This is a Statement of Objectives for a design-build project to upgrade yard piping and flow measurement infrastructure at the Brackish Groundwater National Desalination Research Facility in Alamogordo, New Mexico. The project involves comprehensive upgrades to source water (SW), potable water (PW), and concentrate water (CW) piping systems, along with associated flow measurement and control infrastructure.

Key work includes: installation of a TP10 Flow Measurement Vault with three magnetic flow meters for monitoring SW from three storage tanks; replacement of a damaged 4" TP10 return line; removal and rerouting of buried piping to new above-grade manifolds; installation of three TP10 Piping Manifolds with connections to SW, PW, and CW sources; pressure CW drain piping from manifolds to a CW Vault with valving distribution capability to three evaporation ponds; installation of additional magnetic flow meters at TP7, Well 2/4 bypass line, and within the CW Vault; modification of SW piping from the acid room valve manifold to test pads TP7, TP8, and TP9; installation of four concrete vaults at existing valve locations; full SCADA integration with controls cabling, conduit installation, surge suppression, and signal programming; temperature-controlled heat trace and insulation for all pressure piping; and facility commissioning, testing, and training. An optional line item includes locating and replacing 50-500 feet of damaged SWST2 pipeline in 50-foot sections. The contractor must comply with Reclamation Safety and Health Standards, manage multiple concurrent contracts in the vicinity, and follow detailed submittal requirements including design packages at 30-, 60-, 90-, and 100-percent completion levels, with Government review and approval required before construction of each phase. Work hours are restricted to 7:30 a.m. to 4:30 p.m., Monday through Friday, unless approved by the Contracting Officer's Representative.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior February 2026

Brackish Groundwater National

Desalination Research Facility

Yard Piping and Flow

Measurement Design-Build

Statement of Objectives

Alamogordo, New Mexico

Upper Colorado Basin Region

This page intentionally left blank.

Foreword

00 00 30 - 1

Brackish Groundwater National Desalination Research Facility

Yard Piping and Flow Measurement Design-Build

Alamogordo, New Mexico

FOREWORD

Work is located on the Brackish Groundwater National Desalination Research Facility

(BGNDRF) site at 500 Lavelle Road in Alamogordo, New Mexico in Otero County.

The Project shall provide upgrades to site source water (SW), potable water (PW) and concentrate water (CW) piping and flow measurement infrastructure. Drawings and conceptual layout figures to be provided in Phase 2 and are cited as follows; Figure C6-2026, Figure C8-

2026, Figure C9-2026, Figure C10-2026, Figure M6-2026, and Figure M4-2026 which are provided in Section 52 00 00.

Design and Construct:

1. Yard piping and flow measurement upgrades:

a. The following descriptions reference points A through Q, which are shown on

Figure C6-2026, Figure C9-2026, Figure C10-2026, Figure M6-2026, and Figure

M4-2026, provided in Section 52 00 00.

b. OPTIONAL CLIN: Locate leak and replace 50-500 ft (50-ft sections priced in Price

Schedule C) of damaged Source Water Storage Tank 2 (SWST2) pipeline shown on

Figure C9-2026.

c. TP10 Flow Measurement Vault (Point C) including below grade vault, access hatch(es), power and controls, valves, piping, accessories, and three magnetic flow meters:

1) Three (3) for the existing SW piping from SWST1, SWST2, and SWST3 to the

TP10 Manifolds (Point E).

2) Provide, controls, and integration with SCADA, electrical power to flow meters and heat trace, including duct bank and conduit. The flow meters shall provide local readout and remote readout to the existing plant SCADA system.

d. Replace existing 4” TP10 return line to SWST2 (Point B) using similar route as existing temporary (shallow) line. This requires replacement of sun-damaged piping and valves at the test pad (see Photos 51-52 in 51 00 90). The approximate location of the existing piping is shown on Figure C9-2026.

e. Removal of the existing partially buried TP10 manifold, which contains existing piping from SWST1 (SW 1), SWST2 (SW 2), SWST3 (SW 3), and PW source, and rerouting buried piping to the TP10 Flow Measurement Vault (Points C, D).

f. Buried piping for SW 1, SW 2, SW 3, and PW from TP10 Flow Measurement Vault

(Point C, D) to three above grade piping manifolds at TP10 (Point E).

00 00 30 - 2

g. Three TP10 Piping Manifolds (Point E) that each provide above grade connection to

SW 1, SW 2, SW 3, and PW sources and a connection to CW pressure drain piping.

h. Separate pressure CW drain piping (three pipelines) from each of the three TP10 manifolds (Point E) to the CW Vault (Point L). The pressure drain piping shall be buried between the TP10 manifolds and the CW Vault.

i. A valving manifold within the CW Vault (Point L) which allows any of the three

TP10 Piping Manifolds to deliver CW water to any of the three Evaporation Ponds

(Point M, Point N, or Point O).

j. Install a magnetic flow meter on the 6” SW line at TP7 (Point I). See Figures C9-

2026 and M6-2026. Provide, controls, and integration with SCADA, electrical power to flow meters and heat trace, including duct bank and conduit. The flow meters shall provide local readout and remote readout to the existing plant SCADA system.

k. Install a magnetic flow meter on the 4” Well 2/4 bypass line west of Pond 1. Provide, controls, and integration with SCADA, electrical power to flow meters and heat trace, including duct bank and conduit. The flow meters shall provide local readout and remote readout to the existing plant SCADA system.

l. Modify SW piping from acid room (Point A) valve manifold to TP 7, 8, and 9 (Points

I, J, and K, respectively) as conveyed on Figures C9-2026, M4-2026, and M6-2026.

