Attachment 11 - Total Evaluation Price - TEP 16 March 2022.xlsx

XLSX spreadsheet 40 KB Posted

Attached to
Roofing Repair, Hill AFB, UT Federal contract opportunity
Solicitation number
FA8201-22-R-0010
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Total Evaluated Sumamry

Total Evaluated Price TEP Calculation for the Roofing Single Contract Award Indefinite Delivery Indefinite Quantity
Instructions:

1. The Offeror shall fill out both the Notional Amount Application Worksheet and the Seed Project Worksheet.

2. All prices shall be fully burdened and shall include direct, indirect costs, profit and construction labor.

3. The Offeror shall only complete fields highlited in yellow and not alter the spreadsheet in any way.

4. Offeror shall input all prices as whole dollars for all worksheets.

5. The Offeror shall complete all priced cell for the Notional Amount Worksheet (note: years 2 through 5 have a preset formula that may be adjusted or removed as desired).

6. The "Grand Total" for the Notional Amount Application" shall be a sum of the Totals and will auto populate into the "Total Evaluated Price Worksheet" Notional Amount Application Price Cell (C23).

7. Seed Project: The Offeror shall complete all priced cells highlighted in yellow (cells should have corrisponding amounts next to them).

8. The offeror shall input Bond information on the Seed Project Worksheet in the appropriate fields.

9. The "Grand Total" for the Seed Project shall be a sum of the Totals plus "BOND AMOUNT" and will auto populate into the "Total Evaluated Price Worksheet" Seed Project Price Cell (C24).

10. The Evaluated Price is the same as the Nontional Amount Application, the Total Combined Price is the combination of both but not considered for award.

11. If additional information is required the Offeror may be required to submit additional breakout of divisions.

Product or ServiceTotal Price Element
Notional Amount Application$ - 0
Seed Project$ - 0
Total Combined Price$ - 0
Evaluated Price$ - 0

&"Arial,Regular"FA8201-16-R-0006 Roofing IDIQ

Notional Amount Application Notional Amount Application Worksheet - 16 March 2022 All rates will auto-populate into this spreadsheet. All notional quantities will be determined by the Government prior to Offeror evaluation and will be applied to all Offerors equally. Notional quantities and totals will be populated by the Government and will not be disclosed to the Offerors.

