Attachment 1. SOW Repair FACP and MNS.pdf

PDF 208 KB Posted

Attached to
Design-Build Repair Fire Alarm and Mass Notification
Solicitation number
FA663325R0001
Issued by

About this file

This Statement of Work (SOW) details a design-build project to repair fire alarm and mass notification systems at two aircraft maintenance hangars (B821 and B870) located at the Minneapolis Air Reserve Station in Minnesota. The project requires professional design services across three phases: Title I Type A (field investigations), Title I Type B (design document preparation), and Title II (construction phase services), with a total performance period of 472 days (189 days for design, 283 days for construction).

Key technical requirements include replacing existing obsolete fire alarm control panels (FACP) with Monaco MAAP-X systems, adding mass notification systems, addressing specific deficiencies like overfilled conduits and disabled foam systems, and evaluating/modifying fire protection components. The project involves detailed design submissions at 50% and 95% completion stages, with government reviews and conferences, followed by a construction phase encompassing pre-construction submittals, mobilization, construction activities, inspections, and closeout. The contract is a 100% small business set-aside with a firm-fixed-price structure, targeting facilities with Class I Div 2 hazardous areas.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLASSIFICATION: UNCLASSIFIED

Repair FACP and MNS, B821 & B870 Page 1 of 10

STATEMENT OF WORK - QJKL 24-0014, 01 July 2025

PART 1 - GENERAL

1.01 PROJECT SCOPE

Contractor shall obtain professional design services (Title I Type A, Title I Type B and Title II Services), provide all supervision, labor, materials and equipment necessary to fully meet all requirements of this Statement of Work, Front-end Specifications, SOW Drawings and all other Contract Documents related to and/or titled: “REPAIR FACP & MNS B821 & B870” at the Minneapolis Air Reserve Station, Minneapolis Minnesota. Both facilities are aircraft maintenance hangars. Electronic PDF and AutoCAD drawings are available. The Construction Manager/ General Contractor is responsible for providing Guaranteed Maximum Price (GMP) for the project. The GMP shall be developed in conjunction with the Designer of Record (DOR) and reflect the scope of work indicated on the drawings and specifications developed per Paragraph 1.03. Title II services shall be provided by the DOR.

1.02 PROFESSIONAL DESIGN SERVICES

A. Title I (Type “A” Services). These services involve field investigations and surveys; similar fact-finding surveys of the site essential to proper design; preparation of reports and similar services not involved in the preparation of designs, plans, drawings, and specifications.

B. Title I (Type “B” Services). These services include those items normally furnished by an DOR in the actual preparation of the design documents (plans, drawings, specifications, submittal register etc.) and include visual inspection of the site or facility for familiarization with scope, general conditions, and coordination with using activities.

C. Title II (Type “C” Services). Those items involving inspecting, monitoring, and evaluating construction activities to validate conformance to plans and specifications, including reviewing, evaluating and testing product submittals and shop drawing, and preparation of construction contract modifications.

D. Applicable Standards, Manuals, and Pamphlets: The DOR shall prepare all design documents in conformance with the applicable portions of the following:

1. Unified Facilities Criteria (UFC)

2. Applicable Air Force Policy Directives, Instructions, Pamphlets, Manuals, Technical Data

Bulletins, Engineering Technical Letters and other documents.

3. Current national codes, regulations, and specifications involving architectural, civil, electrical, environmental, and mechanical disciplines associated with the design and construction of each project as referenced by UFC.

4. Guide Specification: The DOR shall use Unified Facilities Guide Specifications (UFGS) as the basis for producing specifications under this contract. The specifications shall be tailored to suit the specific work requirements of the individual items contained in the Delivery Order. Extraneous material that does not apply to the project shall be deleted. While the DOR should cover relevant items in full scope to assure quality construction and compliance, the use of notes on the drawings either to accentuate important items in the specifications, or to take the place of lengthy written specifications for routine or simple items is encouraged. The DOR is permitted to use specific manufacturer’s part or model numbers to describe a specified item, however, in all such cases, at least two other approved manufacturer’s part or model numbers shall be specified or an “or equal” statement shall be included unless the government wishes to

Repair FACP and MNS, B821 & B870 Page 2 of 10 sole source an item. If sole source is required, the Government will provide the appropriate justification for that specific sole source.

