This technical specification (Section 01 7419) details Construction Waste Management and Disposal requirements for a federal contract at the Mike Monroney Aeronautical Center (MMAC). The document establishes comprehensive guidelines for managing construction and demolition waste, with a mandatory requirement for contractors to divert at least 55 percent of non-hazardous solid waste from landfills and incinerators through salvaging, recycling, and reuse strategies.
Key requirements include developing a detailed waste management plan, submitting monthly waste reduction progress reports, and implementing specific procedures for handling various waste types including demolition waste (concrete, brick, metal, equipment) and construction waste (metal scraps, packaging materials). The specification covers waste identification, separation, transportation, and disposal processes, with an emphasis on environmental responsibility. Contractors must train workers on waste management procedures, designate specific areas for waste sorting, and provide documentation on waste diversion efforts, including records of donations, sales, recycling, and disposal.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specification
01 7419 - 1 CONST. WASTE MGMT. & DISP.
11/13/2024
SECTION 01 7419
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
PART 1 - GENERAL
1.01 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Salvaging nonhazardous demolition and construction waste.
2. Recycling nonhazardous demolition and construction waste.
3. Recycling demolition and construction universal waste.
4. Disposing of nonhazardous demolition and construction waste.
B. Related Sections:
1. Section 01 5000 Temporary Construction Facilities and Controls
2. Section 015723 Stormwater Pollution Prevention
3. Section 02 4100 Demolition.
4. Section 04 2000 Unit Masonry.
5. Section 31 2000 Earth Moving
C. Related Documents: Refer to the FAA Construction Waste Management Requirements for
Contracts (AMS Clause 3.6.3-22 Dated October 2024)
1.02 DEFINITIONS
A. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
B. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.
C. Universal Waste: As regulated in Title 40 of the Code of Federal Regulations (CFR) in Part 273, includes batteries, pesticides, mercury-containing equipment, lamps, and aerosol cans.
D. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
E. Mike Monroney Aeronautical Center (MMAC) – FAA Facility
F. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
G. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
H. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work.
1.03 PERFORMANCE REQUIREMENTS
A. In performance of this contract, the Contractor must establish a program to minimize waste generation, as well as recycle, reuse, and salvage construction and demolition (C&D) debris generated to the maximum extent possible. The Contractor must divert at least 55 percent weight of the total non-hazardous solid waste generated by the work from landfills and incinerators.
01 7419 - 2 CONST. WASTE MGMT. & DISP.
B. Practice efficient waste management in the use of materials in the course of the Work. Use all reasonable means to divert construction and demolition waste from landfills and incinerators. Facilitate recycling and salvage of materials, including the following:
1. Demolition Waste:
• Concrete
• Brick
• Carpet
• Ceiling Tiles
• Metal structural elements
• Asphalt
• Soil
• Equipment
• Metal Ductwork
• Metal Piping
• Electrical conduit
• Copper wiring
• Switchgear and panelboards
• Transformers
• Universal Waste
• Wood / Pallets
2. Construction Waste:
• Metal scraps
• Packaging: Regardless of salvage/recycle goal indicated in “General” Paragraph above, salvage or recycle 100 percent of the following uncontaminated packaging materials:
• Paper
• Cardboard
• Boxes
• Plastic sheet and film
• Polystyrene packaging
• Wood crates / Pallets
• Plastic pails
1.04 ACTION SUBMITTALS
A. Waste Management Plan: Submit plan within 15 days after contract award / Notice to
Proceed (NTP) prior to the start of construction activities. The plan must be found acceptable by the Contracting Officer's Representative (COR) or the COR's designated representative prior to the Contractor starting work.
B. Surplus Soil Analysis: Submit surplus soil analysis within 10 days of receiving results. The analysis must meet EPA requirements for the disposal specified. If results are not approved for the disposal specified, a modification to the contract will be required.
1.05 INFORMATIONAL SUBMITTALS
A. Waste Reduction Progress Reports: Submit report by the 15th day of each month.
Include the following monthly information for all construction and demolition (C&D) waste:
1. FAA facility name and address, report date and reporting period, contract number and project name.
2. Date waste is removed from the facility.
3. Material Category
4. Generation-point of waste
01 7419 - 3 CONST. WASTE MGMT. & DISP.