Cap and abandon in place unused portions of the three pipelines that connect the acid room valve manifold to the outdoor test pads and replace with a single line that connects to the associated line from the acid room. See Figures C9-2026, M4-2026, and M6-2026. Unused piping can be removed to facilitate new design.

m. Remove buried interconnections between TP 7, 8, and 9 piping and provide new isolation valves above grade on the vertical section of each test pad’s piping manifold. Cap and abandon in place or remove piping taken out of service as necessary to ensure each test pad is fed by a single pipeline that matches what is coming from the building. Provide, controls, and integration with SCADA, electrical power to flow meters, heat trace, and insulation, including duct bank and conduit as required.

n. Three (3) magnetic flow meters in the CW Vault which measure instantaneous and total CW flow to the three Evaporation Ponds (Point M, Point N, or Point O). One magnetic flow meter on the 4” Well 2/4 bypass line west of Pond 1 (Point Q). The flow meters shall provide local readout and remote readout to the existing plant

SCADA system. Provide, controls, and integration with SCADA, electrical power to flow meters and heat trace, including duct bank and conduit..

2. Installation of four concrete vaults at or near the four existing valve vaults (Pond 1, Pond

2, Pond 3, and Agriculture) to provide access to the existing flow meters which measure flow to Ponds 1-3 and Agriculture magnetic flow meters (Point P). This may include relocation of the flow meters and installing gravel at Pond 2 and the Agriculture supply vaults.

3. The contractor shall install new conduit from all new flow meter locations to the existing plant SCADA system. Controls cabling from flow meters to interface with existing

SCADA system. The Contractor shall be responsible for installing and terminating

00 00 30 - 3 controls cabling through new terminal blocks to the existing SCADA PLC within the existing Research Facility building. The contractor shall also be responsible for providing surge/transient suppression on these new cables. The Contractor shall be responsible for programming the new signals into the existing SCADA system.

4. Temperature controlled heat trace and insulation for all pressure piping above frostline and as required for below grade or vaulted infrastructure.

5. Utilities as needed and as described herein.

6. All other components required to provide a fully functional system that meets the intent of this solicitation.

7. Testing, training, and commissioning.

FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION

“RECLAMATION SAFETY AND HEALTH STANDARDS” WHICH IS APPLICABLE

TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT WBR 1452.223-81, SAFETY

AND HEALTH.

00 00 30 - 4

Yard Piping and Flow Measurement

Table of Contents 00 01 10 - 1

SECTION C - DESCRIPTION / SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 12 10 Other Contracts 01 12 16 Work Sequence 01 14 10 Use of Site 01 14 12 Work Restrictions and Limitations 01 31 19 Project Management and Coordination 01 32 20 Construction Program 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 57 15 Utility Line Investigations 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 90 Preservation of Historical and Archaeological Data 01 60 00 Product Requirements 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents 01 79 20 Training 01 81 05 General Performance Requirements 01 91 16 Facility Commissioning

DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS IN PHASE 2

51 00 00 Information Available to Offerors 51 00 30 Green Procurement Form 51 00 31 Property Lease Agreements 51 00 32 Environmental Assessment 51 00 33 Geotechnical Engineering Report 51 00 60 Electronic Media Release 51 00 90 Existing Conditions Photographs 51 46 00 Facility Discharge Permit 51 46 02 Raw Water Quality Data

Table of Contents 00 01 10 - 2

DIVISION 52 – DRAWINGS

52 00 00 Drawings and Conceptual Layout Figures

END OF CONTENTS

Summary of Work

01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located on the Brackish Groundwater National Desalination Research Facility

(BGNDRF) site at 500 Lavelle Road in Alamogordo, New Mexico in Otero County. Refer to Section 52 00 00 - Drawings for vicinity and location maps.

1.02 PRINCIPAL COMPONENTS OF WORK

A. The Project shall provide upgrades to site source water (SW), potable water (PW) and concentrate water (CW) piping and flow measurement infrastructure. Drawings and conceptual layout figures to be provided in Phase 2 and are cited as follows; Figure

C6-2026, Figure C8-2026, Figure C9-2026, Figure C10-2026, Figure M6-2026, and Figure

M4-2026 which are provided in Section 52 00 00.

B. Design and Construct:

1. Yard piping and flow measurement upgrades:

a. The following descriptions reference points A through Q, which are shown on Figure C6-2026, Figure C9-2026, Figure C10-2026, Figure M6-2026, and Figure M4-2026, provided in Section 52 00 00.

b. OPTIONAL CLIN: Locate leak and replace 50-500 ft (50-ft sections priced in Price Schedule C) of damaged Source Water Storage Tank 2 (SWST2) pipeline shown on Figure C9-2026.

c. TP10 Flow Measurement Vault (Point C) including below grade vault, access hatch(es), power and controls, valves, piping, accessories, and three magnetic flow meters:

2. Three (3) for the existing SW piping from SWST1, SWST2, and SWST3 to the TP10 Manifolds (Point E).

3. Provide, controls, and integration with SCADA, electrical power to flow meters and heat trace, including duct bank and conduit. The flow meters shall provide local readout and remote readout to the existing plant SCADA system.

d. Replace existing 4” TP10 return line to SWST2 (Point B) using similar route as existing temporary (shallow) line. This requires replacement of sun-damaged piping and valves at the test pad (see Photos 51-52 in 51 00 90). The approximate location of the existing piping is shown on Figure C9-2026.

e. Removal of the existing partially buried TP10 manifold, which contains existing piping from SWST1 (SW 1), SWST2 (SW 2), SWST3 (SW 3), and PW source, and rerouting buried piping to the TP10 Flow Measurement Vault (Points C, D).

