Summary: Statement of Work for Simplified Acquisition of Base Engineering Requirements (SABER)

This Statement of Work establishes the requirements for a fixed-price, indefinite delivery/indefinite quantity (IDIQ) contract for maintenance, repair, and minor/new construction services at Niagara Falls Air Reserve Station (NFARS), New York. The contract is effective for 12 months with four optional 12-month periods exercisable at the Government's discretion. The minimum guaranteed contract amount is $5,000, with an estimated maximum of $8,000,000 across all options. Work encompasses diverse construction disciplines including civil, structural, architectural, mechanical, plumbing, electrical, fire protection, communications, environmental remediation, and related trades. Individual task orders (TOs) are anticipated to range from $5,000 to $75,000 (small projects), $75,001 to $300,000 (medium projects), and up to $1,500,000 (large projects). Pricing is structured using the e4Clicks cost estimating software with a Unit Price Guide (UPG) based on RS Means data organized by Construction Specification Institute (CSI) Master Format divisions, supplemented by a Contractor-proposed coefficient multiplier to cover overhead, profit, and indirect costs.

The Contractor must provide a qualified Program Manager and comprehensive project management staff with engineering and administrative capabilities, maintain a management office on NFARS at Contractor expense, and ensure a qualified project manager is on-site 100% during active work hours. Key requirements include submission of comprehensive Quality Control and Safety plans within 30 days of award; preparation of detailed proposals including design drawings, cost estimates, and material submittals for each TO; coordination with multiple Government offices and stakeholders; compliance with Buy American Act requirements; adherence to environmental protection and EMS standards; implementation of Foreign Object Damage (FOD) prevention for airfield-related work; and provision of equipment training to Government employees. The Contractor is responsible for all temporary utilities, site cleanup, debris removal, and restoration activities. Compensation for non-standard working hours, design fees for complex projects, and engineering certifications when specified are allowable line items, while most overhead items are incorporated into the Coefficient. The contract includes comprehensive performance evaluation criteria assessing management effectiveness, schedule adherence, quality control, labor standard compliance, and safety program implementation.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

31 March 2025

FOR

SIMPLIFIED ACQUISITION OF BASE ENGINEERING

REQUIREMENTS

(SABER)

NIAGARA FALLS AIR RESERVE STATION, NY

OFFICE OF THE BASE CIVIL ENGINEER

1. SABER Contracting Vehicle

1.1. SABER Contract

1.1.1. A Simplified Acquisition of Base Engineering Requirements (SABER) Contract is a fixed price, indefinite delivery/indefinite quantity (IDIQ) contract used for a broad range of maintenance, repair, and minor and new construction works on real property.

1.1.2. The Contractor shall coordinate all work under this SABER Contract with the assigned Contracting Officer (CO). The term “Contractor” shall be interpreted to mean the prime Contractor and all its subcontractors. The term “Contracting Officer” shall mean the CO and/or designated representative(s).

1.2. Contracting Officer Authority

1.2.1. Only the CO is authorized to make changes to the Contract or any Task Order (TO) issued thereunder. No other Government or Non-Government official may alter this Contract or any TO issued in accordance with the basic Contract terms and conditions.

The Contractor is to report any attempts to alter this Contract or any TO to the CO. In the event the Contractor effects any such changes at the direction of any person other than the CO, the change will be considered to have been made without authority and no adjustment will be made in the Contract price to cover any increase in costs incurred as a result thereof. The Contractor may also be required by the CO to undo any such changes at no additional expense to the Government.

2. Contract Information

2.1. Contract Location

2.1.1. This SABER Contract is for construction efforts at Niagara Falls Air Force Reserve Station (NFARS), Niagara Falls, New York, for the 914 Civil Engineer Section (914th MSG/CE).

2.1.2. At the Contractor’s discretion, the Contractor will be allowed to maintain a management office on NFARS to perform all general management operations associated with this Contract. The Government will designate a location on NFARS for the Contractor to set up a temporary office facility. Contractor will be responsible for all costs associated with installation and maintenance of a temporary office trailer including electrical and restroom services.

2.1.3. Regardless of whether the Contractor chooses to maintain a management office on the installation, the Contractor shall have a qualified project manager on-site 100% during work hours on any active TO.

2.2. Contract Description

2.2.1. During the SABER contract period, the Government will identify required construction projects and provide a Statement of Work (SOW). The CO will then issue individual Requests for Proposals (RFPs) to the Contractor for which the Contractor shall prepare a proposal as outlined in Section 12 Task Order Proposal Procedures. If the CO approves the proposal, a subsequent TO; as defined by FAR 16.501-1 will be issued to the Contractor for construction completion.

2.2.2. Types of TO projects associated with this Contract include, but are not limited to, new construction and interior/exterior remodeling/renovation/repairs. TO project disciplines may include, but not be limited to: civil, structural, architectural, mechanical, plumbing, carpentry, welding, masonry, communications, intrusion/ detection, audio/ visual systems, and electrical disciplines; petroleum/ oil/ lubricants systems; and asphalt and concrete pavements, sheet metal, various roofing systems, earthworks and landscaping, aerial and underground utilities, power, steam fitting, demolition, painting, HVAC, asbestos removal, and lead abatement.

2.2.3. Individual jobs will vary in size with the majority expected to be of a small ($5,000 to $75,000) to medium size ($75,001 to $300,000) with some large projects ranging from $300,001 to the maximum TO of $1,500,000. The minimum contract amount of $5,000.00 is guaranteed to the successful offeror. The estimated maximum contract amount is $8,000,000.00 including all options, if exercised.

