect items from damage during transport and storage;

(5) Install salvaged items to comply with installation requirements for new materials and equipment. Provide connections, supports, and other materials necessary to make items functional for use intended; and

(6) Do not sell salvaged items on the project site.

Dispose of all materials unsuitable for salvage, recycling, or reuse according to Subsection 203.05(a).

107.14 Vehicles and Equipment. Submit a list of equipment to be used at each site for review and approval. Include the equipment name, make, model, and year of the equipment. Include if the equipment is rented or owned by contractor. No equipment larger than a small excavator and a small skid steer shall be used at Adams Creek. If the contractor feels it is necessary to use larger equipment to complete the contract work, they shall submit in writing, the equipment name, make, model, and year of equipment prior to using it on the project. They shall state why it is deemed necessary to use this piece of equipment. Submit this information to the CO for review and approval before mobilizing equipment to the project site.

Avoid soil compaction from heavy equipment to surrounding area by keeping equipment inside the limits of work of the project. If work outside the limits is necessary, perform the work only when the soil is dry. After work is completed, rip or decompact soils to enable vegetation to grow. Return all disturbances to grade and rake out and seed any tracks from equipment.

Do not allow vehicles or equipment inside the water.

Section 108. — PROSECUTION AND PROGRESS

108.01. Add the following:

Construction operations are limited as follows:

(a) No work will be permitted on Saturdays, Sundays, or National legal holidays.

J-12

(b) No cutting of trees greater than 3 inches diameter at breast height will be permitted from April 1 to November 15.

(c) No in-stream construction will be permitted during the following periods and locations:

• October 1 to December 31 at Conashaugh Creek, Bushkill Creek, and Adams Creek.

• October 1 to April 1 at Toms Creek.

• April 1 to June 15 at Bushkill Creek.

If the Contractor finds it necessary to work on a Saturday or National legal holiday, request approval from the CO at least 48 hours before the planned work. Do not request Sunday work.

Do not work at more than one bridge at a time.

108.03(c). Add the following:

Under FAR Clause 52.249-10, Default (Fixed-Price Construction), the Contractor can request a time extension for a delay due to unusually severe weather as defined under Section

155. If a time extension is requested for unusually severe weather, submit a time impact analysis according to Subsection 108.03(b) and include supporting historical weather data according to Subsections 155.04A and 155.04B. The following criteria will be used for determining a time extension for unusually severe weather:

(1) Time adjustment for rain delays. If the net number of actual workdays lost to rain is less than the total lost days for the month in question, then no time adjustment will be made. If the net number of actual workdays lost to rain is more than the total lost days for the month in question, then a time extension may be granted.

(2) Time adjustment for other weather delays. If a time extension is requested for other unusually severe weather conditions such as snow, extreme cold or heat, high winds, etc., follow the same calculation, submittal, and criteria procedures as outlined for rain delays.

Section 109. — MEASUREMENT AND PAYMENT

109.08(a). Add the following:

Full or partial progress payment will be withheld until the SWPPP is brought into compliance and approved by the CO.

109.08(b). Add the following:

Submit invoices by the 7th day after the closing date. Invoices received after the 16th day following the closing date will not be accepted for payment processing that month. Include late, unprocessed invoice submittals in the following month’s invoice.

J-13

109.08(c). Add the following:

The Government’s designated billing office is:

Federal Highway Administration Eastern Federal Lands Highway Division Loudoun Tech Center 21400 Ridgetop Circle Room 200 Sterling, Virginia 20166-6511

ATTN: CONSTRUCTION OFFICE

Section 152. — CONSTRUCTION SURVEY AND STAKING

152.04. Delete the last sentence of the eighth paragraph and substitute the following:

Reestablish any missing initial reference lines, control points, and stakes set by the Government.

152.05. Add the following:

(m) Preconstruction survey. Perform survey of areas to be excavated prior to beginning excavation work as directed by the CO. Do not start excavation work until preconstruction survey has been completed.

Section 154. — CONTRACTOR SAMPLING AND TESTING

154.01. Add the following:

This work includes furnishing personnel to perform monitoring and other duties.

154.02. Add the following:

Submit proposals for using alternate AASHTO or state department of transportation approved test methods in writing for approval. Alternate methods may be allowed based on documented equivalence to the method specified.