Summary of Work

01 11 00 - 2

f. Buried piping for SW 1, SW 2, SW 3, and PW from TP10 Flow Measurement Vault

(Point C, D) to three above grade piping manifolds at TP10 (Point E).

g. Three TP10 Piping Manifolds (Point E) that each provide above grade connection to SW 1, SW 2, SW 3, and PW sources and a connection to CW pressure drain piping.

h. Separate pressure CW drain piping (three pipelines) from each of the three TP10 manifolds (Point E) to the CW Vault (Point L). The pressure drain piping shall be buried between the TP10 manifolds and the CW Vault.

i. A valving manifold within the CW Vault (Point L) which allows any of the three

TP10 Piping Manifolds to deliver CW water to any of the three Evaporation Ponds

(Point M, Point N, or Point O).

j. Install a magnetic flow meter on the 6” SW line at TP7 (Point I). See Figures C9-

2026 and M6-2026. Provide, controls, and integration with SCADA, electrical power to flow meters and heat trace, including duct bank and conduit. The flow meters shall provide local readout and remote readout to the existing plant SCADA system.

k. Install a magnetic flow meter on the 4” Well 2/4 bypass line west of Pond 1.

Provide, controls, and integration with SCADA, electrical power to flow meters and heat trace, including duct bank and conduit. The flow meters shall provide local readout and remote readout to the existing plant SCADA system.

l. Modify SW piping from acid room (Point A) valve manifold to TP 7, 8, and 9 (Points

I, J, and K, respectively) as conveyed on Figures C9-2026, M4-2026, and M6-2026.

Cap and abandon in place unused portions of the three pipelines that connect the acid room valve manifold to the outdoor test pads and replace with a single line that connects to the associated line from the acid room. See Figures C9-2026, M4-2026, and M6-2026. Unused piping can be removed to facilitate new design.

m. Remove buried interconnections between TP 7, 8, and 9 piping and provide new isolation valves above grade on the vertical section of each test pad’s piping manifold. Cap and abandon in place or remove piping taken out of service as necessary to ensure each test pad is fed by a single pipeline that matches what is coming from the building. Provide, controls, and integration with SCADA, electrical power to flow meters, heat trace, and insulation, including duct bank and conduit as required.

n. Three (3) magnetic flow meters in the CW Vault which measure instantaneous and total CW flow to the three Evaporation Ponds (Point M, Point N, or Point O). One magnetic flow meter on the 4” Well 2/4 bypass line west of Pond 1 (Point Q). The flow meters shall provide local readout and remote readout to the existing plant

SCADA system. Provide, controls, and integration with SCADA, electrical power to flow meters and heat trace, including duct bank and conduit.

2. Installation of four concrete vaults at or near the four existing valve vaults (Pond 1, Pond

2, Pond 3, and Agriculture) to provide access to the existing flow meters which measure flow to Ponds 1-3 and Agriculture magnetic flow meters (Point P). This may include relocation of the flow meters and installing gravel at Pond 2 and the Agriculture supply vaults.

Summary of Work

01 11 00 - 3

1.03

3. The contractor shall install new conduits from all new flow meter locations to the existing plant SCADA system. Controls cabling from flow meters to interface with existing SCADA system. The Contractor shall be responsible for installing and terminating controls cabling through new terminal blocks to the existing SCADA PLC within the existing Research Facility building. The contractor shall also be responsible for providing surge/transient suppression on these new cables. The Contract shall be responsible for programming the new signals into the existing SCADA system.

4. Temperature controlled heat trace and insulation for all pressure piping above frostline and as required for below grade or vaulted infrastructure.

5. Utilities as needed and as described herein.

6. All other components are required to provide a fully functional system that meets the intent of this solicitation.

7. Testing, training, and commissioning.

SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

1.04 DEFINITIONS

A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 53:

1. CO: Contracting Officer.

2. COR: Contracting Officer’s Representative.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Summary of Work

01 11 00 - 4

Other Contracts

01 12 10 - 1

SECTION 01 12 10

OTHER CONTRACTS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: Include in prices offered in the Price Schedule for other items of work.

1.02 OTHER CONTRACTS

A. During work under this contract, other work may be performed in the vicinity of the work by Government or other contractors, including the following:

1. PFAS Treatment Building and associated infrastructure construction

2. Evaporation pond liner replacement and modifications.

3. Stormwater improvements and pavement repairs and replacement

4. Evaporative Cooler replacement

B. Cooperate and coordinate with other contractors on access to and use of work areas and contractor use areas. Comply with FAR 52.236-8, Other Contracts. See diagram of approximate locations for other contracts on following page.