2.3. Overall Period of Performance

2.3.1. This is an Indefinite Quantity Contract for miscellaneous construction projects at NFARS for the 914th MSG/CE, effective for a 12-month period from date of Contract award, with 4 option periods of 12-months each to be exercised at the discretion of the Government.

2.4. High Priority Items

2.4.1. The Contractor’s performance may be interrupted from time to time because of high priority mission schedules. For each calendar day and/or portion of a calendar day that the Contractor is removed from the job site, the performance period will be extended 1 calendar day. The Contractor shall document any delays and request extension of performance period. Liquidated damages will not be assessed for delays caused by the Government.

2.5. Weather Delays

2.5.1. The Contractor shall log any weather events that impact performance of the TO.

The log shall include; date of weather event, time period effected, type of weather event, description of all work effected by the weather event. The CO will review all requests for weather delays, taking into account adverse weather conditions not reasonably anticipatable for NFARS and the time of the year, the weather event (type, duration), the work effected. The CO will determine; if the weather event is beyond reasonable anticipation, and the impact on the completion of the TO. After review the CO will determine if weather delays will be assessed against the TO and alter the completion date accordingly.

2.6. Government Liability

2.6.1. The Government shall not be held liable for Contractor expense due to damage or loss of Contractor property, including stock, or for expenses incidental to such damage or loss.

2.7. Liquidated Damages

2.7.1. Liquidated damages shall be defined for each TO in the TO RFP and may be assessed if the Contractor fails to complete the work within the time specified in the TO.

2.8. Buy American Act

2.8.1. All supplies and construction materials shall be purchased in accordance with the Buy American Act (40 U.S.C. 10a-10d). The purchase of supplies is governed by FAR

25.1 Buy American Act – Supplies, and the purchase of construction materials is governed by FAR 25.2 Buy American Act – Construction Materials.

2.9. Meeting Schedule Requirements

2.9.1. Progress Meetings: For the duration of the SABER Contract, including option years, at the CO’s discretion progress meetings will be held every 2 weeks between the CO, SABER Team and Contractor’s team. Progress meetings may require corporate management representation at the CO’s discretion.

2.9.2. Pre-Performance Meeting: Prior to issuance of a TO Award for any TO, the CO may elect to host a Pre-Performance Meeting. The Contractor and subcontractors shall be represented at the scheduled meeting and be prepared to discuss potential difficulties, obstacles, conceptual level approach, and the Erosion and Sedimentation Control Plan, if relevant, for the TO.

2.9.3. Pre-Construction Conference: After the issuance of a TO Award for any TO, the Contractor shall meet with the CO prior to the commencement of any work to discuss any issues pertaining to the work. During this meeting, the CO will provide the Contractor with site storage and parking areas. Any Government Furnished Property required for the TO shall be distributed or arranged to be distributed to the Contractor.

2.9.4. Pre-Construction Safety Meeting: For each TO issued, representatives of the Contractor shall meet with the CO prior to the start of repair, alteration, or construction activities for the purpose of reviewing the Contractor’s safety and health programs and discussing implementation of all safety and health provisions pertinent to the work to be performed under the Contract. The Contractor shall be prepared to discuss, in detail, the measures he/she intends to take in order to control any unsafe or unhealthy conditions associated with the work to be performed under the Contract. This meeting may be held in conjunction with the Pre-Construction Conference, if elected by the CO. The conduct of this meeting is not contingent upon a general Pre-Construction Conference. The level of detail for the safety meeting is dependent upon the nature of the work and the potential inherent hazards. The Contractor’s principal onsite representative(s), the general superintendent, and his/her safety representative(s) shall attend this meeting.

2.9.5. For all meetings, the Contractor shall prepare, publish, and submit meeting minutes for CO approval. Meeting minutes shall track all action items assigned, document all items discussed at the meeting, and record the meeting’s attendees. Meeting minutes shall be published no later than 5 working days following meeting dates.

2.10. Government Project Management

2.10.1. The CO shall maintain control over the SABER Contract and all TOs issued under the Contract; however, technical elements of the TOs are the responsibility of the Base Civil Engineer (BCE).

2.10.2. The BCE reserves the right to assign a Government-provided Contracting Officer’s Representative (COR) to monitor Contractor progress, and identify non-compliance items while performing technical surveillance of workmanship. The COR must have access to the job site whenever work is being performed and, as a minimum, during the described work hours. This in no way authorizes ANYONE, except the CO, the right to commit the Government financially, or contractually, by making changes to the Contract. The COR and Superintendent may jointly agree to a No-Cost Field Change, which appears to be mutually beneficial to all involved, but all field changes must be approved by the CO prior to accomplishment. The COR does not relieve the Contractor of his/her own quality control and construction inspection to ensure all applicable standards are met.

2.10.3. Site Inspections

2.10.4. Inspection of work by the Government will normally be accomplished along with the work as it progresses. At the discretion of the CO, inspection may be directed at the completion of various phases of the work prior to initiation of any further work. The Contractor shall notify the CO that a phase will be complete at least 3 days in advance of the completion of each phase to be inspected.

2.10.5. Prior to covering, enclosing, or hiding any of type work, the Contractor shall contact the CO to perform an inspection. Failures to have the CO or his/her representative perform inspection prior to concealment shall result in the Contractor being required to uncover performed work sufficiently to allow for proper inspection, at no additional cost to the government.

2.11. Freedom of Information Act

2.11.1. The Contractor shall comply with Department of Defense (DoD) Regulation 5400.7/Air Force Supplement, DoD Freedom of Information Act Program requirements.

The regulation sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding For Official Use Only material.

2.12. SABER Contract Technical Specifications

2.12.1. The Technical Specifications, are numbered and organized by the latest edition of the Construction Specification Institute’s (CSI) Master Format. All specifications are filed in Divisions 1 through 48 per CSI guidelines.

2.12.2. The intent of these specifications is to furnish concise industrial and/or commercial standards for maintenance, repair, and minor construction of Government facilities.

2.13. Unit Price Guide (UPG)

2.13.1. The UPG contains pricing information for the description of the work to be accomplished in the unit of measure specified. Unless otherwise specified in the UPG, prices given include all material, direct and indirect; labor; testing; and equipment costs to complete the item of work described. Indirect materials shall be defined as materials associated as integral to the installation of an item without which the item cannot be properly installed. No additional line items (priced or non-priced) shall be added to supplement the UPG costs. See paragraph 7.2.2 Coefficients, for items that are disallowed in TO pricing.

2.13.2. The UPG consists of Divisions 1 through 48, which are based on the Master CSI.

Also see section 7.5.

2.13.3. If the Government specifies an item which meets both the UPG definition AND the characteristics called out in the Technical Specifications, the Contractor is obliged to furnish that item, regardless of actual cost compared to the UPG cost.

2.14. Sample Calculation. The following sample calculation illustrates the use of the UPG.

All dollar figures are fictitious and therefore may or may not exist in the UPG used for this contract.

DESCRIPTION OF WORK: Remove existing 11’ x 15’ x 6” thick concrete parking apron and replace with 4000 PSI concrete.

DEMOLITION: 11x15x.5/27= 83/27=3 CY, 11x15/9= 18 SY

REPAIR

BASE - 11x15x.17/27= 1 CY CONC - 11x15x.5/27= 3 CY MESH - 11x15= 165 SF

FORMWORK - 11+ 11 +15 + 15= 52 LF

SAMPLE CONTRACTOR PROPOSAL FOR: PARKING APRON DEMOLITION & REPAIR

Line Unit Price Item # UPG # Description Qty Bare Cost Total

EXISITN CIBDUTUIBS

0001 02-41-19-19-3080 Selective Demo, Rubbish Handling 3 CY @$17.70/CY $53.10

CONCRETE

0002 03-05-05-10-0060 Selective Demo, Concrete 3 CY @$110.30/CY $330.90 0003 03-11-13-65-1420 Form Work 52 LF @$2.79/LF $145.08 0004 03-22-11-10-0400 Welded Wire 1.65CSF @$63.00/CSF $103.95 0005 03-31-13-35-0300 Concrete (400psi) 3 CY @$113.00/CY $339.00 0006 03-31-13-35-0300-1520 Concrete Modifier 1 EA @$74.50/EA $74.50 0007 03-31-13-70-4300 Placing Concrete 3 CY @$17.83/CY $53.49 0008 03-35-13-30-0100 Concrete Finishing 165 SF @$0.26/SF $42.90 0009 03-39-23-13-0300 Concrete Curing Compound 1.65CSF @$19.10/CSF $31.52

EXTERIOIR IMPROVEMENTS

0010 32-11-23-23-0400 Base Course 18 SY @$8.87/SY $159.66 0011 32-13-13-23-0530 Concrete Surface Treatment 18 SY @$7.32/SY $131.76

$1465.86

TOTAL DIRECT COST: $1465.86

LOCATION FACTOR (2016 2nd Qtr) 0.8910

SUB TOTAL $1306.08

*PERCENTAGE FACTOR: x 1.05*

TOTAL PRICE $1371.38

*Assumes fictitious Coefficient of 1.05 for standard working hours.

NOTE: UPG#s are from the 2015 Facilities Construction Cost Data Book

3. Project Requirement Types. The two types of project requirements are “Routine” and “Emergency.” Either of these types may be issued at any time during the length of this contract.

The Government is responsible for determination of project requirement type. A pre-determination of project type to be disclosed prior to solicitation.

3.1. Routine Requirement. Within three (3) calendar days of project notification, unless otherwise directed by the CO, the Program Manager (PM), or authorized representative(s) shall attend a Pre-Proposal Site Visit to clarify any project requirements, and/or further define the project objective/scope of work. This meeting will be used to develop the government’s SOW and subsequent funding request. If funded the CO will issue a Request for Proposal (RFP) to the contractor. The Contractor’s proposal shall be submitted to the CO in accordance with the RFP letter for all work.

3.2. Emergency Requirement. In the event of an emergency or time sensitive requirement, the Contractor Program Manager, or authorized representative(s) response time shall be as soon as directed by the CO. The Contractor’s proposal shall be submitted IAW paragraph 5, or as directed by the CO, normally within 24 hours.

4. Commencement Documents. Contractor design documents shall be developed so that a distinction is made between items that are associated with each classification of work (i.e.

Demolition, Minor (new) Construction, Repair, and Additives). See Statement of Work (SOW) paragraph 12 for “Task Order Proposal Procedures”. Categories of work notes shall be affixed throughout the contract documents to clearly distinguish between works that are Demolition (D), Minor Construction (MC), or Repair (R) and further delineate any items that are Additive Bid Items (reflected as “Option #”) and shall be accounted for and priced separately in the price proposal. The concept of the SABER program provides for a minimum of 35% design level effort. However, some portions of a design may require up to a 65% to 80% design effort depending upon nature/complexity (i.e., some mechanical/electrical).

4.1. A 100% design level effort may be necessary when Professional Engineer (PE) Certification is required. In the case of 65% to 80% design or 100% design level of effort;

Base Civil Engineering will identify the requirement in advance and will identify what the Contractor is responsible for designing.

4.2. Statement of Work (SOW): The initial document, with drawings where applicable, provided to the Contractor by the Government outlining the work to be completed. The SOW may also detail a required or desired performance period.

5. Contractor’s Proposal Package. The proposal package includes written descriptions documenting the detailed work elements required by each Government RFP prepared by the Contractor from the SOW. The Contractor shall submit for Government review, one electronic (by e-mail) copy of the price proposal for technical evaluation, presenting the Contractor’s offer as determined by the Government. The Contractor pricing shall be submitted in the following formats; (1) pdf by line item list, (1) e4clicks estimate by line item list. The Contractor’s design shall be IAW paragraph 5.10. The format shall as a minimum include: a detailed cost estimate (in the authorized format); all Government requested project design drawings and thorough applicable design calculations IAW paragraph 5.8 thru 5.11 and a Material Submittal Schedule (AF 66) reflecting proposed product submissions and required contract reports. When the Contractor desires to offer alternatives, they shall: clearly state and identify alternatives proposed; their segregated associative costs; a delineation of impacted line items; and advantages and disadvantages for Government evaluation. The Contractor shall provide support, verification and justified reasoning behind their proposal to alter the Government’s project request.

5.1. Technical Plan. The Contractor shall develop a detailed project technical plan incorporating all elements of the agreed upon proposal, SOW, all applicable Base, Local, State and Federal regulations, and all comments and or mitigations identified on the project SOW. All elements of the price proposal shall be captured in the technical plan and drawings. The awarded negotiated price proposal shall be used for reference to verify scope or drawing omissions if necessary, however the preference and intent is for all elements of work and major items for installation to be on the plan and drawings.

5.2. Cost Estimates. Cost estimates shall be calculated using the e4clicks, see paragraph 7.

5.3. AF Form 66, Schedule of Material Submittals (AF 66). For each project request, the Contractor shall provide one copy of an AF 66 reflecting all proposed materials and required contract documents to the CO for approval. The AF 66 shall be submitted as part of the Contractor’s proposal package (Para. 5). The AF 66 is a living document, and shall be updated, with items added to the form, as necessary by the Contractor for approval, and/or as required by the CO or authorized representative throughout the life of the TO.

5.4. Preliminary Drawings: The Contractor shall submit preliminary drawings via Material Submittal Form AF IMT 3000 at the time of the submission of a proposal for all TO that require drawings. Preliminary drawings will be required for all projects where there is any deviation to existing conditions by work performed under a SABER TO. Preliminary drawings will include dimensions, utility lines, foundation plans, floor plans, elevation views, roofing plans, shop drawings; layout of walls, doors, windows; finish schedules, plumbing plans, riser diagrams, HVAC plans, duct work, control systems, fire sprinkler and detection systems, electrical plans, schematics, lighting, receptacles, switches, panels, panel schedules, any pertinent sections and details, etc. Preliminary drawings will be completed to the point the Government representative can verify size, shape, quantity and type materials proposed in the Contractor’s price proposal. The Contractor shall be responsible for the reproduction of these drawings if multiple copies are needed (i.e., Sub-contractor copies).

5.5. Material Approval Submittal Form (AF IMT 3000): Material submittals are required for all materials being submitted on any given TO. Any other items (e.g. Progress Schedules, Dig Permits, Test Reports, As-Builts, O&M Manuals) requiring approval that have not been required to be submitted earlier with the Contractor’s proposal package shall be submitted by the Contractor using AF IMT 3000. These type submittals shall be submitted no later than ten

(10) working days after the issuance of the “Notice to Proceed” (NTP) or as otherwise directed by the CO. The Government will provide space for a submittal sample display area.

The Contractor shall install, catalog and maintain submittals, as approved, to avoid repetitive duplication in subsequent TO. The Contractor will not order any type of materials until the Material Approval Form has been signed and approved by all parties. If the submittal has been disapproved, the explanation will be noted in the back of the Material Approval Form and shall then be resubmitted in the time frame noted on the Material Approval Form. 914th MSG/CE may provide a list of expected AF IMT 3000 for each TO. Requirements for submittals no later than five (5) working days after issuance of the NTP are:

5.5.1. Submission Requirements. The Contractor shall submit to the CO all required documents and samples for a particular item on the approved List of Submittals as a group package. Partial submittals for product approval will be returned without action and shall be the sole responsibility of the Contractor for any delays due to this failure to comply. All printed documents shall be legible, and as a minimum, one shall be an original version (not copied nor Fax generated). When multiple items are included on printed documents, the Contractor shall mark/ highlight all applicable data regarding the item presented for approval. The Contractor shall mark/ highlight product data showing where the material or item being submitted meets the requirements of the specifications, UFCs, NFPAs, etc.

5.5.2. Material Samples. The Contractor is responsible for identifying and locating required materials for submittals to include matching any existing materials. The Contractor shall provide all color selection samples, regardless of product type, as a group to facilitate design compatibility selection, and partial submittals of these related items will be returned without action and shall be the sole responsibility of the Contractor for any delays due to this failure to comply. As a minimum, all wall covering, carpet and other pattern type submittals shall show the full representation of material pattern. All samples provided for approval shall become property of the Government. The Contractor may request return of samples for inclusion on color boards or as submittal library entries, without guarantee of approval.

5.5.3. Color Boards. The Contractor shall provide, after color selection and material approval, one (1) color board for all architectural work as required by the TO. Note, this is required only if directed by the TO. All products shall be mounted on foam board, and grouped in logical sequence as installed (i.e. carpet, paneling, chair-rail, wall covering and ceiling tile). All products shall be referenced with the manufacturers name and color/pattern/style name and number.

