This attachment is related to a federal solicitation for life safety corrections to Fisher House 1. The solicitation number is 36C26122R0051 and is seeking proposals for work on Fisher House 1 located within Veterans Integrated Service Network 21 of the Department of Veterans Affairs. Proposals are due by the date listed in the solicitation for correcting life safety issues at the specified location to bring it up to code and ensure resident safety. Details on the required repairs, specifications, terms, and conditions can be found in the associated specifications document. The work must be completed by the schedule defined in the final contract to address the identified safety concerns at Fisher House 1 for veterans.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Correct Fisher House 1 Life Safety Requirement 05-01-21 VA Palo Alto Health Care System Project# 640-22-111
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 10 Table of Content 05-21 00 11 21 Request for Proposal to Design Build 06-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 05-21 01 32 16.16 Network Analysis Schedules (Design-Build Only) 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 03-19 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 01-21 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 00 Cast in Place Concrete 01-21 03 55 11 Gypsum Concrete Floor Decks 01-21
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 10-17 04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18 05 21 00 Steel Joist Framing 11-18 05 31 00 Steel Decking 01-21 05 36 00 Composite Metal Decking 01-21 05 50 00 Metal Fabrication 08-18 05 51 00 Metal Stairs 01-21
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17 06 16 63 Cementitious Sheathing 01-21 06 20 00 Finish Carpentry 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 08 00 Facility Exterior Closure Commissioning 01-21 07 21 13 Thermal Insulation 01-21 07 60 00 Flashing and Sheet Metal 01-21 07 81 00 Applied Fireproofing 10-17 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 17 10 Integrated Door Assemblies 01-21 08 31 13 Access Doors and Frames 01-21 08 71 00 Door Hardware 01-21 08 71 13 Automatic Door Operators 01-21 08 80 00 Glazing 01-21 08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 23 00 Gypsum Plastering 01-21 09 24 00 Portland Cement Plastering 01-21 09 29 00 Gypsum Board 04-20 09 30 13 Ceramic/Porcelain Tiling 01-21 09 68 00 Carpeting 07-21 09 72 16 Vinyl-Coated Fabric Wall Coverings 01-21 09 72 31 Polypropylene Fabric Wall Coverings 01-21 09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21 10 26 00 Wall and Door Protection 01-21 10 44 13 Fire Extinguisher Cabinets 01-21 10 52 00 Fire Protective Smoke Curtain 08-18
DIVISION 11 – EQUIPMENT
Not Used
00 01 10-3
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 12 – FURNISHINGS
Not Used
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Not UsedSeismic Restraint Requirement for Non- Structural Components
01-21
DIVISION 14– CONVEYING EQUIPEMENT
Not Used
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16 21 12 00 Manual Dry Standpipe Systems 06-15 21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-20 22 05 23 Genera-Duty Valves for Plumbing Piping 09-20 22 08 00 Commissioning of Plumbing Systems 11-16
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results For HVAC 02-20 23 05 41 Noise and Vibration Control For HVAC Piping And
Equipment 02-20
23 05 93 Testing, Adjusting, And Balancing For Hvac 02-20 23 07 11 HVAC And Boiler Plant Insulation 02-20 23 08 00 Commissioning Of HVAC Systems 02-20 23 09 23 Direct-Digital Control System For HVAC 08-20 23 31 00 HVAC Ducts And Casings 02-20 23 34 00 HVAC Fans 02-20 23 36 00 Air Terminal Units 02-20 23 37 00 Air Outlets and Inlets 02-20 23 40 00 HVAC Air Cleaning Devices 03-20
DIVISION 25 – INTEGRATED AUTOMATION
Not Used
DIVISION 26 – ELECTRICAL
26 05 11 Requirements For Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors And Cables 01-17 26 05 26 Grounding And Bonding For Electrical Systems 01-17
00 01 10-4
SECTION NO. DIVISION AND SECTION TITLES DATE
26 05 33 Raceway And Boxes For Electrical Systems 01-18 26 08 00 Commissioning Of Electrical Systems 11-16 26 09 23 Lighting Controls 01-18 26 27 26 Wiring Devices 01-18 26 51 00 Interior Lighting 01-18 26 56 00 Exterior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements For Communications Installations 09-19 27 08 00 Commissioning Of Communications Systems 11-16 27 10 00 Control, Communication And Signal Wiring 06-15 27 31 00 Voice Communications Switching And Routing Equipment 06-15
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 08 00 Commissioning Of Electronic Safety And Security Systems 11-16 28 13 00 Physical Access Control System 10-11 28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
Not Used
DIVISION 32 – EXTERIOR IMPROVEMENTS
Not Used
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 03-17
DIVISION 34 – TRANSPORTATION
Not Used
DIVISION 48 – Electrical Power Generation
Not Used
Correct Fisher House 1 Life Safety Requirement 09-01-21
00 11 21-1
SECTION 00 11 21
REQUEST FOR PROPOSAL TO DESIGN BUILD
FISHER HOUSE 1, LIFE SAFETY CORRECTION
640-22-111
VA PALO ALTO HEALTH CARE DIVISION
A. PART I - GENERAL
A1. Scope of Contract
Provide all labor, materials, tools and equipment, and design-build services necessary for design and construction of a project described here in other specific tasks as further defined by this request for proposal (RFP).
A2. Definitions
A. Design-Build (DB) as defined by the US Department of Veterans Affairs
(VA) is the procurement by the Government, under one contract, with one firm or joint venture (JV) for both design and construction services for a specific project.
1. Contracting Officer: The services to be performed under this contract are subject to the general supervision, direction, control and approval of the Contracting Officer.
2. Project Manager: The Contracting Officer's representative responsible for administering contracts under the immediate direction of the Contracting Officer.
3. Resident Engineer: The Contracting Officer's authorized representative at the construction site. When more than one Resident
Engineer is assigned to a construction project one is designated as being in-charge and is called the "Senior Resident Engineer". The
Resident Engineer is responsible for protecting the Government's interest in the execution of the construction contract work. His duties include surveillance of all construction work to assure compliance with the contract documents, interpretation of the contract documents, approval of changed work, approval of all submittals, samples, shop drawings, etc. The Resident Engineer may issue change orders to the Contractor within the limitations set forth in his delegation of authority from the Contracting Officer.
4. Design Build Contract: This term, as used herein, refers to the
Contract(s) to perform the design and construction of the project.
5. Contractor: This term, as used herein, refers to the contractor under this contract or the DB team.
00 11 21-2
6. AE: This term, as used herein, refers to the Architect-Engineer firm(s)that are a part of the DB team, also referred to as DB/AE.
7. RFP/AE: The firm(s) directly hired by the VA for the preparation of the RFP Documents and to provide other technical assistance to the
VA.
B. Selection Procedure - During the review of offers the VA may ask for additional information. The VA may initiate action to award a contract at any point after review of the offers. Therefore, offers should reflect the offeror’s best terms both from a technical and cost standpoint. See FAR 52.215-1, Instructions to Offerors - Competitive
Acquisition.
C. Tentative Schedule:
Request for proposal issued +14
Pre-proposal conference +21
Proposal submitted +21
Contract award +21
Notice to proceed +30
Construction completion/final inspection/ custody receipt
+378
D. Schedule Objectives - The anticipated completion of this project is 378 calendar days after “Notice to Proceed” (NTP). The proposed schedule may be shorter than this, see Part III, C3, 3c.
A3. Cost Range
The anticipated cost range for this project is between $2,000,000 and
$5,000,000.
A4. Pre-Proposal Conference
A pre-proposal conference will be held on a date to be determined. All offerors, consultants, subcontractors, manufacturers and suppliers are invited to attend. The following agenda is furnished for this meeting:
1. Open meeting;
2. Review of project and design build method for construction contracting;
3. Specifications, Network analysis system and project phasing;
4. General requirements, Solicitation Documents and Offer Submission
Procedure;
5. Review of "Buy American Act";
00 11 21-3
6. Questions and answers;
7. Close; and
8. Site walk through – attendance is optional.
A5. Small Business Conference (Not Applicable)
A6. Selection Criteria and Weightings
A. General proposals will be evaluated and award will be made on the basis of both cost and technical considerations most advantageous to the government as per FAR Part 15. In descending order of importance evaluations will be based on cost, construction management, past performance, schedule and (small disadvantage business participation
*). Responsibility determination will be made in accordance with FAR
9.1, Responsible Prospective Contractors.
B. Technical Evaluations - All technical factors when combined are approximately equal in importance to cost or price. Evaluations will be based on the following technical weightings in descending order of importance:
60% - construction management including corporate project experience, personnel experience, technical/management approach
20% - past performance
10% - schedule
10% - small disadvantaged business participation**
C. Cost Proposal - Offerors are advised that if the technical proposals are essentially equal, award will be made on the basis of the lowest cost.
B. PART II - RESPONSIBILITIES
B1. VA Team
A. The RFP A/E team shall not be included as members of the offeror’s DB team. The RFP A/E team that produced the RFP documents is: Designtech
Associates.
B. The VA team is also comprised of VA Office of Facilities Management and
VA COR, who will be located at the construction site and VA medical center staff.
B2. Design-Build Team:
A. The DB team includes all J/V partners, consultants and sub-contractors to the one firm. The DB team shall provide Architectural and
Engineering disciplines for the preparation of construction documents, 00 11 21-4 and construction contractor capabilities for construction of the project.
B. If the DB Team A/E and contractor are a J/V (not one and the same firm) engineering and other technical consultants shall be subcontractors of the J/V Architect - not the Design-Build construction contractor or sub-contractors. If the DB Team A/E and contractor are one and the same firm (not a J/V) those consultants shall be subcontractors of DB firm not the construction subcontractors.
C. The RFP documents are intended to define existing conditions, certain required items, and design parameters to be included in the project. It is the DB Team’s responsibility to complete the documents and construction in a manner consistent with the intent of the RFP documents within the required time period (contract length).
C. PART III - PROPOSAL REQUIREMENTS
C1. General
A. Proposals shall be based on solicitation documents issued for RFP
Solicitation Number ______, Specification Number ____. Proposals will be in the format stipulated elsewhere in this section.
B. Proposals shall be received before __________. There will be no public opening of the proposals.
C. Submit sealed offers to:
1. For US Postal Service Deliveries:
____________, Contracting Officer Office of Construction & Facilities Management US Department of Veterans Affairs 810 Vermont Ave, NW Washington, DC 20420; OR
2. For Commercial Delivery Services (Monday- Friday, 7:30 am to 4:30
PM):
US Department of Veterans Affairs (CFM) Attn: ____________, Contracting Officer Contact Phone: _________________ 425 I Street NW (suite #_____) Washington DC, 20420
D. Technical and Cost sections of the Offers proposals will be evaluated independently. Offeror shall separately bind each section. Each section must therefore be labeled with the Offeror's organization, business address, and VA Project Number. Offerors shall affix their names and
00 11 21-5 return addresses on their envelope/packaging. E. Carefully follow
“Instructions, Conditions, and Notices to Offerors”.
1. Offeror shall submit separate prices for any Bid Items indicated on the RFP Offer and award;
2. Offeror shall include all required Representations and
Certifications; and acknowledge receiving amendments by number.
C2. Proposal Revisions (FAR 52.215-1)
A. If determined to be necessary, proposal revisions will be requested from the proposals received. The Contracting Officer will identify those offerors, whose proposals are within the competitive range, considering the selection criteria identified in this section.
Negotiations may be conducted with those offerors falling within the competitive range, after which proposal revisions will be requested.
Those selected as within the competitive range will be given 7 calendar days to prepare their proposal revisions. Sealed proposal revisions will be submitted as per Part III.C1.C, above, except as noted below and will be due at a time and place to be determined.
B. Offerors submitting proposal revisions will not be requested to re-submit any documents which are unchanged from their initial proposals.
They should provide necessary changes to individual paragraphs, as briefly as possible, together with a table of contents, that clarifies where within the initial proposal the additional information or changed documents would be placed. A new bid bond shall be submitted only if the final proposal revisions offeror’s price proposal is greater than its initial price proposal.
C3. Technical Proposal Requirements (See Solicitation)
D. PART IV - POST AWARD REQUIREMENTS
D1. Construction Document Preparation:
A. Design Review Submissions:
1. The Design-Build Team A/E (DB A/E) shall prepare and submit complete construction documents for review and approval by the VA in accordance with standard professional practice, the US Department of
Veterans Affairs RFP (VA RFP), and prevailing codes.
2. The documents may be divided into multiple review submission packages. The VA will review as many as six (6) package submissions
(examples: demolition, civil, architectural, structural, mechanical, Electrical, plumbing etc.) to facilitate the start of construction.