Year 1Year 2Year 3Year 4Year 56 month option period will be based upon Year 5 pricing
LINE ITEMUNITNotional QuantitiesUnit PriceNotional TotalNotional QuantitiesUnit PriceNotional TotalNotional QuantitiesUnit PriceNotional TotalNotional QuantitiesUnit PriceNotional TotalNotional QuantitiesUnit PriceNotional Total
AREMOVE EXISTING 4-PLY BUILT-UP ROOFSF5,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.00
BREMOVE EXISTING SINGLE LAYER SHINGLED ROOFSF15,000$0.00$0.0015,000$0.00$0.0015,000$0.00$0.0015,000$0.00$0.0015,000$0.00$0.00
CREMOVE EXISTING INSULATIONSF5,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.00
DREMOVE AND INSTALL NEW ROOF DRAINSEA20$0.00$0.0020$0.00$0.0020$0.00$0.0020$0.00$0.0020$0.00$0.00
EREMOVE EXISTING GUTTERS AND DOWNSPOUTSLF2,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.00
FREMOVE NON-FRIABLE ASBESTOS BASE FLASHING, INCLUDES OFF-BASE DUMPING AND HAULING CHARGESSF2,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.00
GREMOVE EXISTING WATERPROOFING MEMBRANE (DIRT COVERED ROOF)SF1,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.00
HREMOVE EARTH BERM AND BACKFILLCY300$0.00$0.00300$0.00$0.00300$0.00$0.00300$0.00$0.00300$0.00$0.00
IREMOVE EXISTING AGGREGATE OVER BURSF5,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.00
JREMOVE AND INSTALL NEW ROOF HATCHEA6$0.00$0.006$0.00$0.006$0.00$0.006$0.00$0.006$0.00$0.00
KREMOVE / INSTALL LIGHTNING PROTECTION WITH RECERTIFICATIONLF500$0.00$0.00500$0.00$0.00500$0.00$0.00500$0.00$0.00500$0.00$0.00
LLIFT AND RESET LIGHTNING PROTECTION, NO RECERTIFICATION NEEDEDLF500$0.00$0.00500$0.00$0.00500$0.00$0.00500$0.00$0.00500$0.00$0.00
MSET-UP ( EAVE HEIGHT 15' - 30' )LS1$0.00$0.001$0.00$0.001$0.00$0.001$0.00$0.001$0.00$0.00
NSET- UP ( EAVE HEIGHT 30' AND ABOVE )LS1$0.00$0.001$0.00$0.001$0.00$0.001$0.00$0.001$0.00$0.00
OINSTALL A 2-PLY, 30 YEAR SBS MODIFIED BITUMEN ROOF SYSTEM WITH GRANULATED SBS CAP SHEETSF5,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.00
PINSTALL ASPHALT SHINGLES WITH #30 FELTSF15,000$0.00$0.0015,000$0.00$0.0015,000$0.00$0.0015,000$0.00$0.0015,000$0.00$0.00
QINSTALL GALV. METAL FLASHING/COUNTER FLASHING ON EQUIPMENT AND CURBSLF2,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.00
RINSTALL METAL GRAVEL STOP/DRIP EDGE WITH 6" FACELF4,000$0.00$0.004,000$0.00$0.004,000$0.00$0.004,000$0.00$0.004,000$0.00$0.00
SINSTALL EXPANSION JOINTLF400$0.00$0.00400$0.00$0.00400$0.00$0.00400$0.00$0.00400$0.00$0.00
TINSTALL 5" METAL GUTTERS AND DOWNSPOUTSLF2,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.00
UINSTALL 3" RIGID INSULATION BOARDSF5,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.00
VINSTALL FIBERGLASS BATT INSULATIONSF1,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.00
WINSTALL METAL PARAPET CAP/COPINGLF1,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.00
XINSTALL 3' WALKWAYLF400$0.00$0.00400$0.00$0.00400$0.00$0.00400$0.00$0.00400$0.00$0.00
YINSTALL HEAT TRACE SYSTEMLF500$0.00$0.00500$0.00$0.00500$0.00$0.00500$0.00$0.00500$0.00$0.00
ZINSTALL 3/4" SHEATHINGSF400$0.00$0.00400$0.00$0.00400$0.00$0.00400$0.00$0.00400$0.00$0.00
AAINSTALL SCUPPEREA10$0.00$0.0010$0.00$0.0010$0.00$0.0010$0.00$0.0010$0.00$0.00
BBINSTALL PITCH POCKETSEA20$0.00$0.0020$0.00$0.0020$0.00$0.0020$0.00$0.0020$0.00$0.00
CCINSTALL WOOD CURBSBF200$0.00$0.00200$0.00$0.00200$0.00$0.00200$0.00$0.00200$0.00$0.00
DDINSTALL WATERPROOFING SYSTEM WITH DRAINAGE AND PROTECTION BOARD (DIRT COVERED ROOFS)SF1,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.00
EEINSTALL VEGETATION, GRASS (DIRT COVERED ROOFS)SF1,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.00
FFINSTALL GRAVEL COATSF2,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.00
GGINSTALL CONCRETE SPLASH BLOCKEA20$0.00$0.0020$0.00$0.0020$0.00$0.0020$0.00$0.0020$0.00$0.00
HHINSTALL SNOW BARS/STOPSLF1,500$0.00$0.001,500$0.00$0.001,500$0.00$0.001,500$0.00$0.001,500$0.00$0.00
IIINSTALL STRUCTURAL METAL STANDING SEAM ROOF SYSTEM OVER STRUCTURE, FASTNERS AND CLIPS (HYDROSTATIC)SF5,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.00
JJINSTALL EPDM ROOF SYSTEMSF2,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.002,000$0.00$0.00
KKAPPLY CAULK / SEALANT AS NEEDEDLF500$0.00$0.00500$0.00$0.00500$0.00$0.00500$0.00$0.00500$0.00$0.00
LLCLEAN OUT GUTTERS, DOWNSPOUTS, AND DRAINSLF200$0.00$0.00200$0.00$0.00200$0.00$0.00200$0.00$0.00200$0.00$0.00
MMINFRARED SURVEYSF1,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.001,000$0.00$0.00
NNEPDM/TPO/PVC ROOF REPAIRS/PATCHESSF100$0.00$0.00100$0.00$0.00100$0.00$0.00100$0.00$0.00100$0.00$0.00
OOREMOVE EXISTING METAL ROOFINGSF5,000$0.00$0.000$0.00$0.000$0.00$0.000$0.00$0.000$0.00$0.00
PPINSTALL 1/2' COVER BOARDSF5,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.00
QQINSTALL PVC ROOF SYSTEM (80mil minimum)SF5,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.005,000$0.00$0.00
TOTAL$0.00$0.00$0.00$0.00$0.00
GRAND TOTAL$0.00