5.5.4. Operation and Maintenance (O & M) Manuals. The Contractor shall provide, two

(2) copies of operation and maintenance manuals as specified on the Government reviewed, and approved List of Submittals (or equal). One (1) complete set shall be provided prior to field-testing, and the remainder upon equipment acceptance. Manuals shall be approved prior to the field-training course. Operating manuals shall detail the step-by-step procedures required for system startup, operation and shutdown. Operating manuals shall include the manufacturers name, model number, parts list, and brief description of all equipment and their basic operating features. Maintenance manuals shall list routine maintenance procedures, possible breakdowns and repairs, and troubleshooting guides. Maintenance manuals shall include piping and equipment layout, simplified wiring and control diagrams of the system as installed, and system programming schedule. The contractor shall compile a maintenance schedule for all equipment in the TO identifying; equipment, consumables, schedule of maintenance, and any other notes.

5.5.5. Submittal Library. The Contractor shall establish and maintain the submittal library to eliminate repetition and streamline the submission processes for subsequent TO. One

(1) library shall be maintained at the 914th MSG/CE Office and one (1) library at the Contractor’s office. The Contractor is responsible for providing all library documentation/samples at no additional cost to the Government. Once a product is approved, future requirements for the same type item may be referenced to library entries. The Contractor may suggest product inclusion at any time during the contract. A numbering system shall be developed in concert with the CO and 914th MSG/CE to identify all library entries. The Contractor shall catalog and maintain all submittals to avoid duplicate library entries. The Contractor is not restricted to products included in the library, but rather encouraged to propose multiple like items to provide flexibility in future projects.

5.6. Record Drawings/As-Builts. The Contractor will have full access to all Record and As- Built drawings located in 914th MSG/CE as required for development of the Contractor’s design. The Contractor may obtain one (1) copy of the appropriate record drawings, if available, from 914th MSG/CE. The Government does not guarantee the availability, accuracy or adequacy of existing As-Built or record drawings. During the progress of the work, the Contractor shall keep a careful record at the job site of all changes and corrections (Red Line Drawings) from the layouts shown on the preliminary drawings submitted with their proposal, when applicable. The Contractor shall enter such changes and corrections on preliminary drawings promptly, and submit drawings to the CO in accordance with schedule provided in the TO. The As-Built drawings shall indicate, in addition to all changes and corrections; any uncovered electrical, piping or mechanical lines not shown on the drawings, existing construction that is not noted on the record drawings, the actual location of all subsurface utility lines, existing or new. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered or obscured, the record drawings shall show, by offset dimensions to two (or three if height changes) permanently fixed surface features, the end of each run including each change in direction. Valves, splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The depth below the surface of each run shall be recorded, in addition to the size and type of conduit or pipe used for the run.

At the time of beneficial occupancy of each structure or facility involved under the contract, the Contractor shall submit to the CO As-Built plans with the aforementioned data. In addition to the requirement for As-Builts at final inspection, As-Built drawings shall be required, unless noted in the TO, for all projects or where there is any deviation to existing conditions by work performed under a SABER TO. As-Built drawings shall be submitted for approval no later than the date of the final inspection. The Contractor shall provide approved As-Built drawings in both a hard copy format (Mylar copy) as well as a Contractor provided CD compatible with the 914th MSG/CE AutoCAD, or computer aided drafting/design software compatible with Government drafting/design software and computers for all TO.

The contractor shall include a line item for As-Built drawings in all progress schedules.

5.6.1. As-Built drawings shall be submitted in a version of AutoCAD that is coordinated with 914th MSG/CE drafting section at time of submission. The As-Built DWG files shall have no reference files attached as all shall be bound into the file to make one AutoCAD DWG file, which also shall be purged and created with standard AutoCAD pen table.

Scaled drawings should provide a bar scale and shall be in imperial system units.

Contractor shall provide one (1) hard copy of As-Built on Mylar on an Arch D sheet size and one (1) CD in AutoCAD and PDF. Final As-Builts shall include the assigned building number in the title block.

5.6.1.1. AutoCAD drawings shall have correct geometry:

5.6.1.1.1. Segmented lines and arcs are to be made continuous and free of self-overlapping sections, thus decreasing files size and increasing efficiency within the AutoCAD platform.

5.6.1.1.2. All AutoCAD data shall be free of topological errors such as slivers, undershoots, overshoots dangles, overlaps, intersections, etc.

5.6.1.1.3. Area features such as building footprints, parking lots, roadways, and airfield pavements shall be true polyline polygons. Adjacent polygons shall not have gaps or overlaps.

5.6.1.2. AutoCAD drawings shall be checked for correct spatial projection to one of the following:

5.6.1.2.1. North American Datum 1983 State Plane: New York State West FIPS 3103 International Feet

5.6.1.2.2. Universal Transverse Mercator 1984, Zone 17 North

5.6.1.3. Drawings submitted for approval as As-Builts shall have all changes incorporated into the final drawings.

5.6.1.4. Drawings shall be free of revision clouds, hand-written notes, scanned in change orders, etc.

5.6.1.5. Revision symbols shall be accompanied with an entry in the sheet’s revision block. Revision block entries shall consist of a brief description of the change along with the change order number.

5.6.1.6. Each sheet shall be annotated in bold letters near the title block with the date the As-Builts were accepted (i.e. AS-BUILT DRAWING 12 APR 2025).