E. CERTIFICATION OF DRAWINGS AND OTHER DOCUMENTS: The DOR, or their authorized representative, shall sign the original of all drawings and the first page of all specifications, estimates or similar documents under the DOR’s printed name and over the affixed replica of his professional seal (or his registration certificate number and including the state of issuance).

The DOR certifiers of the documents shall be registered in the state of Minnesota. In addition, as part of the 100% submittal, an engineer must certify in writing that the plans and specifications are compliant with UFC 3-600-01 (Fire Protection Engineering for Facilities) and all applicable criteria.

F. RESPONSIBILITY OF THE ARCHITECT ENGINEER: Notwithstanding any review, acceptance or approval by the Government, the A-E shall be responsible for the professional and technical quality of all designs, drawings, specifications, and other material produced under this contract. The DOR shall also be responsible for the professional quality and adequacy of the service and materials furnished and for compliance with design criteria specified by the Government for use under this contract.

1. Reassignment of DOR design responsibilities to construction contractors is highly discouraged by the Government. This includes but not limited to the following: structural steel detailing, fire sprinkler design, stair systems, retaining wall systems, and structural framing systems. This practice in no way relieves the DOR of their responsibility for these items. The A-E will be asked to approve and shall certify all “delegated” designs for conformance to the project design analysis.

G. DESIGN INFORMATION: In general, the requirements presented are design objectives and the DOR is encouraged to suggest changes where they would not seriously deviate from the overall requirements and would result in substantial economic savings, time savings or improved performance in arriving at the end results. Design of structure and appurtenant facilities will comply, where applicable, with such regulations and criteria that exist for the Air Force and objectives of the project as furnished by the Contracting Officer.

H. GOVERNMENT FURNISHED INFORMATION: The Government, through the office of the Contracting Officer, will furnish within five days after issuance of a contract, applicable data and information (as available) for the execution of the work described. Data shall be returned to the Contracting Officer upon completion of the individual project. This data is on file in the Base Civil Engineering (BCE) and may be obtained for review by the DOR during negotiations.

All data from the Government shall be treated with care and is classified as “CONTROLLED UNCLASSIFIED INFORMATION”, unless otherwise noted. All data cannot be distributed, retransmitted or reproduced without written permission from the Government. The data will include where applicable and available:

1. Base Standards: AFRC - Minn-St Paul ARS IFS | WBDG - Whole Building Design Guide

2. Division 01 Specification Sections

3. General Site Plan

4. Existing Record Drawings

5. Design Criteria

6. Sole-source Justification https://www.wbdg.org/airforce/ifs/minn-st-paul-ars-ifs

Repair FACP and MNS, B821 & B870 Page 3 of 10

I. DRAWINGS AND SPECIFICATIONS

1. General: Final drawings shall be submitted on hard copy and in electronic format. Hard copy drawings shall be half size (11” x 17”) paper copy (unless otherwise approved by the Contracting Officer). Electronic drawings shall be provided electronically via DoDSafe (www.safe.apps.mil). Both electronic PDF and AutoCAD copies of the Construction Drawings shall be provided.

a. Cover Sheet/Location Plan: The DOR shall prepare a cover sheet with a location plan on the first sheet of the project drawings. This Location Plan will be the base map or a portion thereof which covers the general project location and base location relative to metro area. The cover sheet containing the latest signature format shall be used. The Project Location shall include, but not be limited to, Base Contracting, Base Civil Engineer, and other facilities related to project management or as directed.

b. Code Data Sheet: The DOR shall prepare a separate sheet showing all code calculations, life safety requirements, and design conditions/assumptions.

c. Preliminary Plans: Preliminary Plans shall be prepared at working drawings scale and will present sufficient details to permit an adequate review. The DOR may use the tracing of the preliminary drawings for working drawings with the addition of necessary details.

d. Demolition and new work shall be clearly noted and shown on the drawings. Gross floor areas shall be shown for the building.

e. Drawings shall contain sufficient detail to clearly indicate type and sizes of materials, utilities, etc., and specifically to list separately all contractor-furnished equipment and all Government-furnished equipment to be installed by the contractor.

f. Final Drawings: The DOR shall not proceed with the final drawings until receipt of written review comments or approval or Phase I and II requirements from the Contracting Officer. These drawings shall be submitted for review by the Contracting Officer and for necessary revision, corrections, or additions before final approval and application of the required signatures of Government personnel.

g. Specifications: The project specifications shall be prepared as a separate document.