Add the following after Subsection 154.02:

154.02A Archaeological Monitoring. Perform archaeological monitoring at Adams Creek and Bushkill Creek in order to identify any previously undocumented archaeological deposits.

Provide proof of qualifications and prior experience to the CO for approval at least 14 days prior to starting any ground disturbing activities. No work may be performed on-site until qualifications and experience for the qualified archaeologist have been submitted and approved

J-14 by the CO. Provide a qualified archaeologist to monitor all clearing, grubbing, grading, excavating, and other ground disturbing activities, including temporary access and staging areas.

This includes but is not limited to, rockery wall installation, bridge work, tree planting, fence installation, and excavation work. Submit a work schedule detailing daily construction work activities to the CO for review by the NPS cultural resource specialist. Do not start any earth disturbing activities unless the archaeological monitor is present. If the archaeological monitor discovers deposits, stop all construction work in the immediate area, secure the area, and notify the CO immediately. Do not resume work in the affected area until directed by the CO.

Perform limited archaeological testing as part of the archaeological monitoring of the excavation for the Adams Creek rockery wall. Remove soils by stratigraphic layer and place them on the top of the bank so the archaeological monitor can screen the soil for artifacts. Record a stratigraphic profile of exposed soils after the creek bank is excavated. Provide a weekly summary of the monitoring results to the CO. Include field notes, photographs, stratigraphic profile, and other associated documentation.

Ensure that monitoring is consistent with the following:

(a) Pennsylvania Historical and Museum Commission guidelines, found at https://www.phmc.pa.gov/Pages/default.aspx;

(b) Secretary of the Interior’s Standards and Guidelines for Archaeological Documentation (48 Fed. Reg. 44716, September 29, 1983), found at https://www.nps.gov/history/local-law/arch_stnds_7.htm;

(c) Secretary of the Interior’s Standards and Guidelines for Archaeology and Historic Preservation (48 Fed. Reg. 44716, September 29, 1983), found at https://www.nps.gov/history/local-law/arch_stnds_0.htm;

(d) Advisory Council of Historic Preservation publications, Recommended Approach for Consultation on Recovery of Significant Information from Archaeological Sites (1999.

Updated 2002), found at https://www.achp.gov/digital-library-section-106-landing/recommended-approach-consultation-recovery-significant; and

(e) Section 106 Archaeology Guidance (January 1, 2009), found at https://www.achp.gov/sites/default/files/guidance/2017- 02/ACHP%20ARCHAEOLOGY%20GUIDANCE.pdf.

Perform all archaeological monitoring activities either by, or directly supervised by, professionals meeting the qualification standards in the Secretary of Interior’s Professional Qualification Standards (36 CFR 61, Appendix A), found at https://www.nps.gov/history/local-law/arch_stnds_9.htm.

154.03. Add the following:

Deliver the Government’s portion of the sample or split sample in an acceptable container https://www.phmc.pa.gov/Pages/default.aspx https://www.nps.gov/history/local-law/arch_stnds_7.htm https://www.nps.gov/history/local-law/arch_stnds_7.htm https://www.nps.gov/history/local-law/arch_stnds_0.htm https://www.achp.gov/digital-library-section-106-landing/recommended-approach-consultation-recovery-significant https://www.achp.gov/digital-library-section-106-landing/recommended-approach-consultation-recovery-significant https://www.achp.gov/sites/default/files/guidance/2017-02/ACHP%20ARCHAEOLOGY%20GUIDANCE.pdf https://www.achp.gov/sites/default/files/guidance/2017-02/ACHP%20ARCHAEOLOGY%20GUIDANCE.pdf https://www.nps.gov/history/local-law/arch_stnds_9.htm https://www.nps.gov/history/local-law/arch_stnds_9.htm

J-15 suitable for shipment to the CO.

154.06. Add the following:

Archaeological monitoring will be evaluated under Subsection 106.02.

154.08. Add the following:

Progress payments for archaeological monitoring will be paid as follows:

• 25 percent of the pay item amount will be paid upon approval of the archaeologist.

• An additional 60 percent of the pay item amount will be prorated based on work complete at Adams Creek and Bushkill Creek.

• The remaining portion of the pay item amount will be paid after final acceptance.