5.6.1.7. Title sheet shall have a vicinity map, project location map, sheet index, and key plan.

5.7. Survey and Mapping Requirements

5.7.1. The Contractor must be capable of surveying to lay out the project work sites to perform its work and where grading or drainage is involved. Drawings shall clearly indicate both existing and new spot elevations and Bench Marks. Survey and mapping requirements shall be defined in each TO or as directed by the CO.

5.7.2. Work outside the boundary of existing footprints of buildings and structures shall require the submission of geospatial/mapping data. This includes, but is not limited to, building and structure footprints, utilities, infrastructure, survey data, etc.

Contract requirements for the collection and delivery of georeferenced geospatial data shall specify either mapping or survey grade Global Positioning System or traditional survey methods of data collection. All projections should be provided as noted in

5.6.1.2. The use of either mapping or survey grade Global Positioning System technology will depend on the precision requirements of the data. Deliverables that involve digital maps or other geospatial data must be delivered in a georeferenced GIS format which would include Environmental Systems Research Institute’s shapefile and geodatabase formats. Detailed specifications for data precision, data collection, attribution, and file format delivery should be included in each contract.

5.7.3. All deliverables that involve maps or other geospatial data must meet the following requirements:

5.7.3.1. All maps and associated data must comply with the latest version of Spatial Data Standards for Facilities, Infrastructure, and Environmental (SDSFIE). This data will be organized using the latest SDSFIE 2.3 Specifications for file, feature class and attribute nomenclature. Guidance on the latest version of SDSFIE is available from the Chief of Engineering and Planning. Information must be collected at no less than 1:400 scale for base cantonment areas and 1:600 for large undeveloped base areas. Spatial data will meet or exceed National Map Accuracy Standards at those scales. Metadata will be provided and will use Federal Geographic Data Committee, Content Standards for Digital Geospatial Metadata for organization.

5.7.3.2. Geospatial data must be delivered in a georeferenced GIS format (feature-based file structures, including one-to-one cardinality between spatial records and attribute records). All attribute data as specifically outlined in the TO Contract must be included either in the GIS data file or as a separate table with a SDSFIE key variable that may be used to relationally join the separate table with the GIS data file. All geospatial data must be delivered in UTM: World Geodetic System of 1984 projection. Further guidance on mapping units, coordinate systems and projections is available from the base Civil Engineering section, Chief Engineering and Planning.

5.7.3.3. Mapping or Survey Grade Global Positioning System or comparable traditional survey methods will be used to collect geospatial data. The use of mapping or survey grade Global Positioning System will depend on the precision requirements of the data. These requirements will be identified in the RFP for all activities where geospatial data are involved. In the case of RFPs involving utility construction, location and attribute data will be obtained at the time of excavation.

Further information about precision requirements should be obtained from the base Civil Engineering section, Chief Engineering and Planning.

5.8. Design Review. Applicable to all TO prepared for design, prior to submitting a Contractor proposal package, the Contractor shall field verify the existing site conditions to satisfy itself with the general and local conditions that can affect the work. The Contractor may make multiple site visits. The Contractor will have full access to all Record and As-Built drawings possessed by, and located in, 914th MSG/CE as required for development of the Contractor’s design. The Contractor is responsible for accuracy of all measurements whether they are obtained in the field, or as existing drawing take-offs to develop accurate working drawings. It shall be noted that minor adjustments of new utility lines may be required to avoid existing underground utility lines or existing structures. All plans, labor, equipment, materials, and incidentals shall be furnished by the Contractor, unless otherwise specified.

The Contractor shall thoroughly review the project request for constructability and advise the Government of possible problem areas prior to project negotiations.

5.9. Professional Engineer (PE) Certification. The TO request may require PE Certification on some or all designs, or portions of designs. Typically, all new electrical power distribution designs; all new boiler/ heating, new ventilation and air conditioning designs if determined complex by the Government (to include temporary requirements); all structural designs, to include entrance canopies, and all sprinkler designs shall require PE certification. Large-scale, new landscaping and irrigation when requested shall be designed by a certified Landscape Architect. Applicable Engineering Fee line items in the UPG may be utilized for PE Certification when deemed necessary by the Government.

5.10. Design Guidance, Specific. This guidance shall be used as applicable to specific projects.

5.10.1. Civil. All design calculations shall be submitted for approval/review with the proposal package IAW paragraphs 5.8 and 5.10.

5.10.1.1. Earthwork. All contouring of terrain shall be pitched for positive drainage. Where reasonable, the Contractor shall install pipe materials using a directional drilling or boring to avoid or minimize root damage to existing trees or under roadways as directed by the TO. All fill materials shall be environmentally "clean" and exhibit no contamination. The Contractor shall provide sampling/analysis results from all borrow sources for topsoil or fill when requested by the Government. Soil shall only be obtained from approved borrow sources.

5.10.1.2. Excavations. The Contractor shall backfill and properly compact all excavations. Trenches shall be top dressed with topsoil IAW paragraph 5.10.1.5.

5.10.1.3. Landscaping. New facilities design shall include adequate landscaping of the site. Ensure landscape layout and schedule are provided. Provide for trees, shrubs and ground cover.

5.10.1.4. Soils and Vegetation Restoration. In addition to the requirements in FAR clause 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements, the Contractor shall restore all areas affected by worksite operations to include all haul roadways prior to final inspection. The Contractor shall not delay soil restoration operations until the end of worksite operations or TO. The Contractor shall promptly restore all disturbed grounds immediately upon final backfilling.