The specifications shall be prepared in accordance with Paragraph 1.02.D.4 Guide Specifications of this Statement of Work. The DOR shall edit the specifications so that the language is compatible with the Government contracting environment. In all cases where the responsible government official is referenced (inspector, engineer, architect, etc.), the specifications shall refer to the Contracting Officer. The DOR shall be responsible for judging whether testing is required for a particular work item.

Do not require tests which are not economically appropriate for the size of the job.

The specifications shall be written so indicating that the prime contractor is the only contractor with whom the government has a legal contract. Subdivision of work is the prime contractor’s responsibility.

Repair FACP and MNS, B821 & B870 Page 4 of 10

1.03 INVESTIGATION/ DESIGN PHASES (Title I Services).

A. Phase 1: During Phase 1, the DOR shall conduct a survey investigation and study based on broad guidance furnished herein, and as may be supplemented by other Government-furnished material, will determine the recommended scope, materials, quantities, etc., and proceed to Phase 2. Conferences or site visits will be conducted (if required).

1. Survey of existing facilities, B821 & B870

2. Evaluate conversion of B821 dry system to wet system

3. Evaluate existing fire pumps conversion to city water pressure

4. Concept plans

B. Phase 2: Develops the drawings and specifications to an interim design level.

1. Notice to Proceed with Design

2. 50% Drawings (half size and electronic)

3. 50% Specifications

4. 50% Guaranteed Maximum Price (GMP)

5. 50% Design Analysis

6. 50% Design Review Conference at Government Offices

7. Notice to Proceed with Design

C. Phase 3: Completes the design and shall include all comments from Phase 2.

1. Final Drawings (95%) (half size and electronic)

2. Final Specifications (95%)

3. Final Guaranteed Maximum Price (95%)

4. Final Design Analysis (95%)

5. Conference at the Contracting Office (unless specifically omitted)

6. Construction Documents (100%) as listed below shall be delivered to the office of the

Contracting Officer incorporating all review comments from the 95% review.

a. Construction Drawings (half size and electronic)

b. Construction Specifications

c. Guaranteed Maximum Price

d. Construction Final Design Analysis

Repair FACP and MNS, B821 & B870 Page 5 of 10

1.04 CONSTRUCTION PHASE SERVICES

A. Title II (Type “C” Services). The Designer of Record (DOR) shall conduct reviews of product data, material samples, design data, certificates, & closeout submittals. Submittals shall be marked; Approved, Approved as Noted, Resubmit, or Rejected. Reviews shall ensure submittals comply with Construction Document requirements. DOR may be required to conduct site visits for quality assurance, testing and/ or coordination, and Owner’s meetings.

PART 2 - ADMINISTRATIVE

2.01 MEETINGS, CONFERENCES AND SITE VISITS

A. Post Award Meeting/Teleconference, Progress Meetings & Design Integration Meetings: After the issuance of a contract, the Contractor shall attend meetings at project site. The purpose of these meetings includes, but is not limited to contract discussions, progress reviews, project scoping, planning, design reviews, project status, and the general exchange of information concerning current and future activities. All meetings shall be held at 934th CEC. The Contractor shall coordinate each meeting with the Contracting Officer. Contractor shall schedule Design Phase review meetings within 5 days of receipt of government comments.

B. Meeting Minutes: The Contractor shall record and provide copies of all meeting minutes not later than 2 business days after the meeting. Minutes shall be sent by email to the Contracting Officer. Meeting minutes shall track all action items assigned and shall document all items discussed at meetings as well as a meeting’s attendees.

C. Base Access: The Contractor shall coordinate with the Contracting Officer to gain access to areas of the installation involving this project. The Contractor shall follow all base rules and regulations regarding entry and access to the base. Contractor shall have in possession all applicable identification documents prior to arrival.

D. Government Property: Contractor shall protect all Government property against damage, to include but not limited to dust, fumes, impact, scratching, water, paint, joint compound, power failure, power surges, weather, heavy equipment, et cetera. All damages caused by the Contractor, whether to equipment, furniture, roads, landscaping, building components or any other type of Government property encountered at or near the project site shall be repaired or replaced to match existing and to the satisfaction of the Contracting Officer at no cost to the Government.

PART 3 - PROJECT DESCRIPTION AND REQUIREMENTS

3.01 DESCRIPTION OF WORK

A. Conduct site investigation of B821 Aircraft Maintenance Hangar. The known issues/ repairs are as follows:

1. Existing FACP is Monaco MAAP+ with Wheelock mass notification system. System is

Class B wiring method.

2. Salvage and turnover to Government all Monaco equipment not expected to be used in the new system.

3. FACP/ MNS conduit that extends over the hangar bay from B821E to B821W is overfilled and need to be replaced.

4. High expansion foam system has been disabled. Foam system yellow pull-stations were converted to red pull-stations and initiate water flow through the foam generators.

Evaluate locations; modify to standard red pull-station activation or demolish.

Repair FACP and MNS, B821 & B870 Page 6 of 10

5. Wheelock notification devises will not work with Monaco MAAP-X and need to be replaced. Evaluate if wiring can be reused or demolished.

6. Hangar bay is Class I Div 2 18-inches AFF and 18-inches below roof.

7. The wet pipe system that supplies the fire suppression system in B821W needs a flow switch added where it Tee’s from the main in B821E Room 160 ceiling.

B. Conduct site investigation of B870 Fuel Cell Hangar. The know repairs are as follows:

1. Existing FACP is an obsolete Notifier panel. System is Class B wiring method.

2. The Hangar Bay and the corrosion control area are both Class I Div 2 spaces.

3. Evaluate requirements for smoke detectors in office areas.

C. Develop Construction Drawings and Technical Specifications that will replace the fire alarm systems, mass notification system to B821 and add mass notification to B870 with a Monaco MAAP-X systems. Make repairs to known deficiencies based on results of site investigation that discovered unknown needed repairs. If the GMP exceeds the budget, Contractor and Government shall develop a priority list to bring GMP in alignment with the Budget.

D. Execute repair project using Construction Drawings, Front-end and Technical Specifications.

3.02 PROJECT AREA LIMITATIONS

A. All work shall be performed in the immediate project area. Refer to the drawings.

1. Work in B821 Hangar Bay access may be restricted due to maintenance activities. When restricted, a portion of the Hangar Bay will not be available. Work in portions of the bay will need to be coordinated with the aircraft maintenance schedule. When the space becomes available, work can shift to Hangar Bay.

2. Work in B870: Hangar Bay access may be restricted due to maintenance activities. When restricted, workers are not allowed entry. Work in this space will need to be coordinated with the aircraft maintenance schedule. When the space becomes available, work can shift to Hangar Bay.

A. Project Laydown Area:

3. B821: Controlled Area near B821E

4. B870: Restricted Area west of B870

3.03 EXISTING WORK

A. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

B. Repair or replace portions of existing work, which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

C. Contractor shall protect all Government property against damage, to include but not limited to dust, fumes, impact, scratching, water, paint, joint compound, power failure, power surges, weather, heavy equipment, et cetera. All damage caused by the Contractor, whether to equipment, furniture, roads, landscaping, building components or any other type of Government property encountered at or near the project site, shall be repaired or replaced to match existing and to the satisfaction of the Contracting Officer at no cost to the Government.

Repair FACP and MNS, B821 & B870 Page 7 of 10

3.04 CONTRACTOR ACCESS AND USE OF PREMISES

A. Activity Regulations: Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations.

Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

B. Subcontractors and Personnel Contact: Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

C. No Smoking Policy: Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

D. Working Hours: Regular working hours will consist of an 8-1/2 hour period established by the Contracting Office, between 0700 and 1530 Monday through Friday, excluding Government Holidays and Unit Training Assemblies.

1. No work will be performed during weekend Unit Training Assembly (UTA). UTA’s are typically held once a month, except July. One or two UTAS may be extended Thursday to Sunday. An official schedule of UTA’s will be provided upon award.

E. Work Outside of Regular Hours: Work outside regular working hours requires Contracting Officer approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government to inspect the work in progress, giving the specific dates, hours, location, and type of work to be performed. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in accordance with requirements of EM 385-1-.1 (if applicable).

3.05 DOCUMENTS

A. The Contractor shall:

1. Check any Government furnished construction drawings immediately upon receipt.

2. Compare any Government furnished construction drawings and verify the figures before laying out the work.

3. Promptly notify the Contracting Officer of any discrepancies.

4. Be responsible for any errors which might have been avoided by complying with this

Paragraph 1.03.

B. Large scale drawings shall, in general, govern over small scale drawings. Figures marked on drawings shall, in general, be followed in preference to scale measurements.

C. Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work, but shall be performed as if fully and correctly set forth and described in the drawings and specifications.

Repair FACP and MNS, B821 & B870 Page 8 of 10

D. The Contractor shall maintain a complete set of construction drawings, construction specifications, project related sketches, pictures, approved Contract modifications (if any) and all approved submittals on the job site at all times. One set of such construction drawings shall be designated the "Record Drawings" upon which as-built data shall be neatly recorded and dated in red ink by the Contractor. Contemporaneous annotation of accurate As-Built data on the Record Drawings is to be verified by the Contracting Officer and the Contracting Officer’s Representative, as a prerequisite to the Contractor receiving progress payments. Upon completion of construction, the Contractor shall submit a copy of record drawings and update Contractor furnished AutoCAD drawing files (*.dwg) with As-Built information and digitally stamp these all these drawings as “As-Built”. The digital stamp shall include the wording “As Built,” the name of the construction Contractor and the month and year of construction completion. These drawing files shall be turned over to the Contracting Officer via DOD-safe prior to final payment. The file drop-off shall include one complete set of AutoCAD drawings and a complete set in Adobe Acrobat format.

E. Where conflicts between the drawings and specifications occur, specifications shall govern in accordance with FAR 52.236-21.

PART 4 - PERFORMANCE

4.01 Performance Period

A. The performance period for this statement of work is 472 days for the contract. The performance period for design phase is 189 days and the construction phase is 283 days.

(See Period of Performance listing below for details.) The Contractor shall begin construction work as described in the scope of work within 10 days of Construction Notice to Proceed (CNTP). All meetings and progress reports are due in a timely fashion and will begin no later than 14 days after receipt of CNTP. All work, including any punch list items, must be completed no later than 222 days after receipt of CNTP. No construction work shall begin prior to government approval of plans and specifications.

Design Phase (Total Calendar Days) 189 Kick-off Meeting (within 10 days after NTP) 10 Survey of Existing Facilities, B821 & B870 4 Study Requirements/ Concept Plan 28 Concept Plan Submittal 1 Concept Plan Government Review 7 Concept Plan Review Conference 1 Notice to Proceed 7 50% Design Phase 28 50% Design Submittal 1 50% Design Government Review 14 50% Design Review Conference 1 Notice to Proceed 7 95% Design Phase 28

Repair FACP and MNS, B821 & B870 Page 9 of 10

95% Design Submittal 1 95% Design Government Review 14 95% Design Review Conference 1 Notice to Proceed 7 Construction Documents Phase 14 Construction Documents Submittal 1 Construction Documents Government Review 14

Construction Phase (Total Calendar Days) 283 Notice to Proceed 7 Pre-construction Submittals 30 Mobilization 7 Construction Activities/ Red Zone 150 Final Inspections and Corrections 28 Beneficial Occupancy Date 1 Closeout Phase 60

PART 5 - ENVIRONMENTAL

5.01 Environmental Requirements

A. Contractor shall adhere to environmental requirements in the following specification sections:

1. 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

2. 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

B. The contractor shall provide Construction & Debris Report as required by Section 01 74 19 and/or prior to contract closeout.

C. The Contractor shall comply with Federal, State of Minnesota, and local regulations for handling, removal, and disposal of asbestos containing material. In case of conflict or ambiguity among these laws and regulations, the most stringent law or regulation shall apply.

PART 6 - DOCUMENTS AND FORMS

6.01 Government Provided Documents

A. Scope of Work Drawings B. Existing Drawings (electronic): PDF and/ or AutoCAD (provided after award)

1. Hydraulic Calculations, B821 and Base Wide Fire Suppression

2. As-built fire suppression drawings, B821

3. As-built fire alarm drawings, B821 & B870

C. Front-end Specifications

Repair FACP and MNS, B821 & B870 Page 10 of 10

D. Submittal Register E. Liquidated Damages

6.02 Forms (Provided after Award)

A. Entry Access List Form B. Submittal Register Template C. DD 1354 Transfer and Acceptance of Military Real Property D. AF-3000 Material Approval E. AF 3064 Contract Progress Schedule F. AF 3065 Contract Progress Report G. AIA G702 Payment Application Form H. ENG Form 6282 Site Safety & Health Officer (SSHO) Designation Letter I. 934th Spill Response Reporting Form

END OF SECTION

STATEMENT OF WORK - QJKL 24-0014, 01 July 2025
PART 1 - GENERAL
1.01 PROJECT SCOPE
1.02 PROFESSIONAL DESIGN SERVICES
A. Title I (Type “A” Services). These services involve field investigations and surveys; similar fact-finding surveys of the site essential to proper design; preparation of reports and similar services not involved in the preparation of designs, pl...
B. Title I (Type “B” Services). These services include those items normally furnished by an DOR in the actual preparation of the design documents (plans, drawings, specifications, submittal register etc.) and include visual inspection of the site o...
C. Title II (Type “C” Services). Those items involving inspecting, monitoring, and evaluating construction activities to validate conformance to plans and specifications, including reviewing, evaluating and testing product submittals and shop drawi...
D. Applicable Standards, Manuals, and Pamphlets: The DOR shall prepare all design documents in conformance with the applicable portions of the following:
1. Unified Facilities Criteria (UFC)
2. Applicable Air Force Policy Directives, Instructions, Pamphlets, Manuals, Technical Data Bulletins, Engineering Technical Letters and other documents.
3. Current national codes, regulations, and specifications involving architectural, civil, electrical, environmental, and mechanical disciplines associated with the design and construction of each project as referenced by UFC.
4. Guide Specification: The DOR shall use Unified Facilities Guide Specifications (UFGS) as the basis for producing specifications under this contract. The specifications shall be tailored to suit the specific work requirements of the individual item...
E. CERTIFICATION OF DRAWINGS AND OTHER DOCUMENTS: The DOR, or their authorized representative, shall sign the original of all drawings and the first page of all specifications, estimates or similar documents under the DOR’s printed name and over th...
F. RESPONSIBILITY OF THE ARCHITECT ENGINEER: Notwithstanding any review, acceptance or approval by the Government, the A-E shall be responsible for the professional and technical quality of all designs, drawings, specifications, and other material ...
1. Reassignment of DOR design responsibilities to construction contractors is highly discouraged by the Government. This includes but not limited to the following: structural steel detailing, fire sprinkler design, stair systems, retaining wall system...
G. DESIGN INFORMATION: In general, the requirements presented are design objectives and the DOR is encouraged to suggest changes where they would not seriously deviate from the overall requirements and would result in substantial economic savings, ...
H. GOVERNMENT FURNISHED INFORMATION: The Government, through the office of the Contracting Officer, will furnish within five days after issuance of a contract, applicable data and information (as available) for the execution of the work described. ...
1. Base Standards: AFRC - Minn-St Paul ARS IFS | WBDG - Whole Building Design Guide
2. Division 01 Specification Sections
3. General Site Plan
4. Existing Record Drawings
5. Design Criteria
6. Sole-source Justification
I. DRAWINGS AND SPECIFICATIONS
1. General: Final drawings shall be submitted on hard copy and in electronic format. Hard copy drawings shall be half size (11” x 17”) paper copy (unless otherwise approved by the Contracting Officer). Electronic drawings shall be provided electronica...
a. Cover Sheet/Location Plan: The DOR shall prepare a cover sheet with a location plan on the first sheet of the project drawings. This Location Plan will be the base map or a portion thereof which covers the general project location and base location...
b. Code Data Sheet: The DOR shall prepare a separate sheet showing all code calculations, life safety requirements, and design conditions/assumptions.
c. Preliminary Plans: Preliminary Plans shall be prepared at working drawings scale and will present sufficient details to permit an adequate review. The DOR may use the tracing of the preliminary drawings for working drawings with the addition of nec...
d. Demolition and new work shall be clearly noted and shown on the drawings. Gross floor areas shall be shown for the building.
e. Drawings shall contain sufficient detail to clearly indicate type and sizes of materials, utilities, etc., and specifically to list separately all contractor-furnished equipment and all Government-furnished equipment to be installed by the contractor.
f. Final Drawings: The DOR shall not proceed with the final drawings until receipt of written review comments or approval or Phase I and II requirements from the Contracting Officer. These drawings shall be submitted for review by the Contracting Offi...
g. Specifications: The project specifications shall be prepared as a separate document. The specifications shall be prepared in accordance with Paragraph 1.02.D.4 Guide Specifications of this Statement of Work. The DOR shall edit the specifications so...
1.03 INVESTIGATION/ DESIGN PHASES (Title I Services).
A. Phase 1: During Phase 1, the DOR shall conduct a survey investigation and study based on broad guidance furnished herein, and as may be supplemented by other Government-furnished material, will determine the recommended scope, materials, quantit...
1. Survey of existing facilities, B821 & B870
2. Evaluate conversion of B821 dry system to wet system
3. Evaluate existing fire pumps conversion to city water pressure
4. Concept plans
B. Phase 2: Develops the drawings and specifications to an interim design level.
1. Notice to Proceed with Design
2. 50% Drawings (half size and electronic)
3. 50% Specifications
4. 50% Guaranteed Maximum Price (GMP)
5. 50% Design Analysis
6. 50% Design Review Conference at Government Offices
7. Notice to Proceed with Design
C. Phase 3: Completes the design and shall include all comments from Phase 2.
1. Final Drawings (95%) (half size and electronic)
2. Final Specifications (95%)
3. Final Guaranteed Maximum Price (95%)
4. Final Design Analysis (95%)
5. Conference at the Contracting Office (unless specifically omitted)
6. Construction Documents (100%) as listed below shall be delivered to the office of the Contracting Officer incorporating all review comments from the 95% review.
a. Construction Drawings (half size and electronic)
b. Construction Specifications
c. Guaranteed Maximum Price
d. Construction Final Design Analysis
1.04 CONSTRUCTION PHASE SERVICES
A. Title II (Type “C” Services). The Designer of Record (DOR) shall conduct reviews of product data, material samples, design data, certificates, & closeout submittals. Submittals shall be marked; Approved, Approved as Noted, Resubmit, or Rejected....
PART 2 - ADMINISTRATIVE
2.01 MEETINGS, CONFERENCES AND SITE VISITS
A. Post Award Meeting/Teleconference, Progress Meetings & Design Integration Meetings: After the issuance of a contract, the Contractor shall attend meetings at project site. The purpose of these meetings includes, but is not limited to contract di...
B. Meeting Minutes: The Contractor shall record and provide copies of all meeting minutes not later than 2 business days after the meeting. Minutes shall be sent by email to the Contracting Officer. Meeting minutes shall track all action items assi...
C. Base Access: The Contractor shall coordinate with the Contracting Officer to gain access to areas of the installation involving this project. The Contractor shall follow all base rules and regulations regarding entry and access to the base. Cont...
D. Government Property: Contractor shall protect all Government property against damage, to include but not limited to dust, fumes, impact, scratching, water, paint, joint compound, power failure, power surges, weather, heavy equipment, et cetera. ...
PART 3 - PROJECT DESCRIPTION AND REQUIREMENTS
3.01 DESCRIPTION OF WORK
A. Conduct site investigation of B821 Aircraft Maintenance Hangar. The known issues/ repairs are as follows:
1. Existing FACP is Monaco MAAP+ with Wheelock mass notification system. System is Class B wiring method.
2. Salvage and turnover to Government all Monaco equipment not expected to be used in the new system.
3. FACP/ MNS conduit that extends over the hangar bay from B821E to B821W is overfilled and need to be replaced.
4. High expansion foam system has been disabled. Foam system yellow pull-stations were converted to red pull-stations and initiate water flow through the foam generators. Evaluate locations; modify to standard red pull-station activation or demolish.
5. Wheelock notification devises will not work with Monaco MAAP-X and need to be replaced. Evaluate if wiring can be reused or demolished.
6. Hangar bay is Class I Div 2 18-inches AFF and 18-inches below roof.
7. The wet pipe system that supplies the fire suppression system in B821W needs a flow switch added where it Tee’s from the main in B821E Room 160 ceiling.
B. Conduct site investigation of B870 Fuel Cell Hangar. The know repairs are as follows:
1. Existing FACP is an obsolete Notifier panel. System is Class B wiring method.
2. The Hangar Bay and the corrosion control area are both Class I Div 2 spaces.
3. Evaluate requirements for smoke detectors in office areas.
C. Develop Construction Drawings and Technical Specifications that will replace the fire alarm systems, mass notification system to B821 and add mass notification to B870 with a Monaco MAAP-X systems. Make repairs to known deficiencies based on res...
D. Execute repair project using Construction Drawings, Front-end and Technical Specifications.
3.02 PROJECT AREA LIMITATIONS
A. All work shall be performed in the immediate project area. Refer to the drawings.
1. Work in B821 Hangar Bay access may be restricted due to maintenance activities. When restricted, a portion of the Hangar Bay will not be available. Work in portions of the bay will need to be coordinated with the aircraft maintenance schedule. When...
2. Work in B870: Hangar Bay access may be restricted due to maintenance activities. When restricted, workers are not allowed entry. Work in this space will need to be coordinated with the aircraft maintenance schedule. When the space becomes available...
3. B821: Controlled Area near B821E
4. B870: Restricted Area west of B870
3.03 EXISTING WORK
A. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
B. Repair or replace portions of existing work, which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a conditi...
C. Contractor shall protect all Government property against damage, to include but not limited to dust, fumes, impact, scratching, water, paint, joint compound, power failure, power surges, weather, heavy equipment, et cetera. All damage caused by ...
3.04 CONTRACTOR ACCESS AND USE OF PREMISES
A. Activity Regulations: Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingre...
B. Subcontractors and Personnel Contact: Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes a...
C. No Smoking Policy: Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobac...
D. Working Hours: Regular working hours will consist of an 8-1/2 hour period established by the Contracting Office, between 0700 and 1530 Monday through Friday, excluding Government Holidays and Unit Training Assemblies.
1. No work will be performed during weekend Unit Training Assembly (UTA). UTA’s are typically held once a month, except July. One or two UTAS may be extended Thursday to Sunday. An official schedule of UTA’s will be provided upon award.