Section 155. — SCHEDULES FOR CONSTRUCTION CONTRACTS

155.02. Add the following:

(g) Reasonably predictable weather. The number of workdays that can expect to be lost in any month due to rainfall based on 10-year historical weather data.

(h) Rain day. A potentially lost workday on which rainfall is equal to or greater than 0.10 inches.

(i) Drying day. A workday immediately following a rainfall equal to or greater than 1.00 inch which is potentially lost because of wet ground conditions.

(j) Workday. A day not excluded from work by Section 108.

(k) Unusually severe weather. When the number of actual workdays lost is greater than the reasonably predictable weather for a specific month.

J-16

155.04(f). Add the following:

If a subcontract has not yet been awarded for a certain portion of the work, include the schedule for that work.

155.04. Add the following:

(j) A completed Table 155-1 prepared according to Subsection 155.04A.

Add the following after Subsection 155.04:

155.04A Reasonably Predictable Weather. Determine reasonably predictable weather for this contract by completing Table 155-1. Calculate data for Table 155-1 by computing the average number of workdays lost (rain days plus drying days) for each month and the standard deviation from the average, using the last 10 years of historical weather data from the nearest National Oceanic and Atmospheric Administration (NOAA) weather data collection station. Add the average number of workdays lost to the standard deviation. The total number of lost days (average workdays lost plus 1 standard deviation, rounded to whole days) will be considered normal for each month.

155.04B Unusually Severe Weather. If requesting a time extension due to unusually severe weather, calculate the number of actual workdays lost by totaling the actual rain days plus the actual drying days occurring in the month in question. From this total, deduct any workdays meeting any one of the following conditions:

(a) The rain day or drying day occurred on a non-work weekday such as a holiday.

(b) The rainfall occurred at a time when no weather dependent work was in progress or occurred during planned or unplanned shutdowns due to other circumstances such as equipment failure, strikes, material supplies, delays, etc.

(c) The Contractor was still working or able to work on weather dependent activities to the extent that less than 50 percent of the workday was lost due to weather.

If the net number of actual workdays lost is greater than the total lost days, then unusually severe weather occurred during the month in question.

J-17

Table 155-1 Reasonably Predictable Weather

Project Number:

Project Location:

NOAA Station Location:

Data Years (10-year history):

Month Average

Workdays Lost

Standard Deviation

Total Lost Days

January February March April May June July August September October November December

155.05. Delete the first sentence and substitute the following:

Prepare and submit a Bar Chart Method (BCM) initial construction schedule.

155.05(a)(1)(c). Add the following:

Include unreflected items, or components of work within a pay item, as separate activities as directed by the CO.

155.06. Delete the first sentence of the second paragraph and substitute the following:

Unless previously approved by the CO, changes to the construction schedule for work that is still to be completed can only be changed with a time impact analysis according to Subsection 108.03, and a Baseline Construction Schedule revision according to Subsection 155.07.

155.07. Delete the third sentence and substitute the following:

Continue to submit monthly schedule updates according to Subsection 155.06 until a baseline construction schedule revision is approved.

J-18

Section 156. — PUBLIC TRAFFIC

156.04. Delete the first paragraph and substitute the following:

Accommodate traffic according to the MUTCD, contract traffic control plan, Section 635, and this Section. An alternate traffic control plan may be submitted for approval in accordance with Subsection 104.03 and the following:

(a) Ensure safe and efficient pedestrian, bicycle, and vehicular traffic (including emergency vehicles) at all times during construction;

(b) Schedule and perform work to minimize disruption to public traffic; and

(c) Accommodate the construction operations as approved under Section 155.

Submit alternate traffic control plans at least 30 days before its intended use. After the initial traffic control plan is approved, revise it as necessary to accommodate approved changes in the construction schedule. Submit the revised traffic control plan at least 14 days before implementation, unless otherwise approved by the CO.

156.04. Add the following:

Use single lane closures with temporary traffic signals for the work at Adams Creek Bridge, Bushkill Creek Bridge, and Toms Creek Bridge according to Section 635 and as shown in the plans.

Install portable changeable message signs according to Section 635 and as shown in the plans or as directed by the CO, at least 7 days before beginning the rockery wall work on Adams Creek Bridge. Remove portable changeable message signs after the rockery wall work is completed.