5.10.1.5. Topsoil. The Contractor shall provide rock-free, natural, friable topsoil containing no more than 10% organic material, and shall contain sandy loam. It shall be obtained from naturally well-drained areas, and shall not be excessively acid or alkaline, nor contain substances harmful to plant growth. Topsoil shall be distributed uniformly to provide a minimum thickness of 4 inches on properly compacted sub-grade. The sub-grade shall be hand raked, disked, or tilled appropriately to ensure water will percolate through the soil and avoid “hardpan” conditions. Topsoil shall be spread to minimize additional soil preparation or tillage. Sub-grade and topsoil shall be damp and frost-free. Topsoil shall not be placed when sub-grade is frozen, excessively wet, extremely dry, excessively compacted, or in a condition detrimental to the proposed planting or grading. The Contractor shall provide a minimum of four

(4) inches topsoil at all excavations performed in vegetation areas. The Contractor shall rake prior to sodding and/or seeding to level topsoil and eliminate all mounds/clods/ruts and rocks larger than a 3/8-inch diameter, and ensure positive drainage. All topsoil shall be environmentally "clean".

5.10.1.6. Grass. All grasses shall be established by sod or hydro seed methods.

Hand/broadcast seeding is unauthorized. All grasses shall be provided on grounds graded for positive drainage. All grasses shall have 90% coverage prior to acceptance.

The Contractor shall maintain the turf until accepted by the Government. The turf shall be reseeded (if required) within five (5) calendar days of notice by the CO, at no additional cost the Government.

5.10.1.6.1. Improved Areas. The following seed mixture shall be used in improved areas on base. A seed mixture of 40% Kentucky bluegrass, 40% tall fescue, and 20% annual ryegrass (Lolium multiflorm). Aroostock ryegrass should be substituted for annual ryegrass for late fall or early spring plantings. The seed mixture will contain a minimum pure live seed content of 70%. Seed will be distributed evenly at a rate of 2.75 pounds per 1,000 feet.

5.10.1.6.2. Restricted Areas (inside flightline fenceline). The following seed mixture shall be used in restricted areas on base. Tall fescue (Festuca arundinacea). The seed mixture will contain a minimum pure live seed content of 70%. Seed will be distributed evenly at a rate of 2.75 pounds per 1,000 feet.

5.10.1.7. Tree Locations. The Contractor shall stake each tree location for approval by the CO prior to planting.

5.10.2. Architectural/Structural. All exterior and interior colors, finishes, and construction materials shall be compatible with existing color and styles per the latest approved Installation Facility Standards, unless otherwise specified. All new work shall be IAW the TO, the National Fire Protection Agency (NFPA), Life Safety Code 101. All design calculations shall be submitted for approval/review with the proposal package IAW paragraphs 5.8 and 5.10.

5.10.2.1. Sensitive Compartmented Information Facility (SCIF). SCIFs and vaults shall comply with Intelligence Community Technical Specification for ICD/ICS 705, Version 1.3 or the most current edition. The Contractor shall be responsible for ensuring that the finished product is adequately constructed to attain certification as described in the technical specification. Any design deficiencies that need correction in order to attain certification shall be the sole responsibility of the Contractor at no additional cost to the Government.

5.10.2.2. Concrete. The Contractor shall provide proper protection from weather and physical damage for curing to all new concrete for a period IAW industry standards, but not less than fourteen (14) days. The use of curing compounds, where required, shall be approved by the CO and shall be clear in color, forming a continuous, opaque coating to exposed concrete surfaces. Finish and color of new concrete for repairs shall match existing adjacent concrete surfaces.

5.10.2.3. Bollards. All new mechanical or electrical installations (i.e. transformers, substations, condensing units, gas meters, etc.) near driveways or parking areas, etc.

where they are subject to vehicular traffic shall have 6” pipe bollards installed to prevent damage. Bollards shall be set in the ground in concrete and with reflective yellow HDPE bollard covers, and have a 6” crown of reflective yellow or painted if approved by the CO.

5.10.2.4. Locksets. Provide Best Access, CorMax (7 pin) cores or approved equal for all new locksets in Base facilities. Contractor to provide minimum of 2 sets of keys for all locksets provided. Contractor to turn-in to CE all lockets removed as part of demolition on all TOs. Key series shall be ordered with an account ID provided by the government to maintain compatibility with master and control keys.

5.10.2.5. Suspended Acoustical Ceilings. New ceiling panels shall be reveal or tegular edges. The panels shall be; Armstrong #934 random textured tegular edge panel, #935 random textured square edge panel, USG Radar 2207 square edge panel, USG Radar 2227 tegular edge panel, or approved equal. If replacing a portion of ceiling panels in a room the panel selection shall be in kind as approved by the CO.

5.10.2.6. Doors. All wood doors shall be solid core. No particleboard shall be allowed unless otherwise specified. All new unpainted doors shall have a natural oak finish, unless otherwise specified. Aluminum entrance doors or storefronts shall be anodized bronze, or painted with an approved finish. Selected finish shall match adjacent existing unless otherwise specified. All extrusions shall be uniform in color and match each other so that the overall product appears uniform in color.

5.10.2.7. Finishes/Schedules/Color Boards.

5.10.2.7.1. Carpet/Carpet Tiles. All carpet/carpet tiles shall be Mannington Mills Inc, Gametime III, style: GT35M, color: Cobb, unless otherwise directed by the TO. If replacing a portion of carpet tile in a room the tile selection shall be in kind as approved by the CO.

5.10.2.7.2. Wall Covering. All wall coverings shall be IAW the latest edition of NFARS’s Architectural Compatibility Plan or IFS unless otherwise directed by the CO.

