Pre-site visit RFI.pdf

PDF 57 KB Posted

Attached to
Johnson Field Repair
Solicitation number
FA442726Q1133
Issued by

View the file

Other files

File Type Posted
Request for Information - Johnson Field Repair.xlsx XLSX spreadsheet
Solicitation Notice - Johnson Softball Field Repair (Amendment 0003).pdf PDF
mutcd11thedition.pdf PDF
Travis Facilities Excellence Guide 2022-08-15.pdf PDF
UFGS 01 33 00 SUBMITTAL PROCEDURES (002).pdf PDF
UFGS 01 14 00 WORK RESTRICTIONS.pdf PDF
Env 202514- Renovate Softball fields 2025-v8.pdf PDF
Attachment 13 - Travis AFB Spec 01000 Word DocWithHyperlinks 1-04-23.pdf PDF
UFGS 01 35 26-GOVERNMENTAL SAFETY REQUIREMENTS.pdf PDF
01 56 00 2026- Engineering Enviornmental Specs-01 56 00.pdf PDF
Attachment 6 - Statement of Work Johnson Softball Field Repair (edited 2 - Sep 1).docx DOCX document
Maint and DurList_Distribution Copy - 2025-07-16.pdf PDF
Travis Design Guide FEG.PDF PDF
Env softball Memo Final.pdf PDF
Travis AFB Spec - 01 00 00 - General Spec_Jan 2022.pdf PDF
UFGS 01 78 00 Closeout Submittals.pdf PDF
UFGS 01 33 16.00 10.pdf_safe.pdf PDF
UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.pdf PDF
Travis AFB Spec - 01 00 00 - General Spec_Sep 2024 - benson.pdf PDF
ufc_3_410_02_2018_c2.pdf PDF
ufc_1_300_08_2023.pdf_safe.pdf PDF
Travis AFB BMP Construction Site Documents feb2025.pdf PDF
UFGS 01 45 00.00 40 QUALITY CONTROL.pdf PDF
Travis AFB Spec - SECTION 01 56 00_Environmental Specs_April 2019.pdf PDF
SECTION 01 03 00 PROJECT CLOSEOUT AUG 13.pdf PDF
Travis AFB Spec - 01 00 01 - General Spec_Sep 2024.pdf PDF
Solicitation Notice - Johnson Softball Field Repair (Amendment 0002).pdf PDF
Attachment 6 - Statement of Work Johnson Softball Field Repair (edited).docx DOCX document
Solicitation Notice - Johnson Softball Field Repair (Amendment 0001).pdf PDF
Attachment 1 - Solicitation Provisions and Contract Clauses by Reference (Amendment 0001).pdf PDF
Attachment 4 - Past Performance Questionnaire (PPQ).docx DOCX document
Attachment 7 - Davis Bacon Act Wage Determination CA20260007.pdf PDF
Attachment 1 - Solicitation Provisions and Contract Clauses by Reference.pdf PDF
Attachment 5 - Travis Air Force Base Security Requirements.pdf PDF
Attachment 6 - Statement of Work Johnson Softball Field Repair.docx DOCX document
Attachment 8 - Location and Vicinity Map - Johnson Softball Field.docx DOCX document
Solicitation Notice - Johnson Softball Field Repair.pdf PDF
Attachment 2 - Contractor Responsibility Verification.pdf PDF
Attachment 3 - Past Performance List of References.docx DOCX document
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Please confirm whether a bid bond/bid guarantee is required with the quote submission.

- No. Bid bonds/guarantees will not be required.

2. Please confirm whether performance and payment bonds will be required after award.

- Yes. Performance and payment bonds will be required. Clause 52.228-16, Performance and Payment Bonds has been added to the list of provisions and clauses.

(a) Definitions. As used in this clause-

"Original contract price" means the award price of the contract or, for requirements contracts, the price payable for the estimated quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) The Contractor shall furnish a performance bond (Standard Form 1418) for the protection of the Government in an amount equal to 100 percent of the original contract price and a payment bond Standard Form 1416) in an amount equal to 100 percent of the original contract price.

(c) The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within 10 days, but in any event, before starting work.

(d) The Government may require additional performance and payment bond protection if the contract price is increased. The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bonds or to obtain additional bonds.

(e) The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register, or may be obtained from the:

U.S. Department of the Treasury, Financial Management Service, Surety Bond Branch, https://www.gsa.gov/forms-library/performance-bond-other-construction-contracts https://www.gsa.gov/forms-library/payment-bond-other-construction-contracts

3700 East West Highway, Room 6 F01

Hyattsville, MD 20782.

Or via the internet at http://www.fms.treas.gov/c570/.

3. The SOW introduction references stadium lighting and boundary fencing; however, the detailed repair section primarily addresses the field, gopher barrier, grading, seeding, and irrigation. Please confirm whether stadium lighting and fencing repairs/replacement are included in the contractor’s required scope.

- The SOW has been updated to reflect the scope of the project accordingly.

4. Please confirm the overall period of performance for the project.

- The period of performance will be 120 calendar days http://www.fms.treas.gov/c570/