Attachment_1_Specifications_FRST_240745.pdf
PDF 12 MB Posted
- Attached to
- Re-Solicit: FRST 240745 - Rehab Sheriff House
- Solicitation number
- 140P2021R0148
About this file
This document provides details for a federal contract solicitation to rehabilitate a historic sheriff's house. The solicitation number is 140P2021R0148 and seeks to rehabilitate the historic sheriff's house at First State National Historical Park in New Castle, Delaware. This is a re-solicitation of a previous solicitation under number 140P2021R0064 for which no contract award was made. The National Park Service National Office within the Department of the Interior is the contracting agency. Interested parties should review the attached specifications document for additional requirements and response details.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
First State National Historic Park
Rehabilitate the Historic Sheriff’s House
FRST PMIS No. 240745
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
100% Final Construction Documents Submission
June 25, 2021
06/25/2021
6/25/2021
FRST - 240745 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 26 01 CONTRACT MODIFICATION PROCEDURES
01 27 00 DEFINITION OF CONTRACT LINE ITEMS
01 31 00 PROJECT MANAGEMENT & COORDINATION
01 32 16 CONSTRUCTION SCHEDULE
01 32 33 PHOTOGRAPHIC DOCUMENTATION
01 33 23 SUBMITTAL PROCEDURES
01 35 13.22 ARCHEOLOGICAL PROTECTION
01 35 23 SAFETY REQUIREMENTS
01 35 91 HISTORIC PRESERVATION TREATMENT PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 42 00 REFERENCE STANDARDS
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 57 19.11 INDOOR AIR QUALITY MANAGEMENT
01 57 19.12 NOISE & ACOUSTICS MANAGEMENT
01 57 23 TEMPORARY STORM WATER POLLUTION PREVENTION
01 67 00 PRODUCT REQUIREMENTS
01 73 29 CUTTING AND PATCHING
01 73 40 EXECUTION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 77 00 CLOSEOUT PROCEDURES
01 78 23 OPERATION AND MAINTENANCE DATA
01 79 00 DEMONSTRATION AND TRAINING
01 81 13 SUSTAINABLE DESIGN REQUIREMENTS
01 91 14 TOTAL BUILDING COMMISSIONING
DIVISION 02 – EXISTING CONDITIONS
02 41 00 SELECTIVE DEMOLITION
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
02 83 13 LEAD HAZARD CONTROL ACTIVITIES
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 01 10 MASONRY CLEANING
04 01 40 STONE REPAIR
04 03 34 HISTORIC BRICK AND STONE MASONRY REPOINTING
04 05 11 REPOINTING MORTAR
04 20 00 UNIT MASONRY
04 40 50 RESETTING EXISTING GRANITE CURBING
FRST - 240745 TOC-2
DIVISION 05 – METALS
05 12 00 STRUCTURAL STEEL
05 51 33 METAL LADDERS
05 52 13 PIPE AND TUBE RAILINGS
05 70 00 DECORATIVE METAL (EXHIBIT DESIGN)
05 75 00 DECORATIVE FORMED METAL (EXHIBIT DESIGN)
DIVISION 06 – WOOD, PLASTICS, & COMPOSITES
06 03 12 HISTORIC WOOD REPAIR
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 40 23 INTERIOR ARCHITECTURAL WOODWORK (EXHIBIT DESIGN)
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 21 00 THERMAL INSULATION
07 54 00 THERMOPLASTIC MEMBRANE ROOFING
07 61 00 SHEET METAL ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 – OPENINGS
08 14 33 STILE AND RAIL WOOD DOORS
08 58 10 CUSTOM STORM WINDOWS
08 71 00 DOOR HARDWARE
DIVISION 09 – FINISHES
09 01 90 PREPARATION FOR PAINTING
09 03 20 HISTORIC TREATMENT OF PLASTER
09 21 16 GYPSUM BOARD ASSEMBLIES
09 22 16 NON-STRUCTURAL METAL FRAMING
09 23 00 GYPSUM PLASTERING
09 30 00 TILING
09 64 29 WOOD STRIP AND PLANK FLOORING
09 91 13 EXTERIOR PAINTING
09 91 23 INTERIOR PAINTING
09 91 33 POWDER COAT FOR METALS
09 93 00 STAINING AND TRANSPARENT FINISH (EXHIBIT DESIGN)
