This is a Statement of Work (SOW) for the Mobile Equipment Storage System project at Youngstown Air Reserve Station (YARS), dated July 31, 2026. The project objective is to procure, deliver, and install a mobile equipment storage system while dismantling and disposing of existing units. The vendor must provide design and project management services, complete disposal services including hauling and dumpster costs, and delivery and installation of the new system during normal business hours Monday through Friday.

The equipment deliverables comprise two separate installations: AFE1 in Building 413 and AFE2 in Building 407, utilizing the Datum 2Mobile 5Carriage System or comparable hardware. AFE1 includes 32 prepunch tops and 160 shelves, one adjustable track unit with one fixed carriage and three mechanical carriages, polyvinyl decking, steel ADA ramp, three hybrid open drive boxes, 16 closed "L" and 24 "T" uprights, various support components, flat rear panels, eight hinged doors with locks, trim and end stops, anti-tip brackets, label holders, and four hybrid melamine end panels. AFE2 in Building 407 requires similar components in larger quantities: 40 prepunch tops and 200 shelves, one adjustable track with one fixed and four mechanical carriages, plus increased quantities of uprights (20 "L" and 30 "T"), supports, panels, doors, and five melamine end panels. The customer must provide a clean, prepared space for unloading and assembly and ensure facility readiness prior to the installation date to prevent delays.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Project Name: Mobile Equipment Storage System

Date Prepared: July 31, 2026

1. Project Objective The objective of this project is to procure, deliver, and install a Mobile Equipment Storage System at the Youngstown Air Reserve Station (YARS) facility. This project also includes the dismantling and disposal of existing units to prepare the space for the new installation.

2. Scope of Work and Services Vendor will provide the following services to YARS ("Customer"):

Design & Project Management: Provision of system design and overall project management to ensure successful implementation.

Disposal Services: Labor and services for the disposal of existing units, which includes hauling and dumpster costs.

Delivery & Installation: Receiving the new materials, delivering them to the site, and performing the complete installation of the mobile carriage system.

Installation will be performed during normal business hours Monday-Friday.

3. Equipment and Deliverables The Vendor will supply the following hardware and components as part of the Datum 2Mobile 5Carriage System or comparable hardware and components:

AFE1 – Building 413

Prepunch top (QTY 32) and unslotted standard duty shelves (12"D x 48"W)

(QTY 160)

Mobile Trak5 adjustable tracks (QTY 1), fixed carriages (QTY 1), and mechanical carriages (QTY 3)

Polyvinyl decking (QTY 1) and steel ADA ramp (QTY 1)

Hybrid open drive boxes with 18" three-spoke handles (QTY 3) Closed "L" (QTY 16) and "T" uprights (QTY 24) (12"D X 97"H) Single rivet supports (QTY 64), carriage shelving supports (QTY 12), and heavy-duty shelf supports (QTY 320) Flat rear panels (QTY 16) and standard hinged doors with key locks (QTY 8)

(48"W x 97.25"H) Deck end trim (QTY 2), low-profile end stops (QTY 2), heavy-duty anti-tip brackets (QTY 6), and label holders (QTY 8) Hybrid melamine end panels (QTY 4)

AFE2 – Building 407

Prepunch top (QTY 40) and unslotted standard duty shelves (12"D x 48"W)

(QTY 200)

Mobile Trak5 adjustable tracks (QTY 1), fixed carriages (QTY 1), and mechanical carriages (QTY 4) Polyvinyl decking (QTY 1) and steel ADA ramp (QTY 1) Hybrid open drive boxes with 18" three-spoke handles (QTY 3) Closed "L" (QTY 20) and "T" uprights (QTY 30) (12"D X 97"H) Single rivet supports (QTY 80), carriage shelving supports (QTY 15), and heavy-duty shelf supports (QTY 400) Flat rear panels (QTY 20) and standard hinged doors with key locks (QTY 8)

(48"W x 97.25"H) Deck end trim (QTY 2), low-profile end stops (QTY 2), heavy-duty anti-tip brackets (QTY 8), and label holders (QTY 10) Hybrid melamine end panels (QTY 5)

4. Customer Responsibilities To ensure a successful and timely installation, the Customer must adhere to the following:

Provide a clean, sufficient, and prepared space for unloading and assembly prior to the scheduled installation date.