Roofing IDIQ

Seed Project

See Total Evaluated Price Worksheet for Instructions how to fill out.
LINE ITEMUNITESTIMATED QUANTITYUNIT COSTTOTAL
AREMOVE EXISTING 4-PLY BUILT-UP ROOFSF950$0.00
BREMOVE EXISTING SINGLE LAYER SHINGLED ROOFSF$0.00
CREMOVE EXISTING INSULATIONSF950$0.00
DREMOVE AND INSTALL NEW ROOF DRAINSEA$0.00
EREMOVE EXISTING GUTTERS AND DOWNSPOUTSLF80$0.00
FREMOVE NON-FRIABLE ASBESTOS BASE FLASHING, INCLUDES OFF-BASE DUMPING AND HAULING CHARGESSF$0.00
GREMOVE EXISTING WATERPROOFING MEMBRANE (DIRT COVERED ROOF)SF$0.00
HREMOVE EARTH BERM AND BACKFILLCY$0.00
IREMOVE EXISTING AGGREGATE OVER BURSF950$0.00
JREMOVE AND INSTALL NEW ROOF HATCHEA$0.00
KREMOVE / INSTALL LIGHTNING PROTECTION WITH RECERTIFICATIONLF$0.00
LLIFT AND RESET LIGHTNING PROTECTION, NO RECERTIFICATION NEEDEDLF$0.00
MSET-UP ( EAVE HEIGHT 15' - 30' )LS2$0.00
NSET- UP ( EAVE HEIGHT 30' AND ABOVE )LS$0.00
OINSTALL A 2-PLY, 30 YEAR SBS MODIFIED BITUMEN ROOF SYSTEM WITH GRANULATED SBS CAP SHEETSF950$0.00
PINSTALL ASPHALT SHINGLES WITH #30 FELTSF$0.00
QINSTALL GALV. METAL FLASHING/COUNTER FLASHING ON EQUIPMENT AND CURBSLF220$0.00
RINSTALL METAL GRAVEL STOP/DRIP EDGE WITH 6" FACELF200$0.00
SINSTALL EXPANSION JOINTLF18$0.00
TINSTALL 5" ALUMINUM GUTTERS AND DOWNSPOUTSLF80$0.00
UINSTALL 3" RIGID INSULATION BOARDSF2,450$0.00
VINSTALL FIBERGLASS BATT INSULATIONSF$0.00
WINSTALL METAL PARAPET CAP/COPINGLF$0.00
XINSTALL 3' WALKWAYLF$0.00
YINSTALL HEAT TRACE SYSTEMLF$0.00
ZINSTALL 3/4" SHEATHINGSF$0.00
AAINSTALL SCUPPEREA$0.00
BBINSTALL PITCH POCKETSEA$0.00
CCINSTALL WOOD CURBSBF$0.00
DDINSTALL WATERPROOFING SYSTEM WITH DRAINAGE AND PROTECTION BOARD (DIRT COVERED ROOFS)SF$0.00
EEINSTALL VEGETATION, GRASS (DIRT COVERED ROOFS)SF$0.00
FFINSTALL GRAVEL COATSF$0.00
GGINSTALL CONCRETE SPLASH BLOCKEA$0.00
HHINSTALL SNOW BARS/STOPSLF100$0.00
IIINSTALL STRUCTURAL METAL STANDING SEAM ROOF SYSTEM OVER STRUCTURE, FASTNERS AND CLIPS (HYDROSTATIC)SF550$0.00
JJINSTALL EPDM ROOF SYSTEMSF$0.00
KKAPPLY CAULK / SEALANT AS NEEDEDLF300$0.00
LLCLEAN OUT GUTTERS, DOWNSPOUTS, AND DRAINSLF$0.00
MMINFRARED SURVEYSF$0.00
NNEPDM/TPO/PVC ROOF REPAIRS/PATCHESSF$0.00
OOREMOVE EXISTING METAL ROOFINGSF550$0.00
PPINSTALL 1/2" COVER BOARDSF1,500$0.00
QQINSTALL PVC ROOF SYSTEM (80mil minimum)SF$0.00
Sub Total$0.00
Bid Bond PercentageBid Bond Percentage
Bid Bond AmontBid Bond Amount$0.00
GRAND TOTAL$0.00