Close the south entrance of Zimmerman Road access from U.S. Route 209 to traffic during construction as approved by the CO. Open roadway within 24 hours after completion of work or as directed by the CO.

Do not close U.S. Route 209 to traffic during construction, except for the rockery wall work on Adams Creek Bridge. Limit the closure for this work to a period of no more than 2 weeks.

Coordinate scheduling of road closures on U.S. Route 209 with the CO. Before performing the road closure, contact the following at least 2 weeks and again at least 24 hours prior to the setup of any traffic control:

(a) PennDOT District 4 Press Office at (570) 963-4044;

(b) PennDOT District 4 Traffic Management Center at (570) 963-4058;

(c) Local emergency units including, but not limited to police, fire services, and medical

J-19 services; and

(d) If the detour is to be in place during the school year, contact the applicable school districts.

Contact these services again when the road is open to unrestricted traffic.

Do not perform single lane closures or full road closures on U.S. Route 209 while Dingmans Bridge, located on Dingmans Falls Road off U.S. Route 209, is closed for maintenance.

156.05(f). Add the following:

Ensure that drains and inlets within the project limits are fully functional throughout the duration of the project.

156.07(d). Add the following:

Obtain approval from the CO at least 7 days before using any location for staging that is not already shown in the plans. Confine staging and parking of vehicles, equipment, and materials to paved pull-offs, parking areas, gravel areas, and other disturbed areas as approved by the CO. Coordinate the location of additional construction staging areas in consultation with the CO. Provide a plan indicating where the alternate staging area is being requested and the proposed mitigation for disturbance. Provide the staging plan 7 days prior to the preconstruction conference.

Long-term placement of equipment requires additional clearance. Store materials and equipment on site at the Contractor’s own risk.

Restore staging areas to their original condition as directed by the CO.

156.07(i). Delete the Subsection and substitute the following:

(i) Limit construction-caused delays to public traffic to a maximum of 10 minutes per passage through the project; and

156.08. Delete the text of the first paragraph and substitute the following:

Perform construction operations during the hours of 7:00 a.m. to 5:00 p.m. unless otherwise specified or approved by the CO.

Nighttime operations are only permitted for the rockery wall construction on Adams Creek Bridge from 9:00 p.m. to 5:00 a.m.

Operations from 5:00 a.m. to 7:00 a.m. are not permitted.

J-20

156.08. Add the following to the second paragraph:

Position the lights downwards.

156.09. Add the following:

Provide a full-time traffic control supervisor exclusively for the project. Ensure the traffic control supervisor is on the site at all times when work is being performed and available during non-work periods.

Section 157. — SOIL EROSION AND SEDIMENT CONTROL

157.01. Add the following:

This work includes updating and maintaining a SWPPP.

157.04. Add the following:

This project is covered under the General Permit BWEW-GP-11, BWEW-GP-8, and BWEW-

GP-3.

Update the Government-provided draft SWPPP, also referred to as the Erosion and Sediment Control Plan, in accordance with the EPA and 25 Pennsylvania Code Chapter 102 using the information provided in the plans, specifications, and permits obtained for the project. Submit an electronic copy of the SWPPP to the CO at least 7 days before the preconstruction conference in accordance with Subsection 104.03 for approval.

For the SWPPP, include an updated Erosion and Sediment Control Plan, a Stream Diversion and Dewatering Plan, a Spill Prevention Control and Countermeasure Plan, and a Flood Contingency Plan.

Update the Erosion and Sediment Control Plan from the contract plans to adjust the footprint of temporary diversion berms, if necessary.

Update the SWPPP constantly throughout the project as work is performed and when changes are made to the project. Maintain a copy of the current SWPPP on-site at all times.

J-21

Add the following after Subsection 157.04:

157.04A Stream Diversion and Dewatering Plan. Prepare a Stream Diversion and Dewatering Plan that includes the following:

(a) Type, size, location, elevation, and method of installation and removal of temporary diversion berms, and means of access;

(b) Sequence and schedule for dewatering and re-watering;

(c) Timing of installation and removal, duration of placement;

(d) How pumped water from dewatering will be treated before it is discharged including identifying the location of soil erosion and sediment control devices;

(e) Best management practices to ensure no erosion or turbidity occurs; and

(f) How to protect stream water quality during removal of stream debris during construction of temporary diversion berms.

