This is a Statement of Objectives (SOO) for the modernization and installation of audio-visual capabilities in the 2nd Space Launch Squadron (2 SLS) conference room at Building 765, Vandenberg Space Force Base, California. The contractor shall provide all supplies, transportation, equipment, tools, materials, labor, supervision, and management to design, procure, deliver, and install a fully integrated audio-visual system. All devices connecting directly to AFNET via wired or wireless means must be DoD APLITS approved and compliant with the current National Defense Authorization Act (NDAA).
The system must include a primary large-format video wall approximately 16 feet wide by 72 inches high at a 16:9 ratio capable of displaying multi-source video feeds including launch pad feeds; two 85-inch 4K secondary displays flanking the primary wall; ceiling-mounted speakers with full room coverage, integrated microphones, and conference table phone integration; two wireless handheld microphone kits; an integrated video conferencing camera system configured for Microsoft Teams compatibility; intuitive A/V control systems featuring touchscreen interfaces at the main conference table and back-of-room primary control station; and a multi-source video router supporting launch pad video feeds from multiple pads with USB-C compatible user-facing ports and connections. All cabling must be routed discreetly through walls, floors, or furniture to ensure zero trip hazards. The contractor shall de-install legacy equipment, provide daily work area cleanup with onsite disposal, and return government-furnished areas to original condition. Installation schedule with identified long-lead items shall be provided with the proposal, with final schedule due within 14 calendar days of contract award. The contractor must conduct 100% system testing and validation with Microsoft Teams capability prior to government acceptance on AFTO Form 747, schedule a final walk-through five calendar days prior to acceptance, and provide system test results and as-built documentation in digital format. Critical spares must be recommended and provided by agreement. In-person comprehensive end-user training shall be delivered upon system turnover, including live demonstrations and operational documentation. The contractor shall provide a minimum one-year system warranty or the OEM standard warranty, whichever is longer, covering all hardware and installation workmanship. All contractor personnel must comply with VSFB security procedures, obtain necessary badges for controlled areas, adhere to OSHA safety regulations, and the contractor shall designate a site Provisioning Project Owner (PPO) as the primary point of contact from award to site acceptance.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives (SOO) 2 SLS, Bldg. 765 Conference Room Audio Visual Modernization
1. Objective: To modernize and install audio-visual (A/V) capabilities in the 2nd Space Launch Squadron (2 SLS) conference room located at Building 765, Vandenberg Space Force Base (VSFB), California. The upgraded system must enable hybrid communications, Microsoft Teams compatibility, and high-quality presentation capabilities consistent with mission launch team operational demands.
2. Requirement: The Contractor shall provide all supplies, transportation, equipment, tools, materials, labor, supervision, and management to design, procure, deliver, and install a fully integrated audio-visual system.
Any device that connects directly to the AFNET via wired or wireless means must be DoD APLITS approved. The approved list can be found at https://aplits.disa.mil/processAPList.action
All devices must be in compliance with the current National Defense Authorization Act
(NDAA).
2.1. System Capabilities and Objectives:
The contractor shall design and implement an A/V solution that achieves the following performance objectives:
• Primary Display: A centrally located, securely mounted large-format video wall (approximately 16’ W x 72” H at a 16:9 ratio) capable of displaying multi-source video feeds, including launch pad feeds.
• Secondary Displays: Quantity (2) 85" 4K displays flanking the primary video wall to expand visibility for the room.
• Audio Clarity: Exceptional audio transmission and reception suitable for a large room footprint (approx. 34’ L x 21’ 6” W x 8’ 9” H). The audio system shall include ceiling-mounted speakers ensuring full room coverage, integrated microphones, and integration with a conference table phone.
• Wireless Audio: Quantity (2) wireless handheld microphone kits fully integrated into the room's audio system.
• Camera System: An integrated video conferencing camera system configured for comprehensive room coverage and Microsoft Teams compatibility.
• Control Systems: Intuitive A/V control system featuring touchscreen interfaces. This includes one remote touchscreen interface for the main conference table and a secondary primary control station located at the back of the room on a contractor-provided table.
https://aplits.disa.mil/processAPList.action
• Routing and Connectivity: Provide and install multi-source video router to support launch pad video feeds from multiple launch pads, to be displayed on video wall and/or flanking screens. Additionally, provide multi-source video routing capabilities allowing users at the conference table to seamlessly broadcast to the video wall and flanking monitors via HDMI. All user-facing ports and connections must support USB-C compatibility (direct or via approved adapters).
• Cable Management: All cabling must be routed discreetly through walls, floors, or furniture to ensure a clean, professional finish with zero trip hazards.
2.2. De-installation and Site Restoration:
• The Contractor shall safely de-install and remove all legacy A/V equipment, including the existing temporary projector, projector screen, televisions, and any associated non-functional hardware.
• Clean-up of work area shall be performed daily. Contractors are responsible for disposal of refuse generated in the performance of their duties. Disposal is available onsite.
• The Contractor shall return all government-furnished laydown areas to their original condition upon completion.
2.3. Project Execution, Testing, and Spares:
• The contractor shall develop an installation schedule for all A/V tasks, which at a minimum identify material procurement and receipt (clearly identify long lead material items), installation of A/V systems and infrastructure, functional testing, and final acceptance testing. A preliminary schedule shall be provided with the contractor’s proposal. The final schedule shall be provided no later than 14 calendar days after the contract award.
• The Contractor shall conduct 100% system testing and validation, demonstrating full functionality and Microsoft Teams capability, prior to government acceptance (AFTO Form 747). The Contractor shall schedule a final project walk-through 5 calendar days prior to acceptance. The contractor shall sign the AFTO 747 after the base has signed the test report and the walk-through and any punch list items have been completed.
• The Contractor shall provide system test results and as-built documentation (including installation redlines) in a digital format.
• The Contractor shall recommend and provide an agreed-upon package of critical spares to ensure continuous operational readiness.
2.4. Training:
• The Contractor shall provide in-person, comprehensive end-user training for government personnel upon system turnover, including live demonstrations and operational documentation.
2.5. Warranty:
• The Contractor shall provide a minimum of one (1)-year system warranty, or the standard warranty provided by the Original Equipment Manufacturer (OEM), whichever is longer, covering all hardware and installation workmanship.
2.6. Security and Base Access:
• All contractor personnel must comply with VSFB security procedures, obtain necessary badges for controlled areas, and adhere strictly to OSHA safety regulations during installation. The contractor shall designate a site Provisioning Project Owner (PPO) to serve as the primary point of contact from award to site acceptance.