00 11 21-6
3. All submission packages will be reviewed at (65% and 100%) completion stages. The (100%) review submission packages will incorporate the final review comments from the previous reviews. If any package is not complete for the required stage a post review may be required the cost of which will be borne by the DB Team.
4. Each review submission package shall include three (3) hard copy sets and one (1) electronic set. The package will include an index of drawings (by sheet number and title) and specifications (by section number and title) submitted. The packages will be distributed to the VA Project Manager, the VA Medical Center, VA
Resident Engineer and others as determined to be appropriate by the
VA Project Manager.
B. Design Review Meetings:
1. A review meeting to resolve design issues will be held for each design review package submitted. The meeting will include discussion of VA comments on functional relationships and technical peer review comments (by others).
2. Participants will include VA Staff and DB team members as appropriate for the specific package to be reviewed and others. The
DB team members will each allow for (1) full day for each discipline/package design review meeting. DB team management will be present at each review meeting.
3. The DB team shall allow a minimum of fourteen (14) calendar days for each review cycle. A cycle includes:
a. The VA’s receipt of the design review submission package.
b. The review meeting.
c. DB teams receipt of comments from the VA, either electronically, by fax, or by hard copy delivery.
4. Coordination of the review meeting schedules will be the responsibility of the VA Project Manager (for the VA) and the DB
Team Project Manager (for the DB Team). See section H. Quality
Assurance/Quality Control.
C. Electronic Media:
1. Design review submission drawings and final Construction Document submission drawings will be executed in electronic formats Autocad
Version 2010 DWGs and PDFs.
2. The drawings included in the VA RFP will be available to the DB team in electronic format for use in preparing the construction drawings.
00 11 21-7
Since data stored on electronic media can deteriorate undetected or be modified without the RFP Architect/Engineer’s knowledge, the drawing files are provided without warranty or obligation on the part of the RFP Architect/Engineer as to accuracy or information contained in the files. The user shall independently verify all information in the files. Any user shall agree to indemnify and hold the RFP Architect Engineer harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the CADD drawing files.
3. Design review submission specifications and other 8 1/2 by 11 formatted material and final Construction Document submission specifications and other 8 1/2 by 11 formatted material will be executed in electronic format Microsoft Word.
4. The specifications included in the VA RFP shall be available to the
DB team in electronic format in Microsoft Word, for use in preparing the construction specifications. Since data stored on electronic media can deteriorate undetected or be modified without the RFP
Architect/Engineer’s knowledge, the drawing files are provided without warranty or obligation on the part of the RFP
Architect/Engineer as to accuracy or information contained in the files. The design builder shall independently verify all information in the files and shall agree to indemnify and hold the RFP Architect
Engineer harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the electronic files.
5. The construction record drawings shall be completed in AutoCAD and
PDF.
6. Construction shop drawings are not required to be completed in
AutoCAD.
D. Professional Licensing:
1. The DB A/E who prepares the construction documents shall be a professional architect or engineer licensed in the state in which the design work is completed.
2. The professional seal indicating such license by the state shall appear on the final construction documents. The architect whose seal is shown will be known as the Architect of Record. The DB A/E shall certify compliance with the VA RFP and all applicable codes.
E. Approved Construction Documents:
00 11 21-8
1. The final construction document submission package will be submitted by the DB team for approval by the VA after completion of the 100% review cycle for the final package to be submitted by the DB team.
The VA will have 14 calendar days to take approval action.
2. The final construction documents submission package will include a full set of construction documents including all disciplines/packages.
3. The final construction documents submission package will incorporate all VA supplied comments from the earlier 65% and 100% submission package reviews and will comply with the VA RFP.
4. If the final construction documents submission package is not complete a post submittal may be required the cost of which will be borne by the DB Team.
5. The approved final construction documents include such details that the project can be constructed and will be used for construction of the project.
6. See PART IV, D2 CONSTRUCTION PERIOD SUBMITTALS for Approved
Construction Document distribution.
F. Construction Drawing Preparation - Mandatory material and equipment schedules and details may be indicated either on the drawings or in the specifications, at the option of the DB team. The construction drawings shall include a coordinated set of the following:
1. Civil engineering drawings including demolition plans, grading and drainage plans, paving plans, utility plans, schedules calculations and details.
2. Landscape drawings (Not Applicable)
3. Structural drawings including foundation plans, framing plans, schedules, and details, including general notes and all calculations.