5.10.2.7.3. Finish Schedule/Color Boards. When directed by the TO. All surfaces being modified or developed shall be included in a finish schedule on the drawings and/or the technical plan. The Contractor shall assemble and submit color boards IAW paragraph 5.5.3 when requested by the Government.

5.10.2.7.4. Door/ Window Schedule. A door and/ or window schedule shall be included on project drawings for all new and/ or replacement doors/ windows.

5.10.2.7.5. Exposed Metal Flashing and Coping. All exposed metal flashing and coping shall match adjacent trim surfaces, unless otherwise directed by the CO.

5.10.3. Mechanical. Design calculations shall be submitted with all mechanical plans for review. All design calculations shall be submitted for approval/review with the SOW package IAW paragraphs 5.8 and 5.10. All work shall be performed to industry standard and all applicable building codes.

5.10.3.1. Boiler/Heating, Ventilation, and Air Conditioning (HVAC) Systems. All boiler/HVAC designs shall be Professional Engineer (PE) Certified when requested.

Provide adequate boiler/HVAC systems as required for year-round comfort, to include necessary humidity controls. Where natural gas service is available, install gas furnaces and water heaters. The 914 MSG/CE will notify 914th MSG/CEV Environmental Air Program Manager of all new permanent and temporary boiler systems. All refrigerants and work on refrigerant systems shall be in accordance with 40 CFR Part 82, Subpart F – Recycling and Emissions Reduction, during HVAC equipment repairs/demolition. Replacement of any refrigerant containing unit cannot utilize Class I or Class II Ozone Depleting Substances (ODS) per 40 CFR 82.154 c (1). Air Conditioning units that have a SEER rating shall have a minimum Seasonal Energy Efficiency Ratio (SEER) 16 rating. Refrigerant removed from a Chiller unit during demolition of a Chiller unit shall be turned over to the Government. The Government will provide the storage container for the recovered refrigerant. All refrigerant recovery is coordinated through the BOS Contractor.

5.10.3.2. Fresh Air Intakes. All new HVAC system designs, and when feasible, renovations of existing designs, shall locate intakes close to the top edge of the facility rather than at first floor levels. Roof mounted intakes shall only be used when wall mounted intakes are not feasible. Sloped roof intakes shall be mounted to the rear, or least visible side of the roof where standing water does not exist. Heavy gauge expanded metal, with an integral filter, shall be constructed over the wind/rain louvers to preclude direct access to the interior ductwork.

5.10.3.3. Equipment Manufacturers. All chillers, heat pumps, furnaces, Air Handling Units (AHU) shall be approved by the Government prior to purchase and installation.

5.10.3.4. Equipment Siting. When siting boiler/ HVAC units, provide for locations where units can be properly maintained and easily accessible. Avoid placing HVAC units on roofs. To minimize loss of usable floor space, provide for air conditioning equipment designed for outdoor installation where possible. Ensure required ductwork is not installed on the exterior of buildings where it is highly visible.

5.10.3.5. Mechanical Systems Testing. All new boiler/ HVAC systems shall be tested and balanced by an independent firm with a formal Test and Balance Report (TABS), unless otherwise specified, and submitted on an AF IMT 3000. All existing boiler/ HVAC systems shall be field verified by the Contractor for operability for design purposes. The Contractor shall submit existing system field verification results with the applicable design calculations for approval/ review with the proposal package IAW paragraphs 5.8 and 5.10. TABS shall be submitted upon completion of installation and prior to final inspection.

5.10.3.6. Temporary Boiler/ HVAC Requirements. The Contractor shall provide temporary boilers/ HVAC equipment to all facilities remaining in operation, unless otherwise specified. All labor, equipment, materials and rentals/fees required to provide temporary boiler/ HVAC shall be separately annotated as an option item on all applicable proposal packages. Air conditioning systems are required to be operational from 15 May through 15 October and the heating systems are required to be operational from 16 October through 31 May. The Contractor shall submit for approval, drawings and calculations of proposed methods with the Contractor’s proposal package.

5.10.3.7. Direct Digital Control (DDC) Systems. The Contractor shall verify with the 914th MSG/CE Project Manager, the use or inclusion of DDC systems in their design whenever any HVAC upgrades or new construction is to be performed. Projects where new buildings are constructed or major upgrades to HVAC are performed, the Contractor shall provide for DDC Systems support unless otherwise specified.

5.10.3.7.1. DDC System Requirements: 23 February 2017

5.10.3.7.1.1. Provide an extension of the existing “Base-Wide” Schneider Electric Andover Controls Direct Digital Control system. The control system shall consist of sensors, indicators, actuators, final control elements, interface equipment, other apparatus, accessories, and software connected to distributed controllers operating in multiuser, multitasking environment on token-passing network and programmed to control mechanical systems. An operator workstation permits interface with the network via dynamic color graphics with each mechanical system, building floor plan, and control device depicted by point-and-click graphics.

5.10.3.7.1.2. The DDC system shall be compatible and communicate with the existing or future base wide system as determined by the TO. The existing base wide system is Schneider Electric Andover Controls but expectations are for future controllers to be compatible with the Schneider Electric EcoStruxure platform The system shall be controlled and monitored from the existing workstations in building 403 and 426.

5.10.3.7.1.3. Provide modular DDC controllers, comprised of a processor board with programmable, random-access memory and backup power source.

DDC controllers shall monitor or control each I/O point, process information, execute commands from other control units, devices and operator stations and download from or upload to operator workstation.

5.10.3.7.1.4. The system shall allow CE technicians to connect to all controllers with all available software in all modes available…