C. Do not interfere with work of other contractors or Government in vicinity of work.

D. Cooperate and coordinate with other contractors on use of temporary utilities.

E. Cooperate and coordinate with other contractors on maintaining dust-free operations.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Other Contracts

01 12 10 - 2

Work Sequence

01 12 16 - 1

SECTION 01 12 16

WORK SEQUENCE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: Include in prices offered in the Price Schedules for other items of work.

1.02 WORK SEQUENCE

A. Government is flexible to an alternate approach to packaging the design and construction submittals:

1. Contractors may propose an alternative approach including fast-tracking via early work packages for Government to review and approve during the initial design stages of the project.

2. In lieu of an approved alternate approach, Contractor to meet specified requirements.

B. Fast-tracking via early work packages:

1. After NTP, Contractor may begin construction on early work packages for which the

Government has reviewed and accepted for constructing the 30-, 60-, 90-, and 100-percent design submittal requirements covered in the early work package.

2. Government will not grant a time extension for a design re-submittal when, in the opinion of the CO, the initial submission failed to meet minimum quality requirements.

C. CO will notify Contractor when approved incremental designs are cleared for construction.

D. No payment will be made for design phase items or in-place construction until Government accepts the required submittals for the design phase or construction item.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Work Sequence

01 12 16 - 2

Use of Site

01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (Reclamation)

1. Cleaning Manual-2021 Inspection and Cleaning Manual for

Equipment and Vehicles to Prevent the

Spread of Invasive Species, September

2021, available at https://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. In accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site on Government land:

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Parking areas, and temporary roads.

2) Utilities including communications, power, and water lines.

3) First-aid facilities.

4) Areas for processing, storing, and disposing of waste materials from construction operations.

5) Temporary fences.

b. Describe methods to preserve, protect, and repair vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with work required under this contract.

1) Include methods to mark work area limits, protect disturbed areas, and prevent erosion.

c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.

d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.

2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.

https://www.usbr.gov/mussels/prevention

Use of Site

01 14 10 - 2

1.04 PROJECT CONDITIONS

A. Government land, as shown on drawings may be used for required construction facilities.

B. When private land is used for construction facilities or other construction purposes, make necessary arrangements associated with use of private land.

C. Location, construction, operation, maintenance, and removal of construction facilities on

Government land.

D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

E. Housing for construction personnel is not permitted on Government land.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 CLEANING

A. Construction Equipment:

1. Before bringing onsite, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds and invasive plant and animal species.

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.

3. Coordinate with COR to allow COR inspection of construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.

3.02 RESTORATION

A. Restore Contractor use areas to pre-construction condition.

B. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.

C. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition to facilitate revegetation, provide adequate drainage, and prevent erosion.

D. Seed disturbed areas of Government land used for construction purposes in accordance with approved seed mix provided in Section 01 81 05 – General Performance

Requirements.

END OF CONTENTS

Work Restrictions and Limitations

01 14 12 - 1

SECTION 01 14 12

WORK RESTRICTIONS AND LIMITATIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. City of Alamogordo (City)

1. Technical Standards-2022 Available at https://ci.alamogordo.nm.us/861/Engineering

1.03 WORK RESTRICTIONS AND LIMITATIONS

A. Allowable Work Hours: 7:30 a.m. to 4:30 p.m., Monday through Friday, unless approved by COR in writing. Comply with additional work hour restrictions listed in other specification sections.

B. Connect to City of Alamogordo infrastructure in accordance with City requirements, including the City’s Technical Standards.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used https://ci.alamogordo.nm.us/861/Engineering

Work Restrictions and Limitations

01 14 12 - 2

Project Management and Coordination

01 31 19 - 1

SECTION 01 31 19

PROJECT MANAGEMENT AND COORDINATION

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (Reclamation)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at https://www.usbr.gov/safety/rshs/index.html

1.03 SUBMITTALS

A. In accordance with Section 01 33 00 - Submittals:

B. RSN 01 31 19-1, Pre-Work Conference.

C. RSN 01 31 19-2, Design Visits and Meetings Notes.

D. RSN 01 31 19-3, Coordination Meeting Documentation:

1. Meetings shall be held at least monthly and can be held electronically or in person. The frequency can increase as needed for design team.

2. Provide agenda.

3. 4-week look-ahead schedule covering the following as applicable:

a. Shop fabrication review items and tasks.

b. Construction review items and tasks.

4. Work completed to date.

5. Meeting minutes from the previous weekly coordination meeting to include the following:

a. Include date, time, and list of attendees.

b. Summary of topics discussed.

c. List of action items including the following:

1) Description of action item.

2) Responsible party.

3) Date to be completed.

https://www.usbr.gov/safety/rshs/index.html

01 31 19 - 2

1.04 DESIGN MEETINGS

A. Pre-Work Conference:

1. Conducted after contract award and as needed.

2. Government and Contractor to review design submission and review procedures, discuss preliminary design schedule, phase completion of the design documents and construction activities.

B. Design Meetings:

1. Held weekly by conference call.

2. Face-to-face on a monthly basis or more frequently, as needed.

C. Document design site visits, phone, and in-person meetings. Include subject, names, discussion, recommendations, and conclusions.

D. 30-, 60- and 90- Percent Review Conferences:

1. Held by conference call for each design review package submittal.

2. Attendees: Contractor personnel responsible for the design.

3. Five days after the close of the review period.

4. Provide written summary of review conference.

E. Additional meetings shall be mutually agreed upon.

1.05 CONSTRUCTION COORDINATION

A. The following meetings are considered significant but do not relieve the Contractor from the responsibility of attending other meetings required by the specifications.

