ATTACHMENT 2.a. PROPOSAL COST BREAKDOWN INSTRUCTIONS (Sample project).docx

DOCX document 16 KB Posted

Attached to
Multiple Award Task Order Contract (MATOC) for Hawaii Federal contract opportunity
Solicitation number
W912CN-23-R-0002
Issued by
Department of the Army Materiel Command Army Contracting Command

About this file

This document provides instructions for contractors to break down proposal costs on an Army Corps of Engineers multiple award task order contract solicitation for construction services in Hawaii. The solicitation requests itemized direct costs for materials, equipment, labor, subcontractors, and other expenses using standardized unit rates and quantities. Prime contractors must also include overhead, profit, and bonding calculations. Subcontractor costs require separate overhead and tax line items. The selection criteria emphasize a best value determination based on technical qualifications and price. Proposals are due by January 15, 2023, and the period of performance for task orders issued against these contracts is five years.

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Task Order Contract (MATOC) for Hawaii, newest first.
File Type Posted
23-R-0002 P00003 SF 30 Final.pdf PDF
23-R-0002 P00003 Conformed Final.pdf PDF
23-R-0002 P00002 SF 30.pdf PDF
RFI Attachments.pdf PDF
23-R-0002 P00002 Conformed.pdf PDF
23-R-0002 P00001 Conformed.pdf PDF
23-R-0002 P00001 SF 30 Amendment 9.22.23.pdf PDF
ATTACHMENT 2.a. PROPOSAL COST BREAKDOWN INSTRUCTIONS (Sample project) rev.docx DOCX document
W912CN 23-R-0002 HI MATOC RFI Responses.pdf PDF
Attachment 2.b COST ESTIMATE SUMMARY SHEET (Sample Project).xlsx XLSX spreadsheet
ATTACHMENT 3 PAST PERFORMANCE INFORMATION.docx DOCX document
Attachment 1 COST ESTIMATE SUMMARY SHEET PROPOSED RATES.xlsx XLSX spreadsheet
ATTACHMENT 4. PAST PERFORMANCE EVALUATION QUESTIONNAIRE.docx DOCX document
W912CN-23-R-0002 SF1442 FINAL.pdf PDF
Attachment 2 - MATOC SAMPLE PROJECT.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROPOSAL COST BREAKDOWN INSTRUCTIONS

DESCRIPTION: Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

UNIT OF MEASURE: Description of the unit in which each item is to be estimated (examples: square yards-SY, cubic yards-CY, square feet-SF, linear feet-LF, board feet-BF, each-EA, pound-LB).

QUANTITY: Contractor’s estimate of quantity required in terms of unit of measure. Items and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

MATERIAL COSTS: Enter description, quantity, and unit cost of material to be supplied and total cost.

EQUIPMENT COSTS: Enter description, quantity, and unit cost of equipment and total cost.

LABOR COSTS: For each job classification, enter the estimated number of manhours needed to perform the work listed with hourly rate and fringes.

OTHER DIRECT COSTS: Enter estimated costs of other items which are special to the contract and of significant dollar value.

SUBCONTRACTOR COSTS: (See below)

NOTE: The grand total, plus overhead and profit, will be shown as follows.

PRIME CONTRACTOR:

TOTAL MATERIAL COSTS $ 1,000,000.00

TOTAL LABOR COSTS $ 5,000,000.00

TOTAL EQUIPMENT COSTS $ 1,000,000.00

TOTAL OTHER DIRECT COSTS $ 0.00

TOTAL DIRECT COSTS $ 7,000,000.00

OVERHEAD __________% $_________________________

SUBTOTAL $_________________________

PRIME CONTRACTOR PROFIT _______% $_________________________

*PRIME CONTRACTOR SUBTOTAL $_________________________

SUBCONTRACTOR:

TOTAL MATERIAL COSTS $ 1,000,000.00

TOTAL LABOR COSTS $ 5,000,000.00

TOTAL EQUIPMENT COSTS $ 1,000,000.00

TOTAL OTHER DIRECT COSTS $ 0.00

TOTAL DIRECT COSTS $ 7,000,000.00

OVERHEAD 10% $ 700,000.00

SUBTOTAL $ 7,700,000.00

Subcontractor PROFIT 5% $ 385,000.00

SUBCONTRACTOR HAWAII STATE TAX 0%$ 0.00
,
SUBTOTAL Subcontractor$ 8,085,000.00
PRIME CONTRACTOR OVERHEAD
ON SUBCONTRACTOR ______%$_________________________

SUBTOTAL (subcontractor and prime overhead on subcontractor) $_________________________

BOND PREMIUM __________% $_________________________

SUBTOTAL $_________________________

HI State Tax ______%$ 0.00
(subcontractor’s cost, overhead

on subcontractor bonding)

GRAND TOTAL PROJECT COST $_________________________

A breakdown of the materials, labor, equipment, subcontractor, and other direct cost will be provided on the excel sheet attachment which is made part of this solicitation. (Attachment 2.b)

Reverse of VG-GK 82-161-R, SEP 10

File details come from the government source that posted it. Updated .