157.04B Spill Prevention, Control, and Countermeasures Plan. Prepare a Spill Prevention, Control, and Countermeasures Plan that includes the following:

(a) A list of potential pollutants including trade material, chemical/physical description, stormwater pollutants, and list of pollution prevention practices to be used;

(b) Location of potential pollutants;

(c) List of any non-stormwater discharges;

(d) Procedures and practices to address fuels and oils, solid waste, fertilizers/nutrient application, paint, concrete, water testing, and offsite vehicle tracking; and

(e) Spill prevention and response procedures including a list of contact information and reporting requirements for unauthorized discharges and spills.

157.04C Flood Contingency Plan. Prepare a Flood Contingency Plan that includes the following:

(a) Procedures for protecting DEWA resources from impacts due to spills, runoff, and equipment during a flood event;

(b) Methods for contacting the Contractor in cases of emergency including Contractor’s on-site personnel, any subcontractors, and any other off-site person’s emergency contact information;

J-22

(c) Methods for determining when a threat of flooding exists;

(d) Procedures for notifying the CO, on-site personnel, any subcontractors, DEWA, and any other off-site persons that require notification and emergency contact information for those individuals;

(e) Procedures to remove from flood prone areas and protect from flood damage all construction materials which are not anchored, restrained, or otherwise secured to the greatest extent possible;

(f) Procedures to implement additional measures necessary to prevent the migration of sediment from unstable areas of the project site; and

(g) Procedures to address the site after a flood event and identify and mitigate any damage sustained.

157.10. Add the following:

(a) Temporary diversion berm. Construct the temporary diversion berm with a minimum height of 6 inches above the level of the diverted water at the time of construction. Pump water as needed from the work area into filter bags.

For imported material needed for access to construct temporary diversion berm on Bushkill Creek, provide washed riprap or rock conforming to AASHTO M 43 greater than 3 inches with no fines.

To remove the temporary diversion berm, make a small opening to allow water to slowly seep into the work zone. Allow sediment to settle or pump sediment-laden water into filter bags. When the water inside the work area is clear, remove the temporary diversion berm.

No stream diversion will be permitted during the periods listed in Subsection 108.01.

(b) Filter bag. Do not place filter bags in any location where a failure would result in sediment being released into any stream or wetlands.

Set the maximum pumping rate at no greater than 750 gallons per minute or half the maximum rate as specified by the filter bag manufacturer, whichever is less. Pumping rates will vary depending on the size of the filter bag and the type and amount of sediment discharged to the water filtration bag. Adjust the pump intake so that it is floating and screened.

Insert the pump discharge hose into the filter bag as specified by the manufacturer and clamp securely.

Dispose of filter bags according to Subsection 203.05(a).

J-23

157.11. Add the following:

(g) On-site concrete washout structure. Submit a plan for location of the structure to the CO for approval. Construct structure as shown in the plans. Clean tools, mixer chutes, and rear of vehicles before exiting the project site. Washing of the drum and vehicle washing on-site is prohibited.

157.12(a). Delete the Subsection and substitute the following:

(a) Temporary cover. Use cover crop as temporary seed mix placed according to Section 625 or topsoil placed according to Section 624 for soil areas disturbed longer than 2 weeks.

157.12(b). Add the following:

Apply temporary turf establishment for areas where additional soil disturbance is anticipated for a period longer than 14 days or as directed by the CO. Apply temporary turf establishment between March 15 and October 15, and according to Section 625.

Add the following after Subsection 157.13:

157.13A Stabilized Construction Exits. Construct stabilized construction exits where construction vehicles will access a work area from a public roadway or as directed by the CO.

Stake the limits of construction exits and access roads for CO approval prior to any clearing, grubbing, or tree removal. Do not exceed 12 feet in width for construction entrances and access roads. Do not excavate when constructing stabilized construction exits.

Submit a proposal for providing access to the rockery wall work on Adams Creek Bridge to the CO for approval.

Construct all stabilized construction exits before any instream work is performed.

157.16. Add the following:

The SWPPP will be evaluated under Subsection 106.02. The SWPPP will be jointly reviewed for accuracy and completeness by the CO and the Contractor before the submission of each monthly invoice. If the review finds that the SWPPP is not in compliance, payment of the Contractor’s invoice will be withheld until the SWPPP is brought up to date as outlined in Subsection 109.08(a).