E. Work Outside of Regular Hours: Work outside regular working hours requires Contracting Officer approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government to inspect the work in progress, giv...

3.05 DOCUMENTS
A. The Contractor shall:
1. Check any Government furnished construction drawings immediately upon receipt.
2. Compare any Government furnished construction drawings and verify the figures before laying out the work.
3. Promptly notify the Contracting Officer of any discrepancies.
4. Be responsible for any errors which might have been avoided by complying with this Paragraph 1.03.
B. Large scale drawings shall, in general, govern over small scale drawings. Figures marked on drawings shall, in general, be followed in preference to scale measurements.
C. Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contracto...
D. The Contractor shall maintain a complete set of construction drawings, construction specifications, project related sketches, pictures, approved Contract modifications (if any) and all approved submittals on the job site at all times. One set of...
E. Where conflicts between the drawings and specifications occur, specifications shall govern in accordance with FAR 52.236-21.
PART 4 - PERFORMANCE
4.01 Performance Period
A. The performance period for this statement of work is 472 days for the contract. The performance period for design phase is 189 days and the construction phase is 283 days. (See Period of Performance listing below for details.) The Contractor sha...
PART 5 - ENVIRONMENTAL
5.01 Environmental Requirements
A. Contractor shall adhere to environmental requirements in the following specification sections:
1. 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
2. 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
B. The contractor shall provide Construction & Debris Report as required by Section 01 74 19 and/or prior to contract closeout.
C. The Contractor shall comply with Federal, State of Minnesota, and local regulations for handling, removal, and disposal of asbestos containing material. In case of conflict or ambiguity among these laws and regulations, the most stringent law or...
PART 6 - DOCUMENTS AND FORMS
6.01 Government Provided Documents
A. Scope of Work Drawings
B. Existing Drawings (electronic): PDF and/ or AutoCAD (provided after award)
1. Hydraulic Calculations, B821 and Base Wide Fire Suppression
2. As-built fire suppression drawings, B821
3. As-built fire alarm drawings, B821 & B870
C. Front-end Specifications
D. Submittal Register
E. Liquidated Damages
6.02 Forms (Provided after Award)
A. Entry Access List Form
B. Submittal Register Template
C. DD 1354 Transfer and Acceptance of Military Real Property
D. AF-3000 Material Approval
E. AF 3064 Contract Progress Schedule
F. AF 3065 Contract Progress Report
G. AIA G702 Payment Application Form
H. ENG Form 6282 Site Safety & Health Officer (SSHO) Designation Letter
I. 934th Spill Response Reporting Form