DIVISION 10 – SPECIALTIES
10 14 00 SIGNAGE
10 14 23 GRAPHIC PANELS (EXHIBIT DESIGN)
10 28 00 TOILET AND BATH ACCESSORIES
10 44 00 FIRE PROTECTION SPECIALTIES
DIVISION 11 – EQUIPMENT
FRST - 240745 TOC-3
11 33 00 RETRACTABLE STAIRS
11 55 00 AV AND INTERACTIVE SYSTEMS (EXHIBIT DESIGN)
DIVISION 12 – FURNISHINGS
12 24 00 WINDOW SHADES
12 32 00 MANUFACTURED WOOD CASEWORK
12 36 00 COUNTERTOPS
DIVISION 13 – (NOT USED)
DIVISION 14 – CONVEYING EQUIPMENT
14 42 00 WHEELCHAIR LIFTS
DIVISION 21 – FIRE SUPPRESSION
21 13 13 WET-PIPE SPRINKLER SYSTEMS
21 13 16 DRY-PIPE SPRINKLER SYSTEMS
DIVISION 22 – PLUMBING
22 08 00 PLUMBING SYSTEMS COMMISSIONING
22 11 19 PLUMBING SYSTEMS PUMPS
22 34 00 DOMESTIC WATER HEATERS
22 40 00 PLUMBING FIXTURES AND EQUIPMENT
DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING
23 05 00 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48 MECHANICAL SOUND AND VIBRATION CONTROLS
23 05 93 TESTING, ADJUSTING, AND BALANCING
23 07 00 MECHANICAL INSULATION
23 08 00 HVAC SYSTEM COMMISSIONING
23 20 00 BUILDING SERVICES PIPING
23 31 13 DUCTWORK
23 33 00 AIR DUCT ACCESSORIES
23 34 16 FANS
23 37 13 AIR OUTLETS AND INLETS
23 28 29 VARIABLE REFRIGERANT SYSTEMS
23 82 39 UNIT HEATERS
DIVISION 26 – ELECTRICAL
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19 ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
26 05 43 UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS
FRST - 240745 TOC-4
26 05 44 SLEEVES AND SLEEVE SEALS FOR ELECRICAL RACEWAYS AND CABLING
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 05 72 SHORT-CIRCUIT STUDY
26 05 74 OVERCURRENT ARC-FLASH STUDY
26 08 00 COMMISSIONING OF ELECTRICAL
26 09 23 LIGHTING CONTROL DEVICES
26 24 16 PANELBOARDS
26 27 13 ELECTRICITY METERING
26 27 26 WIRING DEVICES
26 28 13 FUSES
26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 29 13 MANUAL AND MAGNETIC MOTOR CONTROLLERS
26 33 23 CENTRAL BATTERY INVERTERS
26 41 13 LIGHTNING PROTECTION FOR STRUCTURES
26 43 13 SURGE PROTECTION
26 51 00 INTERIOR LIGHTING
26 51 10 HISTORIC LUMINAIRE RESTORATION
26 52 13 EMERGENCY LIGHTING
DIVISION 27 – COMMUNICATIONS
27 05 29 HANGERS AND SUPPORTS FOR COMMUNICATIONS SYSTEMS
27 11 16 COMMUNICATIONS RACKS, FRAMES, AND ENCLOSURES
27 15 13 COMMUNICATIONS COPPER HORIZONTAL CABLING
DIVISION 28 – ELECTRONICS SAFETY AND SECURITY
28 05 00.10 COMMON WORK RESULTS FOR ELECTRONIC SECURITY
28 05 13.10 SERVERS, WORKSTATIONS, AND STORAGE FOR ELECTRONIC SECURITY
28 08 00.10 COMMISSIONING OF ELECTRONIC SECURITY
28 15 00.10 SECURITY HORIZONTAL CABLING
28 20 00 VIDEO
28 31 00 INTRUSION DETECTION
28 31 11 DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM
DIVISION 31 – EARTHWORK
31 23 33 UTILITY TRENCHING AND BACKFILLING
31 30 00 EARTHWORK (SITE)
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 15 TRENCH REPAIR ASPHALT PAVING
32 14 16 BRICK UNIT PAVING
32 92 20 SEEDING
DIVISION 33 – UTILITIES
33 01 30.73 MANHOLE REHABILITATION
33 10 00 WATER UTILITIES
33 34 00 SANITARY UTILITY SEWERAGE PIPING SYSTEMS
FRST - 240745 TOC-5
33 40 20 WARNING AND TRACER TAPE
END OF CONTENTS
FRST - 240745 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work Covered by the Contract Documents
2. Contractor Use of Premises
3. Public Use of Site
4. Occupancy Requirements for Buildings
5. Conduct of Operations
6. Work Restrictions
7. Special Construction Requirements
8. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: The Sheriff’s House is an urban building located at 10 Market Street, New Castle, Delaware 19720. It is part of the First State National Historical Park and is a contributing structure to the New Castle National Historic Landmark Historic District and is listed in the National Register of Historic Places.