4. Architectural drawings including floor plans, building elevations, building sections, wall sections, reflected ceiling plans, stair details, toilet and bath details, door schedules and details, window schedules and details, room finish schedules, auto transport and other details.
5. Fire protection drawings including floor and roof plans, riser diagrams, equipment schedules, and details, including general notes calculations and all related calculations.
00 11 21-9
6. Plumbing drawings including floor and roof plans, riser diagrams equipment schedules, plumbing fixture schedules, and details, including general notes, and all related calculations.
7. HVAC drawings including floor and roof plans, one-line flow diagrams, equipment schedules, and details, including general notes and all related calculations. Also provide sections for mechanical equipment rooms and sequence of operation for all HVAC equipment.
8. Outside steam (Not Applicable)
9. Electrical drawings including site demolition plans, site, floor and roof plans (power, lighting, and other systems), one-line diagrams, panel schedules, equipment schedules, light fixture schedules calculations and details
10. Asbestos abatement (Not Applicable)
11. Parking Control (Not Applicable)
G. Construction Specifications - Project specifications shall include specifications for all products, materials, equipment, methods, and systems shown on the construction drawings in accordance with standard professional practice and the VA RFP. The specification submitted for review shall include:
1. The name of the manufacturer, the product name, model number, or other identification as appropriate to clearly identify the product that will be used in the construction of the project;
2. Other data as appropriate to clearly identify the product that will be used in the construction of the project i.e. shop drawings, product data, and samples as required by the VA RFP documents; and
3. The required stamp of the licensed architect or engineer of record will be considered as certification of compliance with the RFP requirements.
H. Design Requirements - Compliance with codes and standards.
1. Project design shall be in compliance with applicable standards and codes described in VA Program Guides and design materials included or referenced in the solicitation materials.
2. See Section E. Approved Construction documents, above, for required inclusion of design review comments.
3. In the design of new building and alteration work under this contract, the DB team shall consider all requirements (other than procedural requirements) of:
l. Zoning laws:
00 11 21-10
2. Environmental and erosion control regulations; and
3. Laws relating to landscaping, open space, minimum distance of a building from the property line, maximum height of a building, historic preservation, and esthetic qualities of a building. Also similar laws, of the State and local political division, which would apply to the building if it were not to be constructed or altered by the U.S. Government.
4. The DB team shall consult with appropriate officials of the Federal, state, and political subdivision, and submit plans under the rules prescribed by those reviewing authorities. The A/E and VA shall give due consideration to the recommendations of the referenced building officials. VA will also permit inspection by the officials described above during the construction period in accordance with the customary schedule of inspections in the locality of the building construction. Such officials shall provide VA with a copy of the schedule before construction begins or give reasonable notice of their intention to inspect before conducting an inspection.
5. The DB team shall provide prompt, written notification to the
Contracting Officer concerning conflicts with, or recommended deviations from codes, laws, regulations, standards, and opinions of review officials as described above. No work altering the scope of this contract shall be undertaken prior to receipt of written approval from the Contracting Officer.
6. No action may be brought against the DB Team or VA and no fine or penalty may be imposed for failure to carry out any of the previously described recommendations of Federal, state, or local officials. VA and its contractors, including RFP A/E, shall not be required to pay any amount for any action taken by a state or political division of a state in carrying out functions described in this article, including reviewing plans, carrying out on-site inspections, issuing permits, and making recommendations.
7. The DB team shall advise the Contracting Officer of any variances with the applicable US Department of Labor, Occupational Safety and
Health Standards, for occupancy requirements.
I. Quality Assurance/Quality Control:
1. To reduce design errors and omissions, the DB team shall develop and execute a QA/QC plan that demonstrates the project plans and
00 11 21-11 specifications have gone through a rigorous, thorough review and coordination effort.
2. Within 2 weeks of receipt of Notice to Proceed, the DB Team will submit a detailed QA/QC plan describing each QA/QC task that will be taken during the development of the various design submission packages and the name of the DB Team member responsible for QA/QC.
a. Upon its completion each task shall be initialed and dated by the responsible DB Team member.
b. A 100% completed QA/QC plan shall be submitted with the final construction document submission package.
D2. Construction Period Submittals
A. The DB contractor shall distribute a total of three (3) hard copy sets and one (1) electronic of the approved construction documents prepared by the DB Team to the VA, as directed by the VA Project Manager.
