Attachment 12 - Spec 01 31 00.01 Project Management and Coordination.pdf

PDF 18 KB Posted

Attached to
Z1DA--590-802 | Construct SCI Reno/Addition | Hampton, VA | Federal contract opportunity
Solicitation number
36C77625B0046
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a Project Management and Coordination specification section (Section 01 31 00.01) detailing requirements for digital project management procedures. The specification mandates the use of a web-based project management software package with comprehensive features, including project data compilation, access control, document workflow planning, communication tracking, and mobile device compatibility. Approved software platforms include Procore, Oracle Primavera Submittal Exchange, or equivalent web-based project management software.

Key requirements include providing user licenses for the Owner, Architect, and consultants, delivering eight hours of software training, and creating a digital archive at project completion in a format readable by common desktop applications. The software must support functions such as RFI tracking, submittal management, change order processing, meeting minute distribution, document revision control, and construction progress photograph management. The specification emphasizes real-time communication tracking, secure document markup, and comprehensive project documentation throughout the construction process.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--590-802 | Construct SCI Reno/Addition | Hampton, VA |, newest first.
File Type Posted
Technical Questions Answered.docx DOCX document
VAAR 852.219-75.docx DOCX document
VHA ICRA-1.2 Oct 1 2024.pdf PDF
Amendment 0002.pdf PDF
Site Visit Sign-in Sheet.pdf PDF
Specs - Volume I 8-27-25.pdf PDF
Amendment 0001.pdf PDF
Attachment 09 - Drawings Part V.pdf PDF
Attachment 08 - Drawings Part IV.pdf PDF
Attachment 11 - Wage determination.pdf PDF
Attachment 10 - VA Notice of Limitations on Subcontracting.docx DOCX document
Attachment 06 - Drawings Part II.pdf PDF
Attachment 05 - Drawings Part I.pdf PDF
Attachment 03 - Specs Volume II.pdf PDF
Attachment 07 - Drawings Part III.pdf PDF
Attachment 02 - Specs Volume I.pdf PDF
Attachment 04 - Specs Volume III.pdf PDF
Attachment 01 - Statement of Work.pdf PDF
36C77625B0046.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number

Project Name Project Location

PROJECT MANAGEMENT AND COORDINATION

05-01-24

01 31 00.01 - 1

SECTION 01 31 00.01

PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative provision for coordinating construction operations on Project, including, but not limited to, the following:

1. Web-based Project management software package.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

1.3 DEFINITIONS

A. BIM: Building Information Modeling.

B. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.4 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Web-Based Project Management Software Package: Provide, administer, and use web-based

Project management software package for purposes of hosting and managing Project communication and documentation until Final Completion.

1. Basis of Specification: Procore, Oracle Primavera Submittal Exchange or other equivalent web-based project management software.

2. Web-based Project management software includes, at a minimum, the following features:

a. Compilation of Project data, including Contractor, subcontractors, Architect, Architect's consultants, Owner, and other entities involved in Project. Include names of individuals and contact information.

b. Access control for each entity for each workflow process, to determine entity's digital rights to create, modify, view, and print documents.

c. Document workflow planning, allowing customization of workflow between project entities.

d. Creation, logging, tracking, and notification for Project communications required in other Specification Sections, including, but not limited to, RFIs, submittals, Minor

Changes in the Work, Construction Change Directives, and Change Orders.

e. Track status of each Project communication in real time, and log time and date when responses are provided.

Project Number

Project Name Project Location

PROJECT MANAGEMENT AND COORDINATION

05-01-24

01 31 00.01 - 2

f. Procedures for handling PDFs or similar file formats, allowing markups by each entity. Provide security features to lock markups against changes once submitted.

g. Processing and tracking of payment applications.

h. Processing and tracking of contract modifications.

i. Creating and distributing meeting minutes.

j. Document management for Drawings, Specifications, and coordination drawings, including revision control.

k. Management of construction progress photographs.

l. Mobile device compatibility, including smartphones and tablets.

3. Provide Project management software user licenses for use of Owner, Architect, and

Architect's consultants. Provide eight hours of software training for web-based Project software users.

4. At completion of Project, provide digital archive in format that is readable by common desktop software applications in format acceptable to Architect. Provide data in locked format to prevent further changes.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

- - - END - - -