Attachment 14 - SEED Project 2026 Niagara SABER - PROPOSAL SHEET for Seed Project- OWS RVKQ 24-0010 Install Isolation Valve B919.pdf
PDF 364 KB Posted
- Solicitation number
- FA667026Q0015
About this file
This is a proposal document for the 2026 SABER SEED Project, specifically for Request for Quote (RFQ) 24-0010, detailing the installation of an isolation valve in the inlet piping of Building 919's oil water separator.
The project scope involves installing an isolation valve in the B919 oil water separator inlet piping. The proposal uses a Master Format (MF04) cost structure organized across multiple construction divisions, with primary line items drawn from 01 - General Requirements, 02 - Existing Conditions, 22 - Plumbing, 31 - Earthwork, 32 - Exterior Improvements, and 33 - Utilities. General Requirements items include engineering fees for mechanical work, cost adjustment factors for temporary shoring and security requirements, field personnel costs (general laborers and project managers), permitting, and equipment rental (concrete mixers, backhoes, compactors, rollers, ladders, and trailers). Existing Conditions items address utility removal and selective demolition of utility valves. Plumbing items specify PVC coupling and pipe clamps (10" diameter). Earthwork items include aggregate fill, trench backfill, and structural backfill. Utilities items include a 10" water distribution gate valve with indicator post and 10" diameter HDPE corrugated piping. The proposal incorporates RSMeans NIAGARA FALLS, NY Cost Condition Index (CCI) pricing for Niagara Falls, New York (ZIP 143) and applies a project-level coefficient adjustment. The document provides line item descriptions, unit of measure, quantity fields, unit cost columns, and total cost columns, with provisions for both priced and non-priced line items, though specific pricing values are not populated in this template version.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2026 SABER SEED PROJECT Proposal B919 OWS Install Isolation Valve - RVKQ 24-0010
B919 OWS Install Isolation Valve Install isolation valve in inlet piping of B919 oil water seperator.Project Scope:
Division Summary (MF04) 01 - General Requirements 26 - Electrical 02 - Existing Conditions 27 - Communications 03 - Concrete 28 - Electronic Safety and Security 04 - Masonry 31 - Earthwork 05 - Metals 32 - Exterior Improvements 06 - Wood, Plastics, and Composites 33 - Utilities 07 - Thermal and Moisture Protection 34 - Transportation 08 - Openings 35 - Waterway and Marine Transportation 09 - Finishes 41 - Material Processing and Handling Equipment 10 - Specialties 44 - Pollution Control Equipment 11 - Equipment 46 - Water and Wastewater Equipment 12 - Furnishings 48 - Electric Power Generation 13 - Special Construction Alternate 14 - Conveying Equipment Trades 21 - Fire Suppression Assemblies 22 - Plumbing FMR 23 - Heating, Ventilating, and Air-Conditioning (HVAC) MF04 Total (Without totalling components) 25 - Integrated Automation
Totalling Components RSMeans NIAGARA FALLS, NY CCI Priced Line Items Nonpriced Line Items COEFFICIENT (XX.XXX%)
Material, Labor, and Equipment Totals (No Totalling Components)
Labor:
Equipment:
Other:
Laborhours:
Green Line Items:0
Material:
Priced/Non-Priced Total Priced Items:
Total Non-Priced Items:
Grand Total
Page 1 of 4 B919 OWS Install Isolation Valve - RVKQ 24-0010
Proposal
Totalling Component Details Description Item Count Applicable Amount Applied Amount Applied Result Balance
RSMeans NIAGARA FALLS, NY CCI Included in Total: Yes Type:RSMeans CCI (Project Level) RSMeans NIAGARA FALLS, NY CCI
ZIP:143
Subtotal based on 1 items: "Priced Line Items"
Nonpriced Line Items Included in Total: Yes Type:Total, Master Format Type: MF04 Values:Total Includes: Non Priced Filtering: (none)
Priced Line Items Included in Total: Yes Type:Total, Master Format Type: MF04 Values:Total Includes: Priced Filtering: (none)
COEFFICIENT
Included in Total: Yes Type:Percentage (Project Level)
Page 2 of 4 B919 OWS Install Isolation Valve - RVKQ 24-0010
B919 OWS Install Isolation Valve
Item Quantity Unit CostDescription UM Total Book
01 - General Requirements 1 01-11-31-30-1100 Engineering fees, mechanical (plumbing & HVAC), maximum Contrct
2 01-21-53-50-2350-L Cost adjustment factors, temporary shoring and bracing, add to construction costs for particular job requirements, maximum
Costs
3 01-21-53-60-0120-L Cost adjustment factors, additional costs due to security requirements, daily search of personnel, supplies, equipment and vehicles, daily, physical search, inventory, and documentation of assets, entry
Costs
4 01-31-13-20-0160 Field personnel, general purpose laborer, average Week
5 01-31-13-20-0200 Field personnel, project manager, average Week
6 01-41-26-50-0020 Permits rule of thumb, most cities, minimum Job
7 01-45-23-50-7520 Underground storage tank, volumetric tightness test, <=12,000 gal Ea.