B. The Work consists of the following:
1. The Work consists of rehabilitating the long-vacant historic Sheriff’s House to provide public visitor accommodations on the first floor and Park offices on the second floor.
C. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF PREMISES
A. General: Contractor shall have full use of the building for construction operations during the construction period. Contractor's use of the building is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Storage of Materials: Storage of materials must be confined to the interior of the building. No exterior on-site storage will be permitted. Contractor may arrange and pay for off-site materials at a facility of the Contractor’s choosing. Environmental conditions for stored materials specified herein and in manufacturers’ written product data and instructions shall be maintained at the off-site storage location.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings and resources. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
FRST - 240745 01 11 00 - 2
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
CO and remove agreed-on roots and branches that interfere with construction.
D. Construction Camp: Establishment of a camp within the park will not be permitted.
E. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
1.4 PUBLIC USE OF SITE
A. The building will be closed to the public during construction; however, the adjacent New Castle
Court House Museum and the New Castle Green are expected to remain fully open and accessible to the public during construction.
1.5 OCCUPANCY REQUIRMENTS FOR BUILDINGS
A. Existing Buildings
1. Sheriff’s House: Maintain the existing building in a weather tight condition throughout the construction period. Repair damage caused by construction operations.
2. New Castle Court House Museum: The Court House Museum is a neighboring building that shares a side courtyard and rear access area with the Sheriff’s House. The State of
Delaware Division of Historical and Cultural Affairs owns the building and will occupy and operate it as a museum and office space continually throughout the construction project.
a. Cooperate with Government and State of Delaware during construction operations to minimize conflicts and facilitate State of Delaware usage.
b. Perform the Work so as not to interfere with the State of Delaware’s day-to-day operations.
c. Maintain existing exits, unless otherwise indicated.
d. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.
e. Provide State of Delaware staff and/or contractors access to the existing utility room in the basement, the chillers in the fenced in area, and the boiler room accessed through the rear of the Sheriff’s House upon request. Do not impede State of DE access to these spaces afterhours.
f. Repair damage to the Court House Museum building and site caused by construction operations. Any portions of the walls, etc. of the Court House that are damaged during demolition or construction should be repaired to their original condition using materials that are sensitive and in-keeping with the historic building and the
Secretary's Standards.
g. Utility or other disruptions that will affect operations of the Court House Museum shall be planned in advance during preconstruction scheduling, with a schedule of outages and disruptions to be approved by the CO and the State of Delaware.
1) Unanticipated disruptions or outages to the Court House Museum will require a minimum of 14 days advanced written notice.
FRST - 240745 01 11 00 - 3
1.6 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the CO. Submit requests 2 days in advance of the work to the CO for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the CO.
D. Contractor(s) and contractor personnel shall be required to adhere to the following standards of dress, conduct, supervision, and training while performing the work. It shall be the discretion of the CO to implement immediate removal of Contractor and/or contractor personnel from the premises if these standards are not adhered to during the performance of the contract. Contractor shall be responsible for training and safety precautions, prescribed by OSHA standards regarding safety equipment and devices. Contractor shall administer disciplinary action immediately as required to contractor employees.
1. Be fully clothed at all times, to include an upper garment to cover the body from the waist to neck and long pants or slacks. Garments which have a message, slogan or printing of any kind other than the Contractors business attire is prohibited. (Other approved clothing by the CO is negotiable).
2. Shall not engage in loud or boisterous behavior or use profane or abusive language. The
Contractor(s) and contractor employees must always exercise and exhibit absolute decorum, courtesy, and respect while on the site or at its perimeter or entrances.
3. Contractor and/or contractor personnel shall not lean, sit, or stand on or against gravestones or monuments. No tools or other items shall be placed on or leaned against any gravestone or monument.
4. Food and beverages shall be consumed only within areas designated by the Contractor and approved by the CO. Use or sale of intoxicating beverages and/or drugs is strictly prohibited. Breaks and lunch breaks shall be taken at areas designated.
5. Smoking is prohibited within the building, on the adjacent State of Delaware property
(including the New Castle Court House Museum building grounds, the entirety of the New
Castle Green and its walkways), and within 25 feet of building exterior perimeters.
Smoking will be permitted at an area to be designated by the Contractor and approved by the CO.
6. All above misconduct shall be cause for immediate removal from the premises.
1.7 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of
7:00 a.m. to 4:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Permitted on a case-by-case basis as approved by the CO with at least 2 days advance written notice.
FRST - 240745 01 11 00 - 4
2. Early Morning Hours: Permitted on a case-by-case basis as approved by the CO with at least 2 days advance written notice.
3. Hours for noise generating activities: 9:00 a.m. to 4:00 p.m., Monday through Friday, no exceptions.
B. Existing Utilities
1. Existing Utilities: Notify CO and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify CO in writing not less than 2 days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without CO’s written permission.
3. Maintain telephone and electrical service for building intrusion detection alarms with interruptions only permitted during normal business working hours. Contractor shall not leave site unattended with intrusion detection alarms in an inoperable state.
4. Hours for Utility Shutdowns: Utility shutdowns affecting the New Castle Court House
Museum shall occur outside the museum’s normal open hours of 10:00 a,m, to 4:30 p.m.
Tuesday-Saturday and 1:30 p.m. to 4:30 p.m Sunday.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.8 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
B. Sequencing: Contractor shall complete the following to minimize disruption to the active Court
House Museum located adjacent to this project:
1. Complete existing ramp demolition and new ramp construction at side courtyard prior to the commencement of other work.
2. Complete roof repair and replacement, exterior stone repair, and stone/brick repointing prior to the commencement of any interior restoration and replacement work.
FRST - 240745 01 11 00 - 5
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
FRST - 240745 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
FRST - 240745 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
FRST - 240745 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate
FRST - 240745 01 26 01 - 4
Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.
All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
FRST - 240745 01 26 01 - 5
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………….10% Profit………………8%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
FRST - 240745 01 26 01 - 6
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
FRST - 240745 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 0001 – Building Rehabilitation
1. This item consists of construction of the building as identified in the drawings and specifications. Building scope generally includes:
a. Selective demolition in support of the building rehabilitation scope including hazardous material abatement.
b. Foundation improvements including finish grading at the existing dirt basement floor in preparation for a new concrete slab on grade.
c. Structural improvements including temporary shoring; sistering of 100% of existing joist at first floor; sistering of 100% existing joist at second floor; subfloor repair and replacement; and LVL installation above Exhibit 114.
d. Building envelope improvements including exterior wall repointing; repair and repointing of masonry chimneys; chimney caps; new stone parapet; exterior wall cleaning; masonry beam pocket repair; stone repair at front entrance steps;
installation of aluminum storm windows; installation of power door operators; and preparations and repainting of all windows and exterior doors.
e. Roof improvements including removal and replacement of roof sheathing;
additional/replacement of roof rafters and support beams; rafter straps; installation of 4” batt insulation at rafter cavities; installation of 4” rigid insulation at rafter underside; installation of rigid insulation at attic walls, installation of roofing membrane over existing deck; installation of metal roofing panels; recoating existing metal roofing; and removal and replacement of downspout.
f. Interior space improvements including installation of new partitions and wall furring; enlargement of cased openings, miscellaneous brick patching; repairing existing doors and frames; installation of new door hardware; reinstallation of salvaged and modified doors; preparations and repainting of all interior doors;
restorations of iron jail cells; and installation of toilet room accessories. Also included is the restoration of historic wood stairs from Floor 1 to Floor 2; installation
FRST - 240745 01 27 00 - 2
of wood stairs from Basement Floor to Floor 1; installation of new handrail;
installation of prefabricated aluminum ladder at Floor 2 restroom; and attic access hatch and ladder for room 207. Restoration of existing fireplaces. Installation of plastic laminate countertops and backsplash; base cabinets and wall cabinets; and FCU custom cover cabinets.
g. Interior finishes rehabilitation including miscellaneous patching and repairing of floors, wall and ceilings to receiving new finishes; new and repaired plaster walls and ceilings; painting; miscellaneous brick patch repair; installation of ceramic wall/base tile at restrooms; patching and refinishing existing hardwood floors;
installing new wood flooring, sealing of concrete flooring; patch/repair and refinish wood base trim; install and finish new wood base trim; and restoration of crown molding.
h. Mechanical improvements including selective demolition of existing HVAC equipment and associated components; miscellaneous core drilling and cutting, miscellaneous patching and repair; VRF equipment, fan coils and condensing units;
exhaust fans; electric unit heats; sheet metal ductwork and accessories; duct liners and insulation; grilles and registers; louvers; piping, fittings and pipe hangers;
required excavations; and controls.
i. Electrical improvements including selective demolition of electrical systems, components and accessories; electrical conduits and fittings; lightning protection systems; grounding systems; miscellaneous core drilling, cutting and patching;
panelboards; hangers; motor and equipment connectors; receptacles; cover plates;
GFI receptacles; receptacles modules; lighting; lighting controls; lighting wiring;
telecom and AV system components and accessories; security system access control and monitoring; and fire detections and alarm system components and accessories.
j. Plumbing improvements including selective demolition of existing plumbing fixtures and components; installation of new plumbing fixtures; miscellaneous core drilling; miscellaneous firestop penetrations; copper piping and fittings; cast iron piping and fittings; pipe hangers; and steel piping and fittings.
k. Intrusion detection installation including intrusion detection panels, input module, output module, keypad, motion sensors, glass break sensors, door position switches, piezo sire, and duress alarm.
l. Fire suppression system installation including wet and dry sprinkler piping, piping;
pipe hangers; fire department connections; nitrogen generator and air compressor;
and fire extinguishers and cabinets.
2. Measurement for payment will be percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 0002 – Site Work
1. This item consists of construction of all site work as identified in the drawings and specifications. Site work scope generally includes miscellaneous saw cutting of brick and concrete paving; removing and salvaging of exiting brick paving; removing and salvaging of granite curb; general grading; and site demolition and earthwork, asphalt paving;
reinstallation of salvaged granite curbing; pedestrian paving; concrete site walls; concrete steps; brick ramp walls; metal ramp and stair railings; preparations and repainting of existing metal railings; inclined stair platform lift; signage; turf restoration; plant restorations; and wood fencing. Also included are all site utilities which includes excavation and installation of water supply lines; and excavations and installation of sanitary sewer lines. This work requires coordination with the NPS and NPS archeological monitor prior to the commencement of any ground disturbing work.
FRST - 240745 01 27 00 - 3
2. Measurement for payment will be percentage complete of line item per scheduled value
3. Payment will be made at the contract lump sum price.
C. Contract Line Item No. 0003 - Exhibits
1. This item consists of fabrication and installation of the exhibit elements as identified in the drawings, specifications and supporting design documentation. This generally includes AV (audio visual) media; exhibit components; tactile interactives; graphic rails; graphics and accessories; all exhibit support system components; av media hardware and accessories;
theater sound paneling; desk; merchandising tables and shelving; any ancillary components to provide a fully functional exhibit installation. Electrical and data installation are assumed to occur under CLIN 1; final connection of all exhibit components to provide a fully functional exhibit installation is included in this item.
2. Measurement for payment will be percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
FRST - 240745 01 31 00 - 1
091015 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Construction Coordination.
2. Submittals
3. Coordination Drawings.
4. Requests for Information (RFIs).
5. NPS/DSC SharePoint Project Website.
6. Project meetings.
7. Environmental Coordination.
8. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
4. Section 01 91 14 “Total Building Commissioning” for coordinating the work with
Owner’s Commissioning Authority.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
FRST - 240745 01 31 00 - 2
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
D. Witness Point: Coordinate scheduling, timing and construction operations of all exterior work, including site work, with NPS CO and Archaeology Monitoring Contractor. Coordinate construction operations, included in different Sections of the Specification, to ensure efficient and orderly installation of each part of the Work that allows for proper installation, connection, and operation.
1.3 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base
Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the CO for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 30 by 40 inches.
FRST - 240745 01 31 00 - 3
3. Number of Copies: Submit two opaque copies of each submittal. CO will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
3. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
4. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
5. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches (32 mm) in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
6. Fire-Protection System: Show the following:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
7. Review: CO will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform Contractor, who shall make changes as directed and resubmit.
8. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
FRST - 240745 01 31 00 - 4
2. File Preparation Format: AutoCad.dwg, operating in Microsoft Windows operating system.
3. File Submittal Format: Submit or post coordination drawing files using Portable
Document Format (PDF) file format.
4. CO will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.
a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
D. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. CO will notify Contractor of tentative date for the Pre-
Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Temporary Storm Water Pollution Prevention Plan (UPPP).
11. Indoor Air Quality (IAQ) Management Plan.
12. Contractor’s Commissioning Plan.
13. Historic Preservation Treatment Plan.
14. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
E. All items listed must be provided to the CO before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction
Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the
CO will consider other contractual remedies. Work shall not commence until written Notice to
Proceed has been issued.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
FRST - 240745 01 31 00 - 5
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select
“CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the
Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
FRST - 240745 01 31 00 - 6
1.5 PROJECT WEB SITE
A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period. The NPS/DSC SharePoint Project website will be used for the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting agendas and minutes.
4. Contract modifications forms and logs.
5. RFI form and processing.
6. Task and issue management.
7. Photo documentation.
8. Baseline schedule, schedule updates and calendar management.
9. Submittal form and processing.
10. Payment coordination documentation.
11. Drawing and specification document hosting, viewing, and updating.
12. Online document collaboration.
13. Reminder and tracking functions.
14. Archiving functions.
15. Notification of submittal and RFI statuses and current responsible party.
16. Permits and addendums
B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.
C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later
1.6 PROJECT MEETINGS
A.…