This is a Contractor Responsibility Verification template based on Federal Acquisition Regulation (FAR) 9.103-9.104 requirements. The document establishes the criteria that prospective contractors must satisfy to be determined responsible and eligible for federal contract award.

The template requires contractors to demonstrate responsibility across six key factors: (a) financial resources sufficient to perform the contract, evidenced through profit/loss statements, balance sheets, lines of credit, or a letter from a financial institution; (b) ability to meet required delivery or performance schedules considering existing commercial and governmental commitments; (c) satisfactory performance record within the past three years, demonstrated through two past performance examples or a capability statement for new entrants, with an exemption for contractors with prior government CPARS and SPRS ratings; (d) satisfactory business integrity and ethics, verified through SAM.gov responsibility and qualification information; (e) adequate organizational structure including experience, accounting controls, operational controls, and technical skills; and (f) necessary production, construction, and technical equipment and facilities. The contractor's authorized representative must certify that all information provided across these six factors is correct and accurate. This verification document serves as a standard mechanism for contracting officers to assess whether prospective contractors meet the minimum responsibility criteria required before contract award.

View the file

Other files

File Type Posted
Request for Information - Johnson Field Repair.xlsx XLSX spreadsheet
Env 202514- Renovate Softball fields 2025-v8.pdf PDF
Attachment 13 - Travis AFB Spec 01000 Word DocWithHyperlinks 1-04-23.pdf PDF
UFGS 01 35 26-GOVERNMENTAL SAFETY REQUIREMENTS.pdf PDF
01 56 00 2026- Engineering Enviornmental Specs-01 56 00.pdf PDF
Attachment 6 - Statement of Work Johnson Softball Field Repair (edited 2 - Sep 1).docx DOCX document
Maint and DurList_Distribution Copy - 2025-07-16.pdf PDF
Travis Design Guide FEG.PDF PDF
Env softball Memo Final.pdf PDF
Travis AFB Spec - 01 00 00 - General Spec_Jan 2022.pdf PDF
UFGS 01 78 00 Closeout Submittals.pdf PDF
UFGS 01 33 16.00 10.pdf_safe.pdf PDF
UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.pdf PDF
Travis AFB Spec - 01 00 00 - General Spec_Sep 2024 - benson.pdf PDF
Solicitation Notice - Johnson Softball Field Repair (Amendment 0003).pdf PDF
mutcd11thedition.pdf PDF
Travis Facilities Excellence Guide 2022-08-15.pdf PDF
UFGS 01 33 00 SUBMITTAL PROCEDURES (002).pdf PDF
UFGS 01 14 00 WORK RESTRICTIONS.pdf PDF
ufc_3_410_02_2018_c2.pdf PDF
ufc_1_300_08_2023.pdf_safe.pdf PDF
Travis AFB BMP Construction Site Documents feb2025.pdf PDF
UFGS 01 45 00.00 40 QUALITY CONTROL.pdf PDF
Travis AFB Spec - SECTION 01 56 00_Environmental Specs_April 2019.pdf PDF
SECTION 01 03 00 PROJECT CLOSEOUT AUG 13.pdf PDF
Travis AFB Spec - 01 00 01 - General Spec_Sep 2024.pdf PDF
Solicitation Notice - Johnson Softball Field Repair (Amendment 0002).pdf PDF
Pre-site visit RFI.pdf PDF
Attachment 6 - Statement of Work Johnson Softball Field Repair (edited).docx DOCX document
Solicitation Notice - Johnson Softball Field Repair (Amendment 0001).pdf PDF
Attachment 1 - Solicitation Provisions and Contract Clauses by Reference (Amendment 0001).pdf PDF
Attachment 1 - Solicitation Provisions and Contract Clauses by Reference.pdf PDF
Attachment 5 - Travis Air Force Base Security Requirements.pdf PDF
Attachment 6 - Statement of Work Johnson Softball Field Repair.docx DOCX document
Attachment 8 - Location and Vicinity Map - Johnson Softball Field.docx DOCX document
Solicitation Notice - Johnson Softball Field Repair.pdf PDF
Attachment 4 - Past Performance Questionnaire (PPQ).docx DOCX document
Attachment 7 - Davis Bacon Act Wage Determination CA20260007.pdf PDF
Attachment 3 - Past Performance List of References.docx DOCX document
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor Responsibility Verification

FAR 9.103

(a) Award contracts to responsible prospective contractors only.

(b) Do not award a contract award before making an affirmative determination of contractor responsibility. Without a clear indication of responsibility, make a determination of nonresponsibility. If the prospective contractor is a small business concern, comply with the subpart, Certificates of Competency and Determinations of Responsibility, at part 19.

(c) A prospective contractor must affirmatively demonstrate its responsibility, including, when necessary, the responsibility of its proposed subcontractors.

FAR 9.104

To be determined responsible, a prospective contractor must-

(a) Have adequate financial resources to perform the contract, or the ability to obtain them (see 9.104- 3(a));

(b) Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;

(c) Have a satisfactory performance record (see 9.104-3 (b) and part 42). Do not determine a prospective contractor responsible or nonresponsible based solely on a lack of relevant performance history;

(d) Have a satisfactory record of integrity and business ethics (see part 42);

(e) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors) (see 9.104-3(a));

(f) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them (see 9.104-3(a)); and

(g) Be otherwise qualified and eligible to receive an award under applicable laws and regulations (see also inverted domestic corporation prohibition at 9.108).

For each factor, please provide the following information or submit supporting documentations as applicable in order to verify the Contractor’s Responsibility IAW FAR 9.104-1:

(a) FINANCIAL RESOURCES

Evidence that the contractor has financial resources to perform the contract such as Profit/Loss statement, most recent Balance Sheet, Available Line of Credit from a bank.

Alternatively, the Offeror may provide a statement from their financial institution or a responsible company official on business letterhead confirming that the offeror currently has sufficient financial resources, or the ability to obtain them, to meet this requirement.

I confirm that a responsible company official will provide documentation of adequate financial resources to support this requirement.

(b) MEETING DELIVERY REQUIREMENT

I confirm that my company is able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments

(c) PERFORMANCE RECORD

Provide in the submission two (2), at a minimum, past performance record within the last 3 years OR a capability statement for a satisfactory performance for new entrants. Exemption: Contractors that had previously satisfied contracts with the Government for which CPARS (Contractor Performance Assessment Reporting System) and SPRS (Supplier Performance Risk System) ratings were received.

I confirm that my company has satisfactorily performed similar requirements in the past 3 years I confirm that my company has, or can, provide a capability statement.

My company is exempt from this requirement.

(d) BUSINESS INTEGRITY AND ETHICS

I, , (Company Representative) certify that the information within the Responsibility/Qualification section in SAM.gov of (Company Name), which includes a summary report of any Active or Inactive Exclusions, Proceedings, and Other Responsibility & Integrity Information, are recent, correct, and accurate.

(e) ORGANIZATIONAL STRUCTURE

I confirm that my company currently has an adequate organizational structure (experience, accounting and operational controls, and technical skills), the ability to correct any potential deficiencies, and/or the ability to obtain them.

(f) PRODUCTION CAPABILITIES

Provide in the submission production information on technical equipment and facilities, or the ability to obtain them.

I confirm that my company currently has the adequate production, construction, and technical equipment and facilities, and/or the ability to obtain them to fulfil this requirement.

I, , (Company Representative) certify that the information provided for factors

(a) to (f) are correct and accurate.