157.17. Delete the second paragraph and substitute the following:

Do not measure temporary turf establishment for payment.

Do not measure riprap and rock used for temporary diversion berm construction access for payment.

J-24

157.18. Add the following:

Progress payments for updating and maintaining a SWPPP will be paid as follows:

• 25 percent of the pay item amount will be paid upon acceptance of the SWPPP.

• An additional 50 percent of the pay item amount will be prorated based on total work complete.

• The remaining portion of the pay item amount will be paid at final acceptance.

Section 201. — CLEARING AND GRUBBING

201.03. Add the following:

Remove all suitable soil, organic duff, and material capable of supporting vegetation according to Subsection 204.05 and place as conserved topsoil according to Section 624.

Section 202. — ADDITIONAL CLEARING AND GRUBBING

202.03. Add the following:

Flag the trees that require removal. Obtain approval from the CO prior to tree removal.

Section 203. — REMOVAL OF STRUCTURES AND OBSTRUCTIONS

203.04(b). Add the following:

Remove downed tree trunks within the stream.

203.05(a). Add the following:

Cut tree trunks and limbs into manageable lengths when possible to promote decay, then scatter into forested areas away from trails, roads, and parking areas. Avoid piles as much as possible. Treat debris to blend with the surrounding forest and not be readily apparent to DEWA visitors.

Use wood chippers as directed by the CO. Do not exceed a depth of 2 to 3 inches of mulch.

203.05(b). Delete the Subsection and substitute the following:

(b) Burn. Burning is prohibited.

J-25

203.05(c). Delete the Subsection and substitute the following:

(c) Bury. Burying debris is prohibited.

Section 204. — EXCAVATION AND EMBANKMENT

204.04. Add the following:

For excavation work at Bushkill Creek Bridge, perform preconstruction survey according to Subsection 152.05(m). Submit the results to the CO before, during, and after excavation work has been completed.

204.05. Delete the Subsection and substitute the following:

204.05 Conserved Topsoil. Conserve topsoil from roadway excavation and embankment foundation areas. Stockpile conserved topsoil in low windrows no bigger than 3 feet high by 3 feet wide at the outer portion of the clearing limits or in areas designated by the CO. Separate topsoil from other excavated material. Seed windrowed conserved topsoil with temporary seed mix.

The depth of material conserved for topsoil will vary by location within the project site.

Conserve a minimum of 2 inches of material in all cases or a depth of greater than 12 inches of material where possible. Incorporate live vegetation of less than 1 foot in height and limbs less than 1 inch in diameter as topsoil in the stockpiles. Ensure the conserved topsoil consists of natural humus bearing soils, duff, and vegetable matter obtained during clearing and grubbing operations.

Place conserved topsoil on completed slopes according to Section 624.

204.06. Add the following:

(c) Channel changes. Excavate and remove gravel bars to the elevation described in the plans. Compact the material according to Subsection 204.11.

204.09(a). Delete the Subsection and substitute the following:

(a) Embankment over natural ground. Remove vegetation, topsoil, debris, unsatisfactory soil materials, obstructions, and deleterious materials from the ground surface before placing fills. Plow, scarify, bench, or break up sloped surfaces steeper than 1V:4H so fill material will bond with existing material. Compact the ground surface according to Subsection 204.11.

J-26

204.10(a). Add the following:

Place and compact soil material approved by the CO in layers to required elevations under grass and planted areas.

Section 251. — RIPRAP

251.03. Add the following:

Use native stone type riprap from a local quarry and blend it with the landscape to achieve a natural appearance. Provide the CO with name and location of the proposed quarry 2 weeks prior to bringing material on site.

Provide the CO with a rock sample with texture and color representative of the riprap intended for use at least 7 days prior to riprap placement. Do not begin riprap placement until the CO has approved the appearance of the rock sample.

251.04. Add the following:

Place riprap in a manner to ensure that water flows over rather than under the riprap.

Choke voids in riprap when it is expected to be covered by topsoil or aggregates.

Section 252. — ROCKERY, SPECIAL ROCK EMBANKMENT, AND ROCK BUTTRESS

252.02. Delete the third material and substitute the following:

Granular backfill 703.03(a)

252.03(b). Delete the last paragraph and substitute the following:

Backfill with granular backfill concurrent with rock placement until level with each layer of rock. Place granular backfill in horizontal layers not to exceed 12 inches compacted depth.