5. Total quantity of waste in tons (including disposed, salvaged, recycled & reused)
6. The quantity of waste disposed in tons, method of waste material disposal, and reason why waste was not diverted.
7. Quantity of waste salvaged, both estimated and actual in tons
8. Quantity of waste recycled, both estimated and actual in tons
9. Quantity of waste reused, both estimated and actual in tons
10. Total quantity of waste recovered (salvaged plus recycled) in tons.
11. Total quantity of waste recovered (salvaged plus recycled) as a percentage of total waste.
B. Waste Reduction Calculations: Before request for Substantial Completion, submit calculated end-of-Project rates for salvage, recycling, and disposal as a percentage of total waste generated by the Work.
C. Records of Donations: Indicate receipt and acceptance of salvageable waste donated to individuals and organizations. Indicate whether organization is tax exempt.
D. Records of Sales: Indicate receipt and acceptance of salvageable waste sold to individuals and organizations. Indicate whether organization is tax exempt.
E. Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
F. Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
G. Qualification Data: For waste management coordinator.
1.06 QUALITY ASSURANCE
A. Project Pre-Construction Meeting: Coordinate Waste Management Plan submittal and monthly reporting requirements.
1.07 WASTE MANAGEMENT PLAN
A. General: Develop a waste management plan. Provide an overall strategy for managing C&D debris associated with the project. Plan shall consist of waste identification, waste reduction work plan, handling and transportation procedures and cost/revenue analysis.
B. Waste Identification: Indicate anticipated types and quantities of demolition, site clearing, and construction waste generated by the Work. Include estimated quantities by weight and assumptions for estimates.
C. Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, reused or disposed of in landfill or incinerator. Include points of waste generation, estimated total weight of each type of waste, final disposition for each waste type, and handling and transportation procedures.
1. Salvaged Materials for Reuse: For materials that will be salvaged and reused in this Project (including relocating soil elsewhere on FAA property), describe methods for preparing salvaged materials before incorporation into the Work.
2. Salvaged Materials for Sale: For materials that will be sold to individuals and organizations, include list of their names, addresses, and telephone numbers.
3. Salvaged Materials for Donation: For materials that will be donated to individuals
01 7419 - 4 CONST. WASTE MGMT. & DISP.
and organizations, include list of their names, addresses, and telephone numbers.
4. Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers.
5. Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.
6. Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location where materials separation will be performed.
PART 2 – PRODUCTS – Not Used
PART 3 – EXECUTION
3.01 PLAN IMPLEMENTATION
A. General: Implement approved waste management plan. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.
B. Waste Management Coordinator: Engage a waste management coordinator to be responsible for implementing, monitoring, and reporting status of waste management work plan.
C. Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work occurring at Project site.
1. Distribute waste management plan to everyone concerned within three days of submittal return.
2. Distribute waste management plan to entities when they first begin work on-site.
Review plan procedures and locations established for salvage, recycling, and disposal.
D. Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Designate and label specific areas on Project site necessary for separating materials that are to be salvaged, recycled, reused, donated, and sold.
2. Comply with Section 015000 "Temporary Facilities and Controls" for controlling dust and dirt, environmental protection, and noise control.
3. Comply with Section 015723 “Stormwater Pollution Prevention” for controlling stormwater run-off.
3.02 SALVAGING DEMOLITION WASTE
A. Salvaged Items for Reuse in the Work:
1. Clean salvaged items.
2. Pack or crate items after cleaning. Identify contents of containers.
3. Store items in a secure area until installation.
4. Protect items from damage during transport and storage.
5. Install salvaged items to comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make items functional for use indicated.
01 7419 - 5 CONST. WASTE MGMT. & DISP.
B. Salvaged Items for Owner's Use:
1. Clean salvaged items.
2. Pack or crate items after cleaning. Identify contents of containers.
3. Store items in a secure area until delivery to Owner.
4. Transport items to Owner's storage area designated by Owner.
5. Protect items from damage during transport and storage.
3.03 RECYCLING DEMOLITION AND CONSTRUCTION WASTE, GENERAL
A. General: Recycle paper and beverage containers used by on-site workers.
B. Recycling Incentives: Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to Owner.
C. Procedures: Separate recyclable waste from other waste materials, trash, and debris.
Separate recyclable waste by type at Project site to the maximum extent practical according to approved construction waste management plan.