1. Weekly Coordination Meetings:

a. Attendees as required:

1) Contractor’s Project manager, project engineer, superintendent, and Quality Control

Supervisor, and pertinent subcontractors.

2) COR, project manager, project engineer, safety personnel, and other required

Government staff.

b. Purpose:

1) Review drawings, data, and technical requirements of specifications. Schedule, progress, and coordination:

a) Review safety, progress made, schedule, project issues, submittals, Request for

Information (RFI), and resolution necessary to meet specifications requirements.

b) Review dates that activities started and completed, remaining duration, and percent complete.

01 31 19 - 3

c) Review submittals register, submittals currently in review and approval, and meeting submittals due dates or delivery time frames.

d) Provide 3-week look-ahead schedule at least 3 Federal working days before start of meeting.

e) Review As-built Drawings.

f) Provide meeting minutes from the previous weekly meeting.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

01 31 19 - 4

Construction Program

01 32 20 - 1

SECTION 01 32 20

CONSTRUCTION PROGRAM

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: Include in prices offered in the Price Schedules for other items of work.

1.02 DEFINITIONS

A. Schedule: The Critical Path Method (CPM) of planning and scheduling a construction project where activities are arranged based on activity relationships and network calculations determining when activities can be performed and the critical path of the project.

B. Project Calendar(s): Cross reference of numerical workdays with calendar days. The project calendar serves as the basis for the day/date conversion and assigns workdays and non-workdays.

1.03 REFERENCE STANDARDS

A. Associated General Contractors of America (AGC)

1. AGC Manual-04 Construction Planning and Scheduling

Manual

1.04 SUBMITTALS

A. In accordance with Section 01 33 00 - Submittals.

1. Furnish database files in format compatible with Oracle Primavera P6 Professional

Project Management or Microsoft Project (release 2019 or newer).

2. Upon request, provide information and data used to develop and maintain the

Construction Program to CO.

B. RSN 01 32 20-1, Baseline Schedule:

1. Include:

a. Construction Program/Schedule database.

b. Definition of project calendars.

c. Gantt chart (Bar chart) for project.

d. Activity report including all logic constraints consisting of predecessors, successors, and constraint dates.

C. RSN 01 32 20-2, Updated Schedule:

1. Include:

Construction Program

01 32 20 - 2

a. Construction Program database with updated activity and milestone data.

b. Definition of project calendars if revised from baseline calendars.

c. Gantt chart for project.

d. Narrative report specifically stating status of project.

1) If negative float exists, cite specific actions and conditions which caused the "behind schedule" condition and provide proposed course of action to complete the project within the specified delivery time.

2) List of Contractor-initiated changes to the current schedule stating the reason for the action taken and unresolved issues relating to the Construction Program. Government reserves the right to reject Contractor-initiated changes to the current schedule which negatively impact Government action which was initiated on the basis of the current schedule.

1.05 SCHEDULE

A. Develop, maintain, and use approved Construction Program to plan, monitor, report, and evaluate accomplishment of work.

B. Prepare construction schedules using Critical Path Method outlined in AGC Manual.

C. Failure to include an element of the work will not release Contractor from completing all required work under the contract.

D. Construction Program:

1. Prepare detailed activity network for accomplishing required work organized by work breakdown structure.

2. Prepare schedule based on required sequence and interdependence of activities.

3. Include work of subcontractors, Government interfaces, and contract milestones.

4. Include contract title, contract number, and Contractor's name on each sheet.

5. Adjust Construction Program/schedule for seasonal weather conditions.

6. Define activities to a level of detail resulting in their durations being no greater than 20 workdays unless otherwise accepted by CO.

a. Durations for administrative activities (e.g., submittals and reviews, fabrication, manufacturing), or other specific activities identified in the contract shall not be subject to the workday limitation.

7. Use durations in units of whole workdays.

8. Include activities for Government reviews and approvals of submittals that are critical to the project completion data.

a. Include 30-, 60-, 90-, and 100-percent design submittals.

01 32 20 - 3

b. Combined submittals package as described in Section 01 81 05 - General Performance

Requirements.

c. Incremental design packages described in Section 01 12 16 - Work Sequence.

9. Update schedule with changes directed by contract modifications or approved changes to sequencing.

E. Cost-Loading Schedule:

1. Cost loading is defined as Contractor earnings based on payments from Government to

Contractor.

2. Input contract values as Expenses planned costs in Primavera P6 database.

3. Allocate contract value to schedule activities per CLIN amounts in accordance with contract requirements and Measurement and Payment statements in specifications.

4. Assign values to appropriate activities:

a. Total of activity values equal total contract value.

b. Each activity does not require a value.

c. Examples of activities that typically have no value are submittals, submittal reviews, and manufacturing.

5. Include separate schedule activities to properly depict correct amount and timing of payment, if necessary, such as Deliver activities.

6. Generate cash flow reports showing estimated monthly earned value of activities.

7. Report showing each activity cash flow for project duration.

8. Report showing cumulative monthly cash flow for project duration.

9. Generate Activity value report showing value of each activity.

10. Assign contract values for contract modification activities.

F. Baseline Schedule:

1. Represents Contractor’s as-planned approach to accomplishing the work.

2. Include planned start and completion dates for features of work.

G. Updated Schedule:

1. Enter actual progress.

2. Assign a unique project file name for each schedule update.

H. Contract Change or Delay:

1. Submit a time impact evaluation within 14 days of contract change or delay, showing effects of change order or delay on the progress schedule.