Compact each layer according to Subsection 204.11. Compact areas not accessible to rollers with other approved methods.

252.05. Delete the fourth paragraph and substitute the following:

Roadway excavation and granular backfill will be evaluated under Section 204.

252.06. Add the following:

Do not measure granular backfill used for rockery wall for payment.

J-27

Section 301. — UNTREATED AGGREGATE COURSES

301.03. Add the following:

At the option of the Contractor, an alternate state department of transportation aggregate gradation that is produced according to Subsection 703.05 may be submitted for approval.

Provide target values within the allowable target value range of the state department of transportation aggregate gradation. When target values are not provided, the preproduction target values will be the midpoint of the allowable target value range of the state department of transportation aggregate gradation. The allowable deviation (±) from the target values will be according to Table 703-2B. The maximum allowable pay factor under Subsection 301.10 for a state department of transportation aggregate gradation will be 1.00.

Section 313. — AGGREGATE-TOPSOIL COURSE

313.04. Add the following:

Apply aggregate-topsoil to areas next to the pavement at road shoulder and under guardrails.

Section 552. — STRUCTURAL CONCRETE

552.01. Add the following:

This work includes the sealing of concrete bridge railings.

552.02. Add the following:

Elastomeric strip seals 712.01(h) Penetrating sealant 725.19 Reinforcing steel 709.01 Silicone joint sealant 712.01(i) Steel welded wire reinforcement, plain, for concrete 709.01(h)

552.19. Delete the first sentence of the first paragraph and substitute the following:

For concrete repairs, remove existing or new defective concrete according to Subsection 203.04.

552.19. Add the following after the first paragraph:

When reinforcing steel is exposed and exhibits corrosion, clean the steel until all corrosion is eliminated. Remove concrete cover 2 inches beyond the endpoints of the original corroded portion of the reinforcing steel. Inspect for corrosion. If corrosion is present, then clean steel and remove additional cover until no corrosion is encountered. Do not strike the reinforcing steel with heavy blows. Where the bond between existing concrete and reinforcing steel has

J-28 been destroyed, remove the concrete adjacent to the steel to a depth that will permit new concrete to bond to the entire periphery of the exposed steel. Provide a minimum of 1-inch clearance behind the steel.

Remove and replace reinforcing steel that has lost 25 percent or more of its original cross section area with new bars of the same size and shape. Lap the new bars with the existing bars for a length of 30 diameters on each side of the damaged portion if a sufficient length of the existing bar is exposed. Otherwise, connect the new bar by welding it to the existing reinforcement with a 6-inch arc-welded lap on each side of the damaged portion using a double-flare V-groove weld in accordance with the requirements of Section 555, or by mechanically connecting the new bar to the existing in accordance with the requirements of Section 554.

522.19. Delete the last sentence of the third paragraph and substitute the following:

Repair areas on concrete deck using High Early Strength (HES) concrete. See Table 552-8A for HES concrete requirements.

552.19. Add the following:

In repair areas larger than 2 square feet with exposed reinforcement, install pre-packaged zinc sacrificial anodes on the reinforcement according to manufacturer’s recommendations and the following:

(a) In areas larger than 2 square feet and smaller than 4 square feet, install a pair of anodes on the reinforcement. Install the anodes at opposite sides of the repair and within 6 inches of the edge of the repair; and

(b) In areas 4 square feet and larger, install an additional pair of anodes for each incremental 4-square foot increase in the repair area.

Table 552-8A

High Early Strength (HES) Concrete Requirements Property Test Method Units Specification

Minimum Compressive Strength at 6-Hours ASTM C109 psi 2000

Minimum Compressive Strength at 28-Days ASTM C109 psi 6000

Bond Strength ASTM C882 psi 2500 Maximum Chloride Permeability ASTM C1202 coulombs 1000

Thermal Coefficient of Expansion ASTM C531 in/in/0F 5.0x10-6

J-29

Add the following after Subsection 552.19:

552.19A Sealing Concrete Structure Surfaces.

(a) Submittals. Submit a sealing plan for approval according to Subsection 104.03 at least 15 days before the sealing concrete surface.