Attachment 2 Functional Performance Test Example.pdf

PDF 239 KB Posted

Attached to
Uninterruptable Power Supply (UPS) Federal contract opportunity
Solicitation number
FA570225R0002
Issued by
Department of the Air Force Air Combat Command

About this file

This document is a Functional Performance Test (FPT) for a Static Uninterruptible Power Supply (UPS) system. The test protocol comprehensively covers multiple operational aspects of the UPS, including automatic and manual operation, system protective functions, controls and indications, alarm functions, and remote monitoring capabilities. Key performance requirements include a minimum battery supply duration of 7 minutes at full rated load, overall UPS efficiency of 90% or greater at 100% load, and voltage regulation within ±3% across unbalanced load conditions.

The test procedure details extensive verification processes for the UPS system, including factory testing before shipment, simulated battery testing (full-load, transient-load, overload, and power failure tests), and verification of critical functions such as automatic power transfer, battery charging, manual operational modes, and maintenance bypass operations. The document also specifies requirements for communication interfaces, remote status monitoring, battery string monitoring, and communication with building automation systems, ensuring comprehensive system validation and performance documentation.

View the file

Other files for this federal contract opportunity

Other files attached to Uninterruptable Power Supply (UPS), newest first.
File Type Posted
Consolidated Solicitation Questions for UPS.pdf PDF
B5507. 58 -FA5702-19-C-0022 Construct 763 ERS IC - As Build - Attach (1).pdf PDF
FA5702-19-C-0022 Construct 763 ERS IC As Build - Attach.pdf PDF
Solicitation - FA570225R0002.pdf PDF
Attachment 3- Floor Plans.pptx PPTX presentation
STATEMENT OF WORK.pdf PDF
Attachment 1 B5507 Electrical Requirements.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

158 Burt Road⏐Lexington, KY 40503⏐Tel. (859) 278-5552⏐Fax (859) 278-6501 2611 Waterfront Parkway, Suite 340⏐Indianapolis, IN 46214⏐Tel. (317) 536-2618

Functional Performance Test

[Project Name]

System: Electrical Service: Static Uninterruptable Power Supply

“This Functional Performance Test document represents FCG's standard test protocol, basic functional test, and FCG's best understanding of the designed sequence of operation. This document DOES NOT define design intent, supersede contract documents, or direct means and methods.”

Functional Performance Test Pass Fail Remarks FPT Test Prerequisites Comply with manufacturer's written instructions. * Inspect interiors of enclosures, including the following:

• Integrity of mechanical and electrical connections.

• Component type and labeling verification.

• Ratings of installed components.

Inspect batteries and chargers according to requirements in NETA Acceptance Testing Specifications. *

Factory test complete UPS system before shipment. Use simulated battery testing to include: Full-Load test, Transient-load response test, Overload Test and Power Failure test. Test Result Report provided.

(Reference Specification 263353-2.12.A,B)

Record of Test and Inspections (Reference Specification 263353-3.02.D)

Automatic Operation

Automatic operational features tested* If normal power fails, energy supplied by the battery through the inverter continues supply-regulated power to the load without switching or disturbance.

When power is restored at the normal supply terminals of the system, controls automatically synchronize the inverter with the external source before transferring the load.

If the battery becomes discharged and normal supply is available, the rectifier-charger charges the battery. On reaching full charge, the rectifier-charger automatically shifts to float-charge mode.

Manual Operation

Manual operational features tested* Turning the inverter off causes the static bypass transfer switch to transfer the load directly to the normal ac supply circuit without disturbance or interruption.

Turning the inverter on causes the static bypass transfer switch to transfer the load to the inverter.

External Maintenance Bypass/Isolation Switch Operation:

Bypass/Isolation features tested*

“This Functional Performance Test document represents FCG's standard test protocol, basic functional test, and FCG's best understanding of the designed sequence of operation. This document DOES NOT define design intent, supersede contract documents, or direct means and methods.”

Switch is interlocked via an SKRU system so that it cannot be operated unless the static bypass transfer switch is in the bypass mode.

Full Isolation: Load is supplied, bypassing the UPS.

Normal UPS ac input circuit, static bypass transfer switch, and UPS load terminals are completely disconnected from external circuits.

Maintenance Bypass: Load is supplied, bypassing the UPS. UPS ac supply terminals are energized to permit operational checking, but system load terminals are isolated from the load.

Normal: Normal UPS ac supply terminals are energized and the load is supplied through either the static bypass transfer switch and the UPS rectifier-charger and inverter, or the battery and the inverter.

Performance Requirements - Inverter is switched to battery source.

System protective functions tested* Minimum Duration of Supply:

If battery is sole energy source supplying rated full UPS load current at 80 percent power factor, duration of supply is 7 minutes.

Overall UPS Efficiency: Equal to or greater than 90 percent at 100 percent load.

Maximum AC Output-Voltage Regulation for Loads up to 50 Percent Unbalanced: Plus or minus 3 percent over the full range of battery voltage.

Controls and Indications

Quantitative indications shall include the following:

• Input voltage, each phase, line to line

• System output voltage, each phase, line to line

• System output current, each phase

• System Input and output frequency

• Battery current and direction (charge/discharge)

Basic status condition indications shall include the following:

• Normal operation

• Load-on bypass

• Load-on battery

• Inverter off

“This Functional Performance Test document represents FCG's standard test protocol, basic functional test, and FCG's best understanding of the designed sequence of operation. This document DOES NOT define design intent, supersede contract documents, or direct means and methods.”

• Alarm condition Alarm functions tested* Alarm indications shall include the following:

• UPS Ok

• Low Battery Voltage

• Auto-Transfer Mode

• Fuse Open

• Battery Discharge Mode

• UPS Output Disabled

Controls shall include the following:

• Inverter on-off

• UPS start

• Battery test

• Alarm silence/reset

• Output-voltage adjustment

Remote Lab Status Annunciator Panel Functioning Basic Battery Monitoring

• Monitoring of the battery string voltage and current

• Charge, discharge, and float current monitoring

• Room ambient and battery string temperature

• Five visual status indicators per string

• Battery cycle counts based on duration

• Long term storage of key battery warranty parameters

• Event log with time and date stamp

• External device alarm input

• Alarm relay contacts output

• Network interface with password and community string protection

INDUSTRIAL BUS – COMMUNICATION PROTONODE

Communication of status to remote monitoring equipment tested.*

The Remote communications device shall provide the following status information of the UPS System at the provided register addresses internal to the communication card.

“This Functional Performance Test document represents FCG's standard test protocol, basic functional test, and FCG's best understanding of the designed sequence of operation. This document DOES NOT define design intent, supersede contract documents, or direct means and methods.”

The communication card shall allow for reading of the following fault / status bits of the UPS systems by the building automation system.

* Reference Field Quality Control Requirement per 263353-3.02

Number Date Remark