8 01-54-33-10-0400-3 Rent per week for rent bucket concrete lightweight 1.5 CY Ea.
9 01-54-33-10-2000-3 Rent per week for rent mixer power mortar&concrete gas 16 CF Ea.
10 01-54-33-10-2120-1 Hourly operating cost for rent pump concrete truck mounted 4"line 80'boom Ea.
11 01-54-33-20-0470-3 Rent per week for rent backhoe-loader wheel type 112 HP, 1-1/2 CY capacity Ea.
12 01-54-33-20-1300-2 Rent per day for rent vibratory plate compactor gas 18" plate 3000 lb blow Ea.
13 01-54-33-20-3050-2 Rent per day for rent roller, vibratory, tandem, smooth drum, 35 H.P. Ea.
14 01-54-33-40-3300-4 Rent per month for rent extension ladder 16'-36'long Ea.
15 01-54-33-50-4901-4 Rent per month for highway equipment rental, 75 ton low bed trailer Ea.
01 - General Requirements Total
02 - Existing Conditions 16 02-41-13-23-2900 Utility removal, pipe, sewer/water, 12" diameter, remove, excludes excavation, hauling L.F.
17 02-41-13-36-0100 Selective demolition, utility valves & accessories, utility valves, 4"-12", excludes excavation
Ea.
02 - Existing Conditions Total
Page 3 of 4 B919 OWS Install Isolation Valve - RVKQ 24-0010
B919 OWS Install Isolation Valve
Item Quantity Unit CostDescription UM Total Book
22 - Plumbing 18 22-11-13-76-2660 Coupling, plastic, PVC, socket joint, 10", schedule 80 Ea.
19 22-11-13-76-9817 Pipe clamp for suspension, plastic, polypropylene, 10" Ea.
22 - Plumbing Total
31 - Earthwork 20 31-05-16-10-0610 Aggregate for earthwork, select structural fill, includes load at pit and haul, 10 miles round trip, excludes compaction L.C.Y.
21 31-23-23-13-2200 Backfill, trench, 6" to 12" lifts, dozer backfilling, compaction with vibrating roller B.C.Y.
22 31-23-23-14-1000 Backfill, structural, common earth, 55 HP wheeled loader, 50' haul, excludes compaction
L.C.Y.
31 - Earthwork Total
32 - Exterior Improvements 23 32-92-19-14-5200 Seeding athletic fields, seeding utility mix, 7 lb. per M.S.F., push spreader M.S.F.
32 - Exterior Improvements Total
33 - Utilities 24 33-14-19-20-9060 Water utility distribution valve, gate valve, N.R.S. post type, with rubber gaskets, 10" diameter, includes indicator post, excludes excavation and backfill Ea.
25 33-31-11-20-3060 Public sanitary utility sewerage piping, piping HDPE Corrugated Type S with watertight gaskets, 10" diameter, excludes excavation or backfill
L.F.
33 - Utilities Total
Estimate Grand Total
File details come from the government source that posted it. Updated .