2. Time extensions for performance will be considered only to the extent that Contractor’s current scheduled milestone dates exceed the contract milestone dates.

01 32 20 - 4

I. Float is not for the exclusive use by or benefit of either Government or Contractor.

J. If in the opinion of CO, Contractor falls behind the approved schedule, Contractor shall take steps necessary to improve its progress, including those that may be required by CO.

1. CO may require Contractor to increase the number of shifts, overtime operations, days of work, or the amount of construction plant, and to submit for approval a supplementary schedule or schedules in chart form as CO deems necessary to demonstrate how the approved rate of progress will be regained.

2. Costs for actions required to improve progress are Contractor’s responsibility.

1.06 FAILURE TO COMPLY

A. Failure to comply with the requirements of this section shall be grounds for a determination by CO that Contractor is not prosecuting the work with sufficient diligence to ensure completion within the specified time.

B. CO may terminate Contractor’s right to proceed with the work, or a separable part of it, in accordance with the default terms of this contract.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Submittals

01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost: Include in prices offered in the Price Schedules for other items of work.

1.02 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

C. Submittal Types, as listed in Table 01 33 00A - List of Submittals:

1. A - Action:

a. Government will respond as to adequacy of submittal.

b. Action submittals are considered to be “shop drawings” within terms of clause at FAR

52.236-21, Specifications and Drawings for Construction.

2. I - Informational:

a. Government will acknowledge receipt of Informational submittals.

b. Government may reject an Informational submittal when submittal does not satisfy contract requirements. Correct mistakes or deficiencies in rejected Informational submittals and resubmit.

c. Informational submittals are considered to be “shop drawings” within terms of clause at

FAR 52.236-21, Specifications and Drawings for Construction, except that approval by

Government is not required.

1.03 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1 Decimal Inch Drawing Sheet Size and

Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS United States National CAD Standards

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

01 33 00 - 2

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement Units: US Customary Units.

4. Provide a unique transmittal number for each submittal.

5. Electronic documents shall have searchable text.

C. Drawings:

1. Minimum Identification in Title Block:

a. Contract number and title.

b. Contractor’s or supplier’s title and drawing number.

c. Date.

2. Reserve 3- by 3-inch space next to title block for review stamps.

3. Paper Size or Computer Drafting Paper Space: D size (22 inches by 34 inches) as defined by ASME Y14.1.

4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.

a. Computer drafted drawings:

1) In accordance with NIBS NCS.

2) Electronic file format: Compatible with Autodesk products including AutoCAD, Version 2020 or later, manufactured by Autodesk, Inc., Sausalito, CA.

3) Compile using “eTransmit” utility in AutoCAD.

b. Drawing prepared with drafting equipment, when allowed: Lettering shall be neat.

5. Drawings Designated as “Government Format” in Specifications:

a. Computer drafted.

b. Government will provide electronic AutoCAD format template.

c. Title block and sheet format:

1) As shown on Standard Drawing 40-D-7102.

2) Government will supply template.

3) Government will supply specific title block information to be used.

6. Final Drawings:

a. Computer drafted.

b. Government will supply electronic AutoCAD format template.

c. Show as-built changes, including revision dates, made during installation. Indicate changes by clouding.

01 33 00 - 3

7. Electronic Files: CD or DVD discs, portable memory storage devices, FTP site, or

Electronic Management System.

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner to allow clear photocopying (no highlighter).

d. Strike through items that do not apply.

E. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

F. Manuals:

1. Copies: Bound and indexed.

2. Copies:

a. Printed copies: Bound and indexed.

b. Electronic copies: Adobe pdf on CD or DVD discs. Bookmark longer files to assist in navigating file.

3. Contents:

a. Parts identification lists, lists of special tools, and accessories.

b. Schematics and wiring diagrams.

c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.

d. As-built Drawings, photographs, and test records or reports if required by the specifications.

G. Photographs: Include digital files on CD or DVD in .jpeg or similar format.

H. Samples and Color Selection Submittals:

1. Label with complete manufacturer's product and color identification.

2. Include type and quantity of materials specified in the referenced section in each “set” of samples.

3. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.

4. Color Chips: Sample paint chips. Ink color reproductions are not acceptable.

01 33 00 - 4

5. Label each sample, sample kit, set of color chips, or color chart with contract number and title.

6. Government will select architectural color and pattern after product approval.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals

Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit number of sets specified in “No. of sets to be sent to:” columns in Table 01 33 00A

- List of Submittals.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 10 days after receiving comments unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

F. More than one RSN may be submitted under a transmittal letter, provided responsible code is same.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 21 calendar days for review of each submittal or resubmittal unless otherwise specified.

2. Submittal review will require 28 calendar days for review of 30-Percent Design, 60-Percent Design, and 90-Percent Design submittals unless otherwise specified.

01 33 00 - 5

3. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.

a. Time extension will be to extent that excess review time caused delay to contract completion date.

b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending contract completion date.

2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to extent that:

a. Approval was required under contract, and.

