This is a Project Specifications document for the Lyndon B. Johnson (LYJO) National Historical Park reroof and structural repair project in Johnson City, Texas. The project encompasses three main work locations: the Johnson Boyhood Home (Barn and Smokehouse at 200 East Elm Street), the Johnson Settlement (Bruckner Barn, Cooler House, and optional Settlement Cabin at 100 Lady Bird Lane), and involves reroofing historic structures with synthetic shake/shingle materials, repairing deteriorated wood structural components, and managing lightning protection systems.
The specifications detail comprehensive administrative and construction requirements organized into multiple divisions. Key deliverables and performance requirements include: removal and replacement of wood shingles on four structures (Bruckner Barn, Stubbs Cooler Building, Boyhood Home Barn, and Boyhood Home Smokehouse) with synthetic shake/shingle roofs; removal and reinstallation of existing lightning protection systems on three buildings with new installation on the Smokehouse; optional work on Settlement Cabin for roof replacement and lightning protection (Bid Options 01 and 02); structural repairs to wood joists and purlins; and corrugated metal roof replacement with gutters and downspouts on the Boyhood Home Barn. The contractor must comply with Secretary of the Interior Standards for Rehabilitation, National Park Service Sustainable Design Requirements, historic preservation treatment procedures, and strict environmental controls including electric equipment only (no gas-powered tools), dust capture systems, and waste management protocols. Work must accommodate continuous public access at the Settlement Site with phased construction scheduling, maintain visitor safety through barricading, and coordinate with park operations. The contractor is responsible for obtaining necessary permits, managing a detailed construction schedule using Critical Path Method (CPM) with monthly updates, submitting shop drawings and product data for approval, maintaining photographic documentation, and preparing comprehensive closeout documentation including operation and maintenance manuals.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140PS126Q0036_Amd_0002.pdf | ||
| Attachment_05__Request_for_Information_0002.xlsx | XLSX spreadsheet | |
| Sol_140PS126Q0036_Amd_0001.pdf | ||
| Sol_140PS126Q0036.pdf | ||
| Attachment_05__Request_for_Information.xlsx | XLSX spreadsheet | |
| Attachment_03__PRCING_SHEET.xlsx | XLSX spreadsheet | |
| Attachment_02__Drawings.pdf | ||
| Attachment_04__Wage_Determination_TX20260193.pdf | ||
| Attachment_06__Site_Visit_-_Construction.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PMIS 241284 - RCM: Reroof Three Historic Structures in the Settlement PMIS 250239 RCM: Reroof Barn and Smokehouse at Boyhood Home Bid Option: PMIS 156063 RCM: Reroof Settlement Cabin
Lydon B Johnson National Historical Park Johnson City, Texas
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
100% FINAL CONSTRUCTION DOCUMENTS
May 05, 2026
LYJO 241282 156063-250239
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
| 01 11 00 |
| SUMMARY OF WORK |
| 01 26 01 |
| CONTRACT MODIFICATION PROCEDURES |
| 01 27 00 |
| DEFINITION OF CONTRACT LINE ITEMS |
| 01 31 00 |
| PROJECT MANAGEMENT & COORDINATION |
| 01 32 16 |
| CONSTRUCTION SCHEDULE |
| 01 32 33 |
| PHOTOGRAPHIC DOCUMENTATION |
| 01 33 23 |
| SUBMITTAL PROCEDURES |
| 01 33 23.A |
| SUBMITTAL LIST |
| 01 35 13.22 |
| ARCHEOLOGICAL PROTECTION |
| 01 35 23 |
| SAFETY REQUIREMENTS |
| 01 35 91 |
| HISTORIC PRESERVATION TREATMENT PROCEDURES |
| 01 40 00 |
| QUALITY REQUIREMENTS |
| 01 42 00 |
| REFERENCE STANDARDS |
| 01 50 00 |
| TEMPORARY FACILITIES AND CONTROLS |
| 01 57 19.12 |
| NOISE & ACOUSTICS MANAGEMENT |
| 01 67 00 |
| PRODUCT REQUIREMENTS |
| 01 73 29 |
| CUTTING AND PATCHING |
| 01 73 40 |
| EXECUTION |
| 01 74 19 |
| CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL |
| 01 74 19 |
| WASTE MANAGEMENT APPENDIX A |
| 01 74 19 |
| WASTE MANAGEMENT APPENDIX B |
| 01 77 00 |
| CLOSEOUT PROCEDURES |
| 01 81 13 |
| SUSTAINABLE DESIGN REQUIREMENTS FOR NON-LEED™PROJECTS |
DIVISION 02 – EXISTING CONDITIONS
02 41 91 SELECTIVE HISTORIC DEMOLITION
DIVISION 03-05 – NOT USED
DIVISION 06 – WOOD, PLASTIC, COMPOSITES
· 06 10 00 ROUGH CARPENTRY
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
| 07 31 32 |
| SYNTHETIC SHAKE SHINGLES |
| 07 62 00 |
| SHEET METAL AND SHEET METAL FLASHING |
| 07 65 26 |
| SELF ADHEREING FLASHING |
| 07 92 00 |
| JOINT SEALANTS |
DIVISION 08-25 : NOT USED
DIVISION 26 ELECTRICAL
| 26 05 26 | GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS |
| 26 41 13 | LIGHTNING PROTECTION FOR STRUCTURES |
DIVISION 27-32: NOT USED
LYJO 241282 241283 156063 250239
TOC-2
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Contractor use of site.
3. Public use of sites.
4. Occupancy requirements for buildings.
5. Conduct of Operations.
6. General Dust Control.
7. Work Restrictions.
8. Special Construction Requirements.
9. Work Under Other Contracts.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Johnson Boyhood Home (Barn and Smokehouse), 200 East Elm Street, Johnson City, Texas 87836 B. Second Project Location: Johnson Settlement (Bruckner Barn, Cooler House and Bid Option 01 - Settlement Cabin), 100 Lady Bird Lane Ste 329, Johnson City, TX 78636 C. The Work consists of the following:
1. The work includes, but is not limited to, the following:
a. Removal of wood shingles, repair to wood joists, wood purlins and reinstallation of new Synthetic shake/shingle roofs at the Bruckner Barn and Stubbs Cooler Building (Stubbs Well House), the barn and smoke house at the Boyhood Home Unit.
b. Remove and reinstallation of lightning protection on Bruckner Barn, Polk Barn, and Stubbs Cooler House (Stubbs Well House) and the Boyhood Home’ Barn
c. Add lightning protection to the Smokehouse at the Boyhood Home
d. Bid Option 01: Removal of wood shingles, repair/replace wood purlins and installation of new Synthetic shake/shingle roofs at Settlement Cabin.
e. Bid Option 02: Remove and reinstallation of lightning protection on Settlement Cabin Roof.
D. Project is designed to comply with NPS Sustainable Design Requirements as specified in Division 01 Section 018113 "Sustainable Design Requirements for Non-LEED Projects."
E. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. The overall Johnson Settlement site is very open to visitors. The contractor shall limit the areas of construction and construction activities to avoid disruption to visitors and government
LYJO 241282-241283-205239
01 11 00
SUMMARY OF WORK
staff activities.
2. Limits: Confine constructions operations to areas where work is permitted.
3. The Contractor and construction staff shall have limited access to the Polk Barn and Bruckner Barn. Prior to accessing the Polk and Bruckner Barn, the contractor shall inform the park officials 48 hours in advance.
4. Parking for construction and contractor staff shall be located and confined to a designated area on existing lawns/yards at a location approved by park maintenance.
5. The contractor shall be responsible for the protection of the existing site. Upon completion of the Contract, the contractor shall restore the site including work areas to its original configuration including, but not limited to, original plantings and grading.
6. All vehicles must use pneumatic tires.
7. Any vehicle exceeding a gross weight of 10,000 pounds must use protection described below:
a. Two layers of ¾” plywood, with layer of 2” extruded polystyrene (EPS) panels in between, laid in such a manner that the surface of the ground is covered and protected.
b. When protection panels EPS has become compressed to less than ½ half its original thickness, or to an extend that the EPS is not protecting the existing grade, it is to be replaced as delineated in paragraph “a” above.
B. Storage of Materials: Storage of materials will be permitted at the site.
1. Confine storage of materials to areas indicated by Contracting Officer.
2. Storage of materials shall not interfere with Park access and visitor circulation to the site.
3. Material storage and contractor staging area shall be allowed in an area designated by the CO.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repair or replace existing natural features, at no additional expense to the Government.
2. Provide temporary barriers to protect existing natural features.
3. Do not remove, injure, or destroy existing natural features without prior approval. Consult with Contracting Officer and remove agreed-on existing natural features that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing natural features.
5. Carefully supervise excavating, grading, filling, and other construction operations near existing natural features to prevent damage.
D. Driveways and Entrances: Keep driveways and entrances serving the Johnson Settlement premises clear and available to visitors, the Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.4 PUBLIC USE OF SITE
A. The Bruckner Barn, Polk Barn, Settlement Cabin, and Cooler House (N. T. Stubbs Well House) shall be closed to the public during construction but not the Settlement Site. The barn and smokehouse at the Boyhood Home Site will be closed to the public but not the Boyhood Home.
1. The Settlement Site is a heavily used public facility that will remain open to the public and park operations.
a. Construction activities shall not block access to Settlement roads, drives, pathways and access to adjacent historic structures.
2. Construction schedules and activities shall be planned accordingly.
B. Visitors shall be kept at a safe distance from demolition and construction areas. The contractor shall provide and maintain barricades between work areas and visitor access/egress areas. All barricade locations shall be coordinated with the Contracting Officer and the Park’s Safety Officer.
C. If closure is required to the Settlement Site for construction operations and material deliveries, the Contractor shall notify the Contracting Officer 48 hours prior to closure. The Settlement Site access shall not be closed without the written approval by the Contracting Officer.
1.5 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government shall require access to all the structures in this contract for the duration of the construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage and access. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
1.6 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
D. All work shall adhere to the Secretary of the Interior Standards for Rehabilitation.
1.7 GENERAL DUST CONTROL
A. Compliance with requirements for dust protection and air quality control is required for work areas which abut park resources. Dust removal and periodic cleaning requirements apply to all work and work areas. Contractor shall employ dust and pollution prevention procedures so that a healthy environment is fully maintained at all times.
1. Clean up loose debris daily, or more frequently as required to prevent the wind from spreading debris.
2. Keep dumpsters covered when not in use.
3. Wet down debris (as appropriate) to prevent air pollution from rising from demolition work.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:30 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Not allowed without prior approval.
2. Early Morning Hours: Not allowed without prior approval.
3. Hours for Core Drilling and noisy activity: Coordinate with Contracting Officer for prior approval.
B. Existing Utilities
1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
2. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: Coordinate with Contracting Officer.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1. Contractor shall designate a smoking area and provide means for workers to safely dispose of cigarette/cigar butts.
E. No food, chewing gum or beverages, other than bottled water, are permitted within the work areas.
F. No emissions are allowed, all saws and equipment must be electric, no gas-powered equipment is permitted.
G. All dust generated by Demolition or Construction activities shall be captured.
H. No work shall be performed that adversely impacts historic structures’ fabric - original existing surfaces.
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
A. The Settlement Site will remain open to the public during demolition and construction activities. Coordinate with the Park for phasing and scheduling requirements.
B. If conflicts occur between the drawings and/or specifications, the specifications govern over drawings.
1.10 SPECIAL CONSTRUCTION REQUIREMENTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this contract. Coordinate the Work of this Contract with work performed under separate contracts.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
Page 1 - SECTION 01 26 01
LYJO 241282 241283 250239
Contract Modification Procedures
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year. Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction
Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized, then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
| Overhead | 10% |
| Profit | 6% |
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, then the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3, E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line-Item No. 01 Reroof Bruckner Barn.
1. This item consists of demolition of existing wood shakes, repairs to deteriorated wood sleepers, installation of new synthetic shake/shingles and all appurtenances.
2. Measurement for payment will be the percentage of completion for each line item
3. Payment will be made at the contract per lump sum price.
B. Contract Line-Item No. 02 Reroof Stubbs Cooler Building.
1. This item consists of demolition of existing wood shakes, repairs to deteