This document is a Statement of Objectives (SOO) for the engineering, furnishing, installation, and testing of a new 48-strand single mode fiber optic cable network from Building 603 to Buildings 1852 and 4148 at Pensacola Naval Air Station, Florida. The key objectives include installing new maintenance holes, handholes, ductwork, and fiber optic cabling to establish the new network infrastructure. The work must comply with various safety, security, environmental, and technical requirements, and the contractor must provide project management, quality assurance, testing, as-built documentation, and a one-year warranty. The overall period of performance is 180 calendar days, with the work to be performed at Pensacola NAS during normal duty hours, following federal holidays and down days. This SOO is in support of the related federal contract opportunity FA301024R0016 for the "NAS Pensacola FOC Project", which is a Total Small Business set-aside with a contract value between $500,000 and $1,000,000.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF OBJECTIVES (SOO)
For
Install Fiber Optic Cables from B603 to B1852 & B4148 at
Pensacola NAS FL
16 May 2023
Prepared By
38 ES/ENPC
4064 Hilltop Road
Tinker AFB OK 73145-2713
Attachment 1
FA301024R0016
SOO – Install Fiber Optic Cables from B603 to B1852 & B4148 Page | 2
1. SCOPE.
This Statement Of Objectives (SOO) defines the requirement for the Contractor to engineer, furnish, install and test (EFI&T) a new 48-strand single mode (SM) fiber optic cable (FOC) from Building (B) 603 to B1852 & B4148 at Pensacola NAS, FL.
The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOO. The Contractor shall comply with the current TIA telecommunication installation and testing commercial standard and base installation standards. All equipment, supplies, and materials provided will be new and not refurbished.
This is only a proposed solution. The Contractor may make any recommendations pertaining to the accomplishment of this requirement in their proposal.
2.0 REQUIREMENTS.
2.1 GENERAL REQUIREMENTS.
2.1.1 Safety Requirements.
The Contractor shall remain in compliance with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.
2.1.2 Site Coordination.
The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.
2.1.2.1 Confined Space.
The Contractors and Sub-contractors entering spaces on Pensacola NAS, FL are responsible for the safety of their personnel and for their own permit space program as outlined in AFMAN 91-203. All confined space operations must be coordinated with the Base Safety Office prior to start of work. The primary Contractor is responsible for all Sub-contractor confined space operations.
2.1.2.2 Accident/Incident Reporting and Investigation.
The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel. Notification will be provided to the 81 CS/SCXP Project Manager,the Base Safety Office, and the Contracting Officer unless otherwise stated in the SOO. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to investigate the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
2.1.2.3 Work Area(s).
At day’s end, the Contractor shall remove all debris and surplus materials from the workplace. Safety barriers will be in place to protect unfinished work site at the end of the day. All open holes or trenches will be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the workday. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard.
The Contractor shall co-ordinate with the 81 CS/SCXP to ensure that any locking manhole covers are put back in place at the end of each workday.
Page | 3
2.1.2.4 Traffic Control.
In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall notify the 81 CS/SCXP PM NLT 10 calendar days in advance to inform base Security Forces and Emergency Services personnel of the planned disruptions.
2.1.2.5 Airfield Driving.
Any person operating a motor vehicle inside the airfield fence on Pensacola NAS FL will coordinate with airfield management to obtain the required training/certifications IAW local procedures.
2.1.3 Security Requirements.
The Contractor shall process and provide a Superintendent Letter to 81 CS/SCXP within 5 calendar days after contract award. This letter will identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who will be performing work under this SOO. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel will wear these badges while on duty on the Government site. The badges will identify the individual, company name, be clearly and distinctly marked as Contractor, and be in accordance with base regulations.
2.1.3.1 Security Clearances.
Stated work and associated products will be performed at the UNCLASSIFIED level. However, some of this work may take place in secure areas where Contractor employees must always be escorted. The Contractor must coordinate access to secure areas at least five (5) calendar days ahead of time. It is the Government’s responsibility to provide escorts.
2.1.3.2 Operational Security (OPSEC).
Network infrastructure drawings (MHDS, MH/HH locations, fiber paths, etc.) are on the 81 CS/SCXP Critical Information List and must be protected. The Contractor shall take appropriate measures to protect detailed information pertaining to the EFI&T effort, to include appropriate marking of documents as “Controlled Unclassified Information (CUI),” and ensuring limited distribution of documents and schematics/drawings to only those individuals with a valid need to know. IAW AFI 10-701, OPSEC Considerations, the Contractor shall follow the OPSEC guidance/plan (AFI10-701) to ensure the protection of CUI data either furnished by the Government or produced by the Contractor.
2.1.4 Environmental Compliance.
The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations, and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The Contractors are responsible to know and follow all applicable Federal, State, Local and Air Force regulations for environmental protection, including waste disposal, sewer discharge, air emissions, and storm water requirements. The Contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Pensacola NAS FL. The Prime Contractor shall ensure that their subcontractors (if any) comply with these specifications.
2.1.5 Permits.
The Contractor shall be responsible to coordinate, complete and process all permits required to complete the installation prior to any trenching, horizontal directional boring or modifications to a facility, maintenance hole (MH) or hand-hole (HH). For example:
Page | 4
• Digging permit, AF Form 103 shall be submitted through BCE 14 calendar days in advance of digging activities. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 remains current.
• Confine space entry permit, AF Form 1024 shall be coordinated through base safety office. The Contractor shall be prepared to provide proof of their Confined Space Training Program along with the AF Form 1024 to base safety.
• Base Civil Engineering Work Clearance Request, AF Form 332 will be submitted through BCE 14 calendar days in advance of planned work.
• The Contractor shall trench, excavate, and mark and barricade open trenches IAW OSHA Standards.
All utility markings, flags, etc. will be maintained by the Contractor after the responsible work center/shop identifies/locates them and ensure that the AF Form 103 remains current. The Contractor shall take precautions to protect existing infrastructure. If a utility is severed or damaged due to neglect or if attributed to the fault of the Contractor, then the Contractor shall repair and return the utility back to the same condition it was in prior to the damage.
2.1.6 Quality Assurance.
The Contractor shall provide Quality Assurance Support for the entire life of the project. The Contractor’s quality assurance evaluator will assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A weekly report (soft copy) will be delivered/submitted to the Contracting Officer COB Monday, indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them.
2.1.7 Contractor Personnel.
2.1.7.1 Project Management.
The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.
2.1.7.2 Site Point of Contact (POC).
The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site Superintendent for individual projects in their Site Visit Request Letter. The Site Superintendent or alternate(s) will be on site during duty hours for the duration of the project, up to and until final acceptance by the Government PM and will oversee all facets of the installation tasks. The Site Superintendent will be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.
2.1.7.3 Personnel Requirements.
The Project Manager, Site Superintendent, and respective alternate(s) shall be able to read, write, speak, and understand English and shall be on site to coordinate permits, clearances, and receive shipments/material related to the contract.
2.1.7.4 Minimum Contractor Qualifications.
All work shall be performed by an experienced Telecommunications Contractor. The Contractor shall have a minimum of 3 years of experience in Telecommunications Systems installations.
Page | 5
2.1.8 Warranty.
The Contractor shall provide a one-year warranty or manufacturer’s standard commercial warranty, whichever is longer. This warranty shall include a one-year workmanship warranty. The warranty period will start from the date of system and/or project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.
2.1.9 Manuals and Practices.
The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new equipment.
2.2 SPECIFIC REQUIREMENTS.
As indicated in this SOO, the Contractor shall EFI&T a new 48-strand SM FOC from B603 to B1852 & B4148.
2.2.1 Outside Plant Requirements.
2.2.1.1 Existing Maintenance Holes.
The Contractor shall be responsible for pumping out maintenance holes/handholes. Water from maintenance holes/handholes will be drained onto grass, when possible, to act as a natural filter; then it may be pumped out onto the surrounding ground, as long as there is no impact to roads, driveways, or vehicle traffic. Mud and debris shall be disposed of IAW base requirements. If Contractor comes across a manhole with contaminated water, the Contractor shall coordinate with the environmental office in Base CE.
2.2.1.2 Measurements.
Any distances provided in this SOO are approximations and should NOT be used for ordering materials or determining duct lengths.
2.2.1.3 Underground Utilities Markings.
The Contractor shall coordinate with base agencies to ensure markings are placed over existing base infrastructure prior to digging or horizontal directional boring and will take precautions to protect existing infrastructure. The Contractor is responsible for repair of any damage caused during installation when the infrastructure is clearly marked. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 (Dig Permit) remains current.
2.2.1.4 Closures for Cable Splicing in Maintenance Holes.
Intermediate cable splices will be minimized and consist of fusion splices in a high quality re-enterable splice case. Only splice closures intended for underground applications will be used in the underground system. The Contractor shall use standard re-enterable fiber splice closures. The closures will have adequate strength to protect the splice and maintain cable shield electrical continuity in the below ground environment. The Government quality inspector will have the opportunity to inspect the inside of the splice case before closure pressure testing and encapsulation is performed. A coil of 25 feet of cable will be provided on each cable entering and leaving a splice case in a MH or HH. Not required when using blown fiber.
2.2.1.5 Splice Connectors.
All splicing shall be performed in accordance with RUS Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable. The Contractor shall use pic-a-bonds, 3M 710 splice connectors, or equivalent, for all copper splices.
Page | 6
2.2.1.6 Labeling.
The Contractor shall label all equipment and cables they install, and cables identified for re-use in accordance with TIA-606-B and as directed by the 81 CS/SCXP.
2.2.1.6.1 New Ducts.
New ducts shall be permanently labeled on the wall of each building/MH/HH indicating the connecting building/MH/HH at the other end of the duct (for example, “To MH-306H”). The same information shall appear on the Contractor’s completed as-built-drawings.
2.2.1.6.2 Fiber Optic Distribution Panel (FODP) Marking.
Each FODP shall be stenciled/marked with black ink or paint or adhesive backed decals in letters and numbers. The cover of all new fiber optic distributions (FODPs) shall be labeled to conform to the system used by local maintenance personnel to identify FODPs that terminate fiber. If the manufacturer has not identified the sequence in which ports on FODPs (pigtail modules) are counted, the Contractor shall provide designation labels/strips to identify the sequence in which they are counted. Each splice tray shall be marked to identify the fiber count contained in the splice tray. The marking shall identify the FODP by number (building number), cable number, and count.
Example (FODP): FODP 603
FOC 603-1852, 1-48 SM
FOC 603-4148, 1-48 SM
2.2.1.6.3 FOC Tags.
All tags shall be permanently labeled, easily visible and corrosion resistant. Install cable tags in all maintenance holes/hand-holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a maintenance-hole, put a tag on the cable, approximately 2 feet from each duct entrance. Information on the cable tag will identify cable by size, type, cable number and count. Tagging and labeling of new cables will be IAW the following:
Example (FOC Tag): 48L8.3F
FO 603-1852, 1-48
FO 603-4148, 1-48
First line: “48” stands for Fiber Count. “L” stands for Loose Tube Buffer or (“T”) for Tight Tube Buffer. “8.3” stands for Single Mode. “F” stands for Filled Core (otherwise leave blank).
Second line and following: “FO” stands for Fiber Optic cable. “603 - 1852” stands for From Building Number 603 to 1852. “1-48” stands for Cable/Strand Count.
Third line and following: “FO” stands for Fiber Optic cable. “603 - 4148” stands for From Building Number 603 to 4148. “1-48” stands for Cable/Strand Count.
2.2.1.7 FOC Terminations.
Fiber optic cable termination will be SC connectors with exception to LC connectors in the B603, Room 3024, with no splicing (home run installation), and no jumpers.
2.2.1.8 New Maintenance Holes/Hand holes.
Maintenance holes and Hand Holes installed under this contract shall have an American Association of State Highway and Transportation Officials (AASHTO) rating of H-20. Unless otherwise stated MHs
Page | 7 will have minimum interior dimensions of 6 feet W x 6 feet L x 7 feet H (Width, Length, and Height).
MHs will be furnished with a ladder, cable racks hardware, pulling irons, a sump, water resistance gaskets, bonding ribbon and a grounding system. MH will meet the requirements of TIA-758-B.
Prefabricated MHs are preferred. The MHs will have predrilled duct entry holes. New hand holes will have minimum interior dimensions of 4’ X 4’ X 4’, meet the requirements of TIA-758. Sump (with removable perforated cover), pulling-in irons, ¾” x 10’ground rod, telecommunications industry standard cable racks and hooks, and bonding ribbon attachments will be provided in all new hand holes. Round hand hole covers will be cast with 1/8” raised letters stating “COMMUNICATIONS” displayed on the outside. Coordination with 81 CS/SCXP will be required to identify local Grounding procedures; predrilled duct entry holes [sealed with knockouts configured for splayed entry in the end walls] with duct terminators to accept 4-inch I.D. schedule 40 conduit. It is understood that some MHs/HHs are precast with bonding ribbons or some similar connection, to the manhole rebar and therefore do not require a ground rod. This method of grounding in lieu of a ground rod is satisfactory just as long as the achieved impedance to ground is twenty five (25) ohms or less. MHs/HHs will be of concrete construction and meet the requirements of TIA -758B, paragraphs 5.2.1 and/or
5.2.2. Polymer concrete (i.e., Quazite) construction is NOT authorized.
Prefabricated MHs/HHs are preferred. MH/HH will be installed so that they are reasonably level on a gravel bed of 6 inches to allow drainage of water from the walls. The gravel bed should extend 8 inches to 12 inches beyond the outer edges of the MH/HH. MH/HH covers will be labeled with 1/8” raised letters stating “COMMUNICATIONS”.
2.2.1.9 Cable Racks and Cable Rack Supports.
Cable racks will be installed in maintenance holes and hand holes as required - this includes new and existing MHs/HHs. Splices will not be supported by the cables that enter each end of the splice case.
The splices will be supported by cable hooks under the splice case. Telecommunications industry standard cable hooks of the appropriate length will be provided to support cables and splice cases. The cable hooks will be secured using cable rack locking clips. All cables will be supported using racking clips, cable racks, and cable hooks.
2.2.1.10 Grounding.
Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc.
necessary to properly bond/ground the cable in MHs will be provided by the Contractor. Reference
ANSI/TIA 607.
2.2.1.11 Underground Conduit System.
The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools. Provide a minimum of 12" cover of clean fill above the conduit.
Backfill material will be clean and free from all organic material, clay, marl or unstable materials, debris, lumps, or broken paving. No rocks or stones larger than 3 inches in diameter will be allowed in backfill. Material for backfill may be material resulting from excavation if it meets the above requirements. Directional drilling will be used for major road crossings. Otherwise, crossing of paved surfaces may be performed by pavement cuts and resurfacing with appropriate matching road material.
This does not prevent the Contractor from using directional drilling if it is more cost effective. Ducts will be appropriately protected when placed under paved surfaces.
Page | 8
2.2.1.11.1 Install new micro-duct.
a. The new micro-duct will be comparable with Dura Line Future path 18mm OD/14mm ID system and be suitable for direct buried applications.
b. Each micro-duct tube not used for this project will be capped.
c. Wherever possible, the micro-duct will enter and exit a maintenance hole via corresponding entrances (straight through) to keep it parallel and avoid unnecessary twists.
d. The Contractor shall install micro-duct, so any bends or loops are smooth sweeps following the manufacturers bending radius guidelines and any kinks and sharp bends are avoided.
e. The Contractor shall securely attach or mount newly installed micro-duct inside the maintenance hole on existing or new racking as per applicable technical order guidance, with sufficient slack to reach the opposite end of the maintenance hole.
f. The Contractor shall strip back micro-duct outer sheath cleanly, avoiding any nicks or cuts in micro-ducts, use heat shrink or similar protection as per manufacturers recommendation on butt of sheath for protection. Overlap both sheath and micro-ducts evenly (i.e., centered over butt end).
g. Newly installed micro-duct will be free from holes, blisters, cracks or any other imperfections which would affect the performance or serviceability.
2.2.1.11.2 Installation.
Installation of underground conduits/ducts will be IAW RUS Bulletin 1751F-643 and RUS Bulletin 1753F-151. Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. will be installed a minimum of 36" below grade. Ducts installed beneath roads and parking areas will be protected. It is understood that in some locations, especially at paved surface crossings, the Contractor may bore and substitute 4-inch I.D. HDPE conduit (Roll pipe, suitable for the application) for 4-inch PVC conduit. Also, if HDPE is used, it will be SIDR 11.5 so that the inside diameter of the HDPE will match the inside diameter of the PVC. HDPE will not be placed directly into a MH. The Contractor shall transition to PVC from HDPE prior to terminating conduit into these structures. In maintenance holes (MH) with knockouts, conduits will start at the bottom knockout, allowing for upward future expansion.
All ducts not installed across roads, sidewalks, parking areas, or areas to be paved, etc. will have a minimum of 36 inches ground cover, where possible. The Contractor shall provide other protective measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved.
Grading of ducts and drain slope of ducts will be accomplished IAW BICSI Outside Plant Design Reference Manual (OSPDRM) and RUS Bulletin 1751F-643. Do not allow the ducts to twist or tangle between Maintenance holes.
2.2.1.11.3 Paved Surface Crossings.
The Contractor shall cut and restore, and/or horizontal directional drilling (HDD) in order to cross paved surfaces. Paved surfaces may be asphalt, concrete, brick, or some type of paving stone. Paved surfaces include roads, driveways, sidewalks and parking lots. Paved surface crossings will be IAW guidelines set forth by NAS Pensacola Public Works. At a minimum, grade of PVC conduit at open trench paved surface crossings, or crossings which are planned for paving in the future, will be Schedule 40 and will be concrete encased. If horizontal directional drilling (HDD) is used, then it will be in compliance with commonly accepted telecommunications industry standards and practices relative to the installation, stabilization, and protection of conduits through a bore under a paved surface. The decision whether to trench (cut and patch) across or horizontal directionally drill under paved surfaces is at the discretion of the BCE and will be made on a case-by-case basis.
Page | 9
2.2.1.11.4 Bends and Sealing.
All bends between MHs/HHs will be a minimum of ten times (10X) the diameter of the duct size (i.e., 4 inch duct = 40 inches) with the sum of bends in all directions not exceeding a total of 90 degrees where practical. Coordinate with 81 CS/SCX if runs have bent that total more than 90 degrees is required. Ducts will have bell ends and enter a MH/HH perpendicular to the surface of the wall through which it is entering. All ducts/inner ducts entering MH/HH will be sealed. Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a rigid test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit will be pulled through two diagonally opposite ducts to ensure proper alignment. In addition, all ducts will be cleared of loose materials such as concrete, mud, dirt, stones, etc.
2.2.1.11.5 Utility Separation.
When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.
2.2.1.11.6 Spacers and Tracer Wire.
Along the length of the duct run, if the ducts are installed by trenching, spacers will be placed at five
(5) foot intervals. At least one duct or roll pipe will have tracer wire or be otherwise locatable from the surface. All new tracer wire installed for this project needs to have a wire nut and label installed at all wire ends, and those wire ends secured but not connected to grounds. The tracer wire will be exposed;
free from the conduit and capped (insulated). The tracer will be secured and routed to the maintenance hole or hand-hole neck to a point where maintenance personnel may access the wire without having to enter the maintenance hole/hand-hole and tagged with a label so indicating it as a “Duct Tracer Wire to xxx – Do Not Remove (where xxx is the other end of the wire).” Tracer wires will not be connected to any grounding system. Tracer wire will be pulled back from building entrances until it is underground to prevent lightning damage.
2.2.1.11.7 Warning Tape.
Cable warning tape will be buried one (1) foot below the surface and will follow the duct route. The tape will be a minimum of three inches wide and orange in color with the appropriate warning message.
2.2.1.11.8 Entrance Conduits into Existing Maintenance Holes.
When new entrance conduits/ducts or sleeves are required, the Contractor shall bore and install the necessary holes and install the ducts or sleeves, if knockout doesn’t exist. Penetration will not be in such a location through the wall as to block use of existing ducts in the maintenance hole. New ducts will be a minimum of 18 inches from either the floor or ceiling of the maintenance hole if practical. Ducts will have bell ends and enter the maintenance hole perpendicular to the surface of the wall through which it is entering and will be installed flush with the interior wall of the maintenance hole. Ducts and openings around ducts will be sealed to prevent moisture from entering the maintenance holes.
2.2.1.11.9 Conduit Protection.
The Contactor shall install the appropriate physical protection required [(concrete encasement, steel tube (casing)] for buried PVC conduits or HDPE Roll pipe, consistent with commonly accepted telecommunications industry practices relative to the task and to the environment in which they are installed and the loads (H-5, H-10, H-20, railroads, flight line, etc.) to which they are expected to be
Page | 10 exposed. Type of protection may be dependent upon the specific application and will be IAW applicable federal, state or local (Pensacola NAS Civil Engineering construction requirements) procedures. However, at a minimum, nonmetallic conduits will be encased in concrete of minimum 3000 lb. /in2 compressive strength where vehicular traffic is above the pathway. The encasement will be concrete of a wet type mix and will be placed in such a manner as to ensure the concrete completely surrounds all conduits and no air voids are trapped in the mix a bend or sweep is placed in PVC nonmetallic duct bank between maintenance holes, the duct bank must be encased in concrete with a minimum compressive strength of 3000 pounds per square inch (psi).
2.2.1.11.10 Pull Tape. N/A
All newly installed ducts left vacant will be provided with a pull tape with a waterproof, corrosion resistant, pre-lubricated flat woven polyester pull tape with sequential footage markings, (1250 lb.
pulling strength) for future cable installations. The pull tape will extend into the maintenance holes/hand-holes and be secured to a cable rack or pulling iron, etc. Not required when using blown fiber
2.2.1.11.11 Excavation/Building Penetrations
All wall penetrations, including inside buildings, will be restored to meet the required base fire ratings.
2.2.2 Requirement Installation.
This section describes the underground maintenance hole/conduit system, micro-duct and fiber optic cable installation requirements. The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure in accordance with TIA-758-B. Each cable installation will be coordinated with the 81 CS/SCXP so that the impact on the building users is properly coordinated.
The sequence of installation is at the Contractor’s discretion.
2.2.2.1 Infrastructure Installation.
The Contractor shall install the following new infrastructure. All new locations and distances are approximations.
2.2.2.1.1 New NEMA 4X Enclosure.
The Contractor shall install two NEMA 4X enclosures. One on the exterior wall of B1852 and one on the exterior wall of B4148. The Contractor shall determine the size of the enclosure needed to satisfy the requirement at that location based on the quantity of Micro-duct coming into the enclosure. The entry enclosure and riser conduits will be painted to match the color of the building exterior in the area where it is mounted. The locations of NEMA 4X Enclosures will be provided by 81 CS/SCXP.
2.2.2.1.2 New J-Boxes
The Contractor shall install two J-Boxes at the B603. Reference Project Drawing. Coordinate with 81 CS/SCXP for detail.
2.2.2.1.3 New Backboard.
The Contractor shall install the new backboard (BB) in B603, Room 1017A. The location of new backboard will be provided by 81 CS/SCXP.
Newly installed BB will be AF-standard in accordance with TIA-569-C. The BB must be 0.75”-thick fire-retardant wood/plywood, with two coats of white, fire-resistant paint and the manufactures fire rated stamp must remain visible.
Page | 11
2.2.2.1.4 New Fiber Optic Distribution Panel (FODP).
The Contractor shall install the FODPs at the locations below. The locations of FODPs will be provided by 81 CS/SCXP.
• B603, Room 1017A: Two each 48-port FODP (Wall mounted)
• B603, Room 3024: Two each 48-port FODP (in existing Rack)
• B1852: One 48-port FODP (in existing Rack)
• B4148: One 48-port FODP (in existing rack)
2.2.2.1.5 New Hand holes.
The Contractor shall install ten (10) 4’W x 4’L x 4’H (interior dimensions) hand holes (to be designated as HH-1, HH-2, HH-3, HH-4, HH-5, HH-6, HH-7, HH-8, HH-9 & HH-10. The approximate locations are shown on the Project Drawing. Coordinate with Base 81 CS/SCXP for final hand holes placement and numbering scheme.
2.2.2.1.6 New 1x4 Way Micro-duct (18mm/14mm)
The Contractor shall install 1x4 way Micro-duct as shown in the Table below. The new micro-duct will be comparable with Dura Line Future path 18mm OD/14mm ID system and be suitable for direct buried applications.
Install 1x4-way Micro-Duct (18mm OD/14mm ID)
From To Approx.
Distance
(Feet)
Quantity Notes
B603, Room 1017A
New J-Box #1 12 1x4-way In new 4” EMT
New J-Box #1 New J-Box #2 120 1x4-way In new 4” EMT
New J-Box #2 Existing J-Box 155 1x4-way In new 4” EMT
Existing J-Box HH-A 25 1x4-way In existing 4” EMT
HH-A HH-B
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
HH-B New HH-1 2,000 1x4-way Trenching
New HH-1 New HH-2 2,000
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
New HH-2 New HH-3 2,000
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
New HH-3 New HH-4 2,000
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
Page | 12
New HH-4 New HH-5 2,000
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
New HH-5 New HH-6 2,000
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
New HH-6 New HH-7 2,000
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
New HH-7 New HH-8 2,285
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
New HH-8 New HH-9 1,600
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
New HH-9 B1852, NEMA Box 1,000
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
New HH-9 New HH-10
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
New HH-10 B4148, NEMA Box 525
1x4-way Trenching. Paved surfaces will be bored. Install a 4” conduit as required.
2.2.2.1.7 Electric Metal Tube Conduit Infrastructure.
The Contractor shall install approximately 290 feet of electric metal tube (EMT) conduit from existing J-box to B603, Room 1017A. Coordinate with 81 CS/SCXP for the detail.
2.2.2.1.8 Fiber Optic Cable Installation.
The Contractor shall install single mode (SM), loose buffer tube, water blocked, outside plant (OSP) fiber optic cable (FOC) suitable for underground applications. The intent is to install the cable in one continuous length, to the extent that it is practical. The cable will meet RUS 7 CFR 1755.900 criteria;
will comply with industry standards with regard to manufacturers’ cable marking, jacket, rip cords, water blocking, fiber color coding, jacketing materials, etc. In addition, the FOC will comply with industry standards with regard to mode field diameter, core cladding concentricity, attenuation, and dispersion characteristics at 1310 nm and 1550nm.
All fiber optic cables will be installed in new Micro-duct/corrugate innerduct.
2.2.2.1.8.1 From B603, Room 1017A to B1852.
The Contractor shall install approximately 19,500 feet of 48-strand SM FOC from B603, Room 1017A to B1852. Terminate 48-strand SM FOC in the new 48-port FODP using fusion splice pigtails with SC connectors in B603 and in B1852.
Page | 13
Install 48-Strand SM FOC from B603 to B1852
FROM TO
Approx.
Distance
(Feet)
Sheet # Note
B603, Room 1017A New J-Box #1 12 6 In new 1x4 way Micro-duct
New J-Box #1 New J-Box #2 120 6 In new 1x4 way Micro-duct
New J-Box #2 Existing J-Box 110 6 In new 1x4 way Micro-duct
Existing J-Box HH-A 25 6 In new 1x4 way Micro-duct
HH-A HH-B 85 2 In new 1x4 way Micro-duct
HH-B New HH-1 2,000 2 In new 1x4 way Micro-duct
New HH-1 New HH-2 2,000 2 In new 1x4 way Micro-duct
New HH-2 New HH-3 2,000 2, 3 In new 1x4 way Micro-duct
New HH-3 New HH-4 2,000 3 In new 1x4 way Micro-duct
New HH-4 New HH-5 2,000 3, 4 In new 1x4 way Micro-duct
New HH-5 New HH-6 2,000 4 In new 1x4 way Micro-duct
New HH-6 New HH-7 2,000 4, 5 In new 1x4 way Micro-duct
New HH-7 New HH-8 2,285 5 In new 1x4 way Micro-duct
New HH-8 New HH-9 1,600 5 In new 1x4 way Micro-duct
New HH-9 B1852, Room 111E 1,050 5 In new 1x4 way Micro-duct
2.2.2.1.8.2 From B603 to B4148.
The Contractor shall install approximately 19,550 feet of 48-strand SM FOC from B603, Room 1017A to B4148. Terminate 48-strand SM FOC in the new 48-port FODP using fusion splice pigtails with SC connectors in B603 and in B4148.
Install 48-Strand SM FOC from B603 to B4148
FROM TO
Approx.
Distance
(Feet)
Sheet # Note
B603, Room 1017A New J-Box #1 12 6 In new 1x4 way Micro-duct
New J-Box #1 New J-Box #2 120 6 In new 1x4 way Micro-duct
New J-Box #2 Existing J-Box 110 6 In new 1x4 way Micro-duct
Page | 14
Existing J-Box HH-A 25 6 In new 1x4 way Micro-duct
HH-A HH-B 85 2 In new 1x4 way Micro-duct
HH-B New HH-1 2,000 2 In new 1x4 way Micro-duct
New HH-1 New HH-2 2,000 2 In new 1x4 way Micro-duct
New HH-2 New HH-3 2,000 2, 3 In new 1x4 way Micro-duct
New HH-3 New HH-4 2,000 3 In new 1x4 way Micro-duct
New HH-4 New HH-5 2,000 3, 4 In new 1x4 way Micro-duct
New HH-5 New HH-6 2,000 4 In new 1x4 way Micro-duct
New HH-6 New HH-7 2,000 4, 5 In new 1x4 way Micro-duct
New HH-7 New HH-8 2,285 5 In new 1x4 way Micro-duct
New HH-8 New HH-9 1,600 5 In new 1x4 way Micro-duct
New HH-9 New HH-10 575 5 In new 1x4 way Micro-duct
New HH-10 B4148, Room 147 525 5 In new 1x4 way Micro-duct
2.2.2.1.8.4 Between Room 3024 and Room 1017A in B603. (Drawing Sheet 8)
• The Contractor shall install approximately 50 feet of two 48-strand SM plenum rated tie cables between Room 1017A and Room 3024 in B603
• The Contractor shall terminate one 48-strand SM plenum rated FOC in the new 48-port FODP (B603 – B1852) using fusion splice pigtails with SC connectors in Room 1017A and using fusion splice pigtails with LC connectors in Room 3024
• The Contractor shall terminate one 48-strand SM plenum rated FOC in the new 48-port FODP (B603 – B4148) using fusion splice pigtails with SC connectors in Room 1017A and using fusion splice pigtails with LC connectors in Room 3024
2.2.3 Project Residue.
All residue from this project will be disposed of off base and in accordance with Federal, State, local and base environmental laws and regulations. All residue produced by horizontal directional boring operations (i.e., slurry) will be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor’s expense, IAW federal and state environmental laws and regulations. Under no circumstances will the contractor stage or store boring residue in slurry ponds or other containment areas on Pensacola NAS, FL.
2.2.4 Site Restoration.
The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. The Contractor shall comply with all base grounds restoration requirements. Common use areas will be restored with sod.
2.2.5 Service Outages.
The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 10
Page | 15 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).
2.2.6 National Pollution Discharge Elimination System (NPDES).
If required by Base Civil Engineer (BCE), the Contractor shall obtain approvals for NPDES at State and/or Federal level [in some locations this may be called the Storm Water Pollution Prevention Plan (SWPPP)]. The storm water/environmental plan is the sole responsibility of the Contractor. Base Civil Engineering/CEV will review and advise to ensure minimum standards and storm water controls/BMPs are in place to ensure compliance; this is a compulsory item in the SOO and contract.
The Contractor shall implement storm water controls/BMPs to ensure sediment, as a result of storm water runoff, does not enter storm drainage channels and/or inlets.
The Contractor shall conduct an initial meeting within 10 days of the Contractor site survey with the base environmental office to identify NPDES preparations and/or the storm water/environmental plan.
The Contractor shall review the NPDES requirements applicable to the base; develop a plan to comply with the NPDES; obtain approval of the NPDES plan from all appropriate Government agencies; and comply with any other applicable state requirements for construction.
2.2.7 Identification/Marking.
The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign (minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name and both the Contractor and Site POC's names and local telephone numbers.
2.2.8 Installation Schedules.
The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system. All submissions will be delivered electronically in MS Office-compatible format NLT 10 business days after contract award and as significant schedule changes occur to be determined by the Contracting Officer.
2.2.9 Weekly Status Reports.
The Contractor shall prepare a Weekly Status Report and distribute to the Government Contracting Officer (CO), the System Engineer(s), the Government Project Manager, and other base personnel as required. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.
2.2.10 Drawings.
2.2.10.1 As-Built Drawings.
The 81 CS/SCXP will supply existing system drawings, and the Contractor shall provide updated drawings in Visio for building and rack elevation; Visio and pdf for OSP. These drawings will depict the entire pathway and details of the installation, including but not limited to: labeling, cables, innerducts and maintenance holes/handholes, conduits, maintenance loops, distances, bores, trenches, building entrances. Detailed butterfly drawings will also be required. If the existing cable diagram or butterfly drawings are not available; the Contractor shall create the missing cable diagram/ butterfly
Page | 16 drawings to include all the components used in this project. The Contractor shall record/deliver geospatial data of new outside plant distribution system.
2.2.10.2 Butterfly Drawings.
The Contractor shall record and submit butterfly, cable path and building penetration drawing information for all new installations including butterfly drawings for all maintenance holes and pull boxes that contain new or reused FOC. Drawings will record the path and arrangement of new and reused fiber optic cables, splices, and the arrangement duct banks, ducts, inner-duct and will show maintenance hole orientation with respect to geodetic north. Drawings will be submitted in an easily read electronic format such as pdf. Scanned data sheets or legible Drawings are acceptable.
2.2.10.3 Geospatial Deliverables.
The Contractor shall collect and record geospatial data and provide as-built documentation (shape files) of all new installed maintenance hole/duct system components and new cable components (including metadata) compatible with the Cyberspace Infrastructure Planning System (CIPS) Visualization Component (CVC) drawing system. Data points will be recorded at the center of each manhole/hand-hole lid and at intervals not to exceed 25 feet along cable routes. Sufficient data points will be recorded to capture any change in direction along the route. All GPS coordinates will have +/- 3 feet accuracy for all readings. The Government will review the shape files and transcribe the information to the CVC system. Provide geospatial data via CD as Environmental Systems Research Institute (ESRI) Shape files. Shape files will be delivered within 30 days of project completion.
2.2.11 Test and Acceptance/Installation Test Plan.
The Contractor shall provide a test plan as to how the system will be pre-tested, in-progress-tested and post-tested. Draft Cut-over Test Plan will be submitted NLT 10 calendar days after contract award.
Government comments will be provided after review of the draft. A final plan will be submitted 30 calendar days before the actual cut-over date. The Contractor shall test the system to demonstrate to the Government quality assurance representative that the system is fully operational and meets or exceeds the specified requirements and that the system is fully ready to be placed into service. These tests will be accomplished prior to the system being placed into service.
2.2.11.1 Testing.
The Contractor shall conduct on-site testing IAW OEM’s installation manuals, practices and the appropriate vendor’s test procedures. The Contractor shall furnish all test equipment and personnel required to conduct all required testing. During any testing phase, the Government reserves the right to perform any of the Contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing.
The Contractor shall participate with the Government in testing the complete communications system.
When any system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance and payment will be withheld until such time as the cause of the failure is corrected to the Government’s satisfaction. After appropriate corrective action has been taken, all tests including those previously completed, related to the failed test and the corrective action will be repeated and successfully completed prior to Government acceptance.
2.2.11.1.1 Fiber Optic Tests.
All strands of all fiber optic cables will be tested in accordance with TIA 526-7, Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant, or equivalent. As a minimum, the following tests will be performed. Both Optical Time Domain Reflectometer (OTDR) and Optical
Page | 17
Power Meter tests will be used for all end-to-end circuits. Between FODPs, bi-directional testing at 1310 nm and 1550 nm is required. For incomplete circuits that end in Maintenance Holes, only one way OTDR testing is required.
2.2.11.1.2 Optical Attenuation.
End to end attenuation tests will be conducted on all fiber optic cable strands. Tests will be accomplished to ensure the installed cable is within the specified parameters.
2.2.11.1.3 Distance.
Test to determine the installed cable length between optical patch panels. All strands of all fiber optic cables will be tested.
2.2.11.2 Acceptance/Installation Test Report.
The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan NLT 10 business days after Government Witness Testing is complete.
2.2.12 Final Acceptance IAW AFTO “747 Cyberspace Infrastructure System Acceptance”.
The Contractor shall schedule a final project walk-through with the Base POC, including Quality Assurance Officer and Subject Matter Expert and the Contracting Officer. The walk-through should be scheduled 5 calendar days prior to acceptance. The Contracting Officer shall route the AFTO 747 after the base has signed the test report and the walk-through has been completed.
2.2.13 Deliverable Summary.
All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this contract. All deliverables will be produced using recommended software tools/versions as accepted by the Government.
3.0 GENERAL INFORMATION.
3.1 Period of Performance.
The period of performance will be 180 calendar days beginning 10 days after the notice to proceed.
3.2 Place of Performance.
The place of performance is Pensacola NAS FL.
3.3 Hours of Operation.
The Contractor shall routinely work during normal duty hours of the site. However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours will be coordinated with the 81 CS/SCXP and approved by the Contracting Officer at least 10 calendar days in advance.
3.4 Holidays/Down Days.
The Contractor shall not perform under this contract on federal holidays or site-unique down-days unless expressly authorized by the CO and coordinated with the base POC.
New Year's Day Labor Day Martin Luther King, Jr.'s Birthday Columbus Day Washington's Birthday Veteran's Day Memorial Day Thanksgiving Day Juneteenth Christmas Day
Page | 18
Independence Day
3.5 Base Support.
4.0 On-base laydown and storage areas are available, but the Contractor shall identify the square footage for approval. The Contractor shall coordinate with for 81CS or 479FTG storage space and staging area requirements. Govt./AF equipment should not be expected nor will be provided for the completion of this effort.
APPENDICES.
4.1 Appendix A: APPLICABLE STANDARDS.
The following list is not all-exclusive. The Contractor shall comply with applicable commercial code and standards AFMAN 91-203 – Air Force Consolidated Occupational Safety Instruction OSHA CFR 29 Part 1910-268 – Telecommunications NEMA TC 2- Electrical Polyvinyl Chloride (PVC) Tubing and Conduit TIA-606-D Administration Standard for Telecommunications Infrastructure TIA-568-E Commercial Building Telecommunications (568C.1, 568C.2, 568C.3) Cabling Standard TIA-607-D Commercial Building Grounding (Earthing) and Bonding Requirements for Telecommunications TIA-526-7- Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant TIA-569-E - Commercial Building Standard for Telecommunications Pathways and Spaces TIA-570-D –Residential Telecommunications Infrastructure Standard TIA-758B Customer-owned Outside Plant Telecommunication Infrastructure Standard BICSI TDM Manual - Building Industries Consulting Services International Telecommunications Distribution Methods (TDM) Manual BICSI – Outside Plan Design Reference Manual RUS Bulletin 345-65 (PE-33) – Specification for Shield Bonding Connectors RUS Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable RUS Bulletin 1751F-643 - Underground Plant Design RUS Bulletin 1751F-644 - Underground Plant Construction Telecommunications Engineering Shield Continuity and Construction Manual (TE&CM) 451.2 RUS Bulletin 1751F-801 – Electrical Protection Fundamentals RUS Bulletin 1753F-151 (515b) - Specifications and Drawing for Underground Cable Installation RUS Bulletin 1753F-201 (PC-4) – RUS Standard for Acceptance Tests and Measurements of Telecommunications Plant RUS Bulletin 1753F-207 (PE-87) – REA Specification for Terminating Cables NFPA 70 - National Electric Code Unified Facilities Criteria 3-260-01
Page | 19
Unified Facilities Criteria 3-580 FGDC-STD-007.3-1998 - Geospatial Positioning Accuracy Standards Part 3: National Standard for Spatial Data Accuracy
5.0 Project Drawing
SHEETS 1 THRU 5
HAVE BEEN REMOVED BECAUSE OF
OPERATIONAL SECURITY
CONCERNS
Page | 20
Page | 21
Page | 22
| 1. SCOPE. |
| 2.0 REQUIREMENTS. |
| 2.1 GENERAL REQUIREMENTS. |
| 2.1.1 Safety Requirements. |
| 2.1.2 Site Coordination. |
| 2.1.2.1 Confined Space. |
| 2.1.2.2 Accident/Incident Reporting and Investigation. |
| 2.1.2.3 Work Area(s). |
| 2.1.2.4 Traffic Control. |
| 2.1.2.5 Airfield Driving. |
| 2.1.3 Security Requirements. |
| 2.1.3.1 Security Clearances. |