1. Provide appropriately marked containers or bins for controlling recyclable waste until they are removed from Project site. Include list of acceptable and unacceptable materials at each container and bin.
a. Inspect containers and bins for contamination and remove contaminated materials if found.
2. Stockpile processed materials on-site without intermixing with other materials.
Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
3. Stockpile materials away from construction area. Do not store within drip line of remaining trees or structures.
4. Store components off the ground and protect from the weather.
5. Remove recyclable waste from Owner's property and transport to recycling receiver or processor.
3.04 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
1. Except as otherwise specified, do not allow waste materials that are to be disposed of to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
C. Disposal: Remove waste materials from Owner's property and legally dispose of them.
3.05 SURPLUS SOIL:
A. Soil Sampling and Testing: All soil must be sampled and tested prior to disposal or relocation on the MMAC. If designated elsewhere in the contract documents, the contractor will be responsible for sampling and testing the soil. Refer to Specification Section 312000 Earth Moving for additional information.
01 7419 - 6 CONST. WASTE MGMT. & DISP.
1. If contract documents indicate that soil will be tested by the contractor:
a. The contractor shall collect one (1) composite sample (composed of five (5) to seven (7) discrete subsamples) per 500 cubic yards of soil that will be removed from the construction site. Based on this, the contractor shall determine the number and frequency of samples that need to be collected from the soil excavations and generated stockpiles. The soil samples will be analyzed by USEPA SW-846 methods for TPH, VOCs, SVOCs, RCRA metals, PCBs, and Pesticides. In the unlikely event during excavation that a waste release is encountered, such as odor, etc., then VOC samples shall be collected as discrete, not composite, samples for analysis. Contractor shall assume up to ten (10) additional discrete VOC samples may be required.
b. Soil analysis must be submitted to and approved by the FAA prior to moving soil from the site.
B. Soil Reuse, Relocation or Disposal: The contract documents will specify what will be done with the surplus soil, based on our current understanding of the soil’s properties. If the soil analysis is not acceptable for the specified action a contract modification will be required. Refer to Specification Section 312000 Earth Moving for additional information.
1. Surplus Soil Removed for Sale or Reuse Off Owner’s Property: If designated elsewhere in the contract documents, the contractor will remove and transport the surplus soil from the MMAC and legally dispose of it. Removed soil will be sold or reused to meet waste diversion requirements.
2. Surplus Soil Relocated on the MMAC: If designated elsewhere in the contract documents, the contractor will transport the surplus soil to a designated area on the Owner’s property. The area will be designated prior to the start of construction.
a. The Contractor’s Oklahoma City Land Disturbance Permit, the Oklahoma
Department of Environmental Quality (ODEQ) General Permit (OKR-10), and the Storm Water Pollution Prevention Plan (SWPPP) must include the designated soil relocation area. Refer to Section 015723.
b. The Contractor is responsible for the installation and maintenance of erosion control devices at the designated soil relocation area. The Contractor is responsible for the repair and replacement of damaged erosion control devices at the designated soil disposal area.
c. No foreign / inorganic materials or rocks larger than 2 inches shall be mixed in with the relocated soil.
d. Spread soil 3” thick while maintaining the existing contours of the land. No soil will be relocated into wetland areas or stormwater run-off features.
3. Soil Disposal as Special Waste: If designated elsewhere in the contract documents, soil determined to be unsuitable for use as backfill shall be considered special waste.
The contractor will transport and legally dispose the unsuitable soil to a Non- Hazardous Industrial Waste (NHIW) Landfill located in Oklahoma County and certified by Oklahoma Department of Environmental Quality (ODEQ). The contractor will coordinate with the FAA to profile and manifest the waste for transport to the landfill. Contractor shall transport unsuitable soil in a lined container.
C. Remove waste materials, including trash and debris, from surplus soil to the extent practicable prior to removing surplus soil from the construction site. Recycle waste materials if possible. Otherwise, remove waste materials and legally dispose at a construction debris landfill.
01 7419 - 7 CONST. WASTE MGMT. & DISP.
END OF SECTION