B. Other submittals - The DB team shall submit test results, certificates, manufacturer’s instructions, manufacturers field reports, etc. as required by the VA RFP specifications, to the VA R/E.
C. Project record drawings - The DB team will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process as required by the
RFP specifications. The project record drawings will be available for review by the VA Resident Engineer at all times.
D. Shop drawings and submittals - The DB A/E shall check government furnished and/or the DB construction contractor's shop drawings, detail drawings, schedules, descriptive literature and samples, testing labor-laboratory reports, field test data and review the color, texture and suitability of materials for conformity with the RFP Documents and construction documents. The DB A/E shall recommend approval, disapproval, or other suitable disposition to the VA RE. The VA RE will have final approval authority. The DB AE shall evaluate the submittals with reference to any companion submittals that constitute a system.
When necessary, the DB A/E will request the DB Construction Contractor to submit related components of a system before acting on a single component. Should this procedure be inappropriate, the DB A/E shall review all prior submittals for related components of the system before acting on a single component. The DB A/E may be required to hold joint reviews with the VA technical staff on complicated system submittals.
The DB A/E shall notify the VA Resident Engineer (RE) in writing of any
00 11 21-12 and all deviations from the requirements of the construction documents that he has found in the submittals.
D3. Project Close-Out
The DB team shall comply with the requirements in FAR 4.804 Closeout of
Contract Files, for submission of final RFP as built drawings, manuals, and other documents as noted. Required as built drawings and specifications will be submitted in the same format required for the construction documents.
D4. Site Visits and Inspections
During the construction period the DB A/E shall make weekly visits to the project site when requested by the Resident Engineer (RE). The
Resident Engineer (RE) may also request visits for special purposes.
Only registered architects and engineers thoroughly familiar with the project may make these site visits. The Resident Engineer (RE) has the prerogative to determine the professional discipline(s) required for any visit. The DB A/E shall observe the construction, advise the
Resident Engineer of any deviations or deficiencies or solutions to issues discussed. A site inspection report which includes the purpose of the inspection, items reviewed, deficiencies observed, recommendations and additional actions required, shall be furnished to the Resident Engineer (RE) within five (5) calendar days following the site visit date.
- - - E N D - - -
Correct Fisher House 1 Life Safety Requirement 01-01-21
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Fisher House 1 located in VA Palo Alto Division as required by drawings and specifications.
B. A pre-proposal conference will be held at FH1 in VAPAHCS on a date and time to be determined. All offerors, consultants, subcontractors, manufacturers, and suppliers are invited to attend. Meeting agendas are listed in Specification Section 00 11
21 Request for Proposal to DB.
C. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection.
Such prior notice shall be not less than five (5) calendar days unless otherwise designated by the COR.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, Fisher House 1 Safety Life Safety Correction: BASE BID:
Work includes general construction, alterations, fire rated enclosure stair, fire/smoke curtains, fireproof self-closing doors, necessary removal of existing structures and construction and certain other items.
01 00 00 -2
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at
Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the
Contracting Officer.
C. Guards (Not Applicable)
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of
01 00 00 -3 project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall install all permanent cores at completion of the work. See Section 08 71 00, DOOR HARDWARE and coordinate.
E. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting
Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of
Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the
VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
a) Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
01 00 00 -4
b) “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted
24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. Limited permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the
Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the
Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of
01 00 00 -5 the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by
Department of Veterans Affairs in quantities sufficient for not more than five (5) calendar days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
01 00 00 -6
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR .
All such actions shall be coordinated with the COR or Utility
Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to
Medical Center Director, COR and Contractor.
J. Not Used
01 00 00 -7
K. Fisher House 1 will be not be occupied during performance of work.
1. Not Used
2. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical
Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
3. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
L. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m
(seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum
375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
M. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C
(40 degrees F) at all times, except as otherwise specified.
01 00 00 -8
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company
(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
N. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.
Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11
REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, at least 15 calendar days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
01 00 00 -9
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical
Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 30 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
O. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
P. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
01 00 00 -10
Q. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting
Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by
Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS"
(FAR 52.236-2) and "CHANGES" (FAR 52.243-4).
C. Re-Survey: Thirty calendar days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall
01 00 00 -11 furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
01 00 00 -12
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.