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR

52.242-14, Suspension of Work; however, no such delay shall be deemed to be a

“suspension order” as the term is used in that clause.

C. Return of Submittals:

1. Action Submittals: One set of submittals required for action will be returned either approved, approved with comments, or not approved.

a. Submittals that are not approved shall be revised and resubmitted.

b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.

2. Informational Submittals: Government will acknowledge Informational submittals.

a. Informational submittals will not be returned when they satisfy contract requirements.

b. Informational submittals that do not satisfy contract requirements may be returned for resubmittal or additional information may be requested.

1.07 TRANSMITTAL

A. Addresses for codes listed in Table 01 33 00A - List of Submittals:

1. Contract Specialist, Valerie Jiron, Bureau of Reclamation, 555 Broadway NE Suite 100, Albuquerque, NM 87102.

2. Project Manager, 500 Lavelle Road, Alamogordo, NM 88310.

01 33 00 - 6

3. Technical Service Center, Bureau of Reclamation, Attn: 86-68160, P.O. Box 25007, Denver CO 80225-0007; Express Mail: Sixth and Kipling, Building 67, Room 152.

B. Send original transmittal letter with appropriate number of sets to office listed in

“Responsible Code” column in Table 01 33 00A - List of Submittals.

1. Responsible codes starting with “86-6” are located in Technical Service Center. Send these submittals to TSC address shown above.

C. Send copy of transmittal letter with appropriate number of sets to offices that are not responsible code, but show “No. of sets to be sent to” in Table 01 33 00A - List of

Submittals.

D. When “No. of sets to be sent to” is 0, send a copy of transmittal letter to that office.

E. Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:

1. Submit in accordance with this section.

2. Submit to Project Manager unless otherwise specified.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Table 01 33 00A - List of Submittals

* Submittal Types: A - Action, I - Information

** CO indicates Contracting Officer, PM indicates Project Manager, and TSC indicates Technical Service Center.

RSN

Clause or

Section

Title

Submittals required

Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO PM TSC

01 14 19-1 Use of Site Land Use and

Landscape

Rehabilitation

Plan

At least 28 days before use of Government land

A COR 0 1 0

01 31 19-1 Project

Management and

Coordination

Pre-Work

Conference

Within 28 days after Notice to Proceed

I COR 0 1 0

01 31 19-2 Project

Management and

Coordination

Design Visits and

Meetings

Within 7 days after visit or meeting

I COR 0 1 0

01 31 19-3 Project

Management and

Coordination

Weekly

Coordination

Meeting

Documentation

Weekly I COR 0 1 0

01 32 20-1 Construction

Program

Baseline Schedule Within 21 days after receipt of Notice to Proceed

I COR 0 1 0

01 33 00 - 7

Table 01 33 00A - List of Submittals

* Submittal Types: A - Action, I - Information

** CO indicates Contracting Officer, PM indicates Project Manager, and TSC indicates Technical Service Center.

RSN

Clause or

Section

Title

Submittals required

Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO PM TSC

01 32 20-2 Construction

Program

Updated Schedule With monthly requests for progress payments

I COR 0 1 0

01 35 10-1 Safety Data

Sheets

Complete LHM and SDS

At least 14 days before jobsite delivery of hazardous material

I COR 0 1 0

01 35 10-2 Safety Data

Sheets

Updated LHM and SDS

At least 14 days before jobsite delivery of hazardous material not previously listed

I COR 0 1 0

01 35 20-1 Safety and

Health

Resumes Submitted and accepted before mobilization

I COR 0 1 0

01 35 20-2 Safety and

Health

Safety Program Submitted and accepted before commencing onsite mobilization. See RSHS

Section 3.

I COR 0 1 0

01 35 20-3 Safety and

Health

Job Hazard

Analysis List

At least 14 days before commencing work

I COR 0 1 0

01 35 20-4 Safety and

Health

Monthly Accident

Summary Report

Monthly I COR 0 1 0

01 46 00-1 Quality

Procedures

Contractor

Quality Control

Program

Submitted and accepted at least 28 days before mobilization

I COR 0 1 0

01 46 00-2 Quality

Procedures

Contractor’s

Daily Reports

Weekly I COR 0 1 0

01 46 00-3 Quality

Procedures

Quality Control

Supervisor

Resume

Submitted and accepted at least 28 days before mobilization

I COR 0 1 0

01 46 00-4 Quality

Procedures

Contractor’s

Quality Testing

Plan

Submitted and accepted at least 28 days before mobilization

I COR 0 1 0

01 46 00-5 Quality

Procedures

Summary of Test

Results

Monthly I COR 0 1 0

01 46 20-1 Testing Agency

Services

Qualifications and

Testing Agency

Service Plan

Submitted and accepted at least 28 days before mobilization

I COR 0 1 0

01 46 20-2 Testing Agency

Services

Initial Contractor

Quality Test

Results

Within 24 hours after test completion

I COR 0 1 0

01 46 20-3 Testing Agency

Services

Final Contractor

Quality Testing

Results

Within 7 days after test completion

I COR 0 1 0

01 56 10-1 Protection of

Existing

Installations

Plan for

Protecting

Existing

Installations

At least 21 days before mobilization

01 33 00 - 8

Table 01 33 00A - List of Submittals

* Submittal Types: A - Action, I - Information

** CO indicates Contracting Officer, PM indicates Project Manager, and TSC indicates Technical Service Center.

RSN

Clause or

Section

Title

Submittals required

Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO PM TSC

01 56 10-2 Protection of

Existing

Installations

Initial

Construction Site

Recording

At least 21 days before mobilization

I COR 0 1 0

01 56 10-3 Protection of

Existing

Installations

Post Construction

Site Recording

Within 14 days after completion of construction activities

I COR 0 1 0

01 57 15-1 Utility Line

Investigations

Locating Utility

Lines Plan

Submitted and accepted at least 28 days before beginning utility lines location work

I COR 0 1 0

01 57 15-2 Utility Line

Investigations

Permits Submitted and accepted at least 28 days before beginning work in area of each utility line

I COR 0 1 0

01 57 15-3 Utility Line

Investigations

Utility Lines

Information

Within 4 days after each utility line is located

I COR 0 1 0

01 57 30-1 Water Pollution

Control

Pollution

Prevention Plan

At least 28 days before start of onsite construction work

I COR 0 1 0

01 57 50-1 Tree and Plant

Protection

Protection Plan At least 28 days before commencing construction activities

I COR 0 1 0

01 57 90-1 Preservation of

Historical and

Archaeological

Data

Alternate Use

Area or Borrow

Plan

At least 28 days before start of onsite construction work

I COR 0 1 0

01 74 00-1 Cleaning and

Waste

Management

Waste Production and Disposal Plan

At least 28 days before starting onsite work

I COR 0 1 0

01 74 00-2 Cleaning and

Waste

Management

Waste Production and Disposal

Records

Within 7 days after disposal I COR 0 1 0

01 78 30-1 Project Record

Documents

Final Drawings Within 14 days after acceptance of final As-Built

Drawings

I COR 0 1 0

01 78 30-2 Project Record

Documents

O&M Manuals Within 28 days after completion of work

A COR 0 1 0

01 78 30-3 Project Record

Documents

List of Extra

Materials

Within 28 days after completion of work

I COR 0 1 0

01 78 30-4 Project Record

Documents

Warranties Within 28 days after completion of work

I COR 0 1 0

01 79 20-1 Training Training

Materials

Submitted and accepted

28 days before training session

A COR 0 1 1

01 79 20-2 Training Training Video Within 14 days after completion of training

01 33 00 - 9

Table 01 33 00A - List of Submittals

* Submittal Types: A - Action, I - Information

** CO indicates Contracting Officer, PM indicates Project Manager, and TSC indicates Technical Service Center.

RSN

Clause or

Section

Title

Submittals required

Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO PM TSC

01 81 05-1 General

Performance

Requirements

Subsurface Utility

Engineering

Report

Per Contractor’s accepted baseline schedule and updates in

RSN 01 32 20-1 and -2

A COR 0 1 1

01 81 05-2 General

Performance

Requirements

30-Percent Design Per Contractor’s accepted baseline schedule and updates in

RSN 01 32 20-1 and -2

A COR 0 1 1

01 81 05-3 General

Performance

Requirements

30-Percent

Comment

Response

Within 14 days after receiving Government comments

A COR 0 1 1

01 81 05-4 General

Performance

Requirements

60-Percent Design Per Contractor’s accepted baseline schedule and updates in

RSN 01 32 20-1 and -2

A COR 0 1 1

01 81 05-5 General

Performance

Requirements

60-Percent

Comment

Response

Within 14 days after receiving Government comments

A COR 0 1 1

01 81 05-6 General

Performance

Requirements

90-Percent Design Per Contractor’s accepted baseline schedule and updates in

RSN 01 32 20-1 and -2

A COR 0 1 1

01 81 05-7 General

Performance

Requirements

90-Percent

Comment

Response

Within 14 days after receiving Government comments

A COR 0 1 1

01 81 05-8 General

Performance

Requirements

100-Percent

Design

Per Contractor’s accepted baseline schedule and updates in

RSN 01 32 20-1 and -2

I COR 0 1 1

01 81 05-9 General

Performance

Requirements

Construction

Progress

Submittals

Per Contractor’s accepted submittal table in

RSN 01 81 05-8

100-Percent Design

I COR 0 1 1

01 81 05-10 General

Performance

Requirements

100-Percent

Construction

Within 28 days after completing construction

I COR 0 1 1

01 91 16-1 Facility

Commissioning

Facility

Commissioning

Test Plan

At least 28 days before start of facility commissioning

A COR 0 1 1

01 91 16-2 Facility

Commissioning

Facility

Commissioning

Test Procedures

At least 28 days before start of facility commissioning

A COR 0 1 1

01 91 16-3 Facility

Commissioning

System Turnover

Books

Within 28 days after completing Monitored Test

A COR 0 1 1

01 91 16-4 Facility

Commissioning

Discrepancy List Monthly during facility commissioning

A COR 0 1 1

01 33 00 - 10

Table 01 33 00A - List of Submittals

* Submittal Types: A - Action, I - Information

** CO indicates Contracting Officer, PM indicates Project Manager, and TSC indicates Technical Service Center.

RSN

Clause or

Section

Title

Submittals required

Due date or delivery time

Type

Respon-sible code

No. of sets to be sent to: **

CO PM TSC

01 91 16-5 Facility

Commissioning

Preliminary SOPs At least 28 days before start of facility commissioning

A COR 0 1 1

01 91 16-6 Facility

Commissioning

Final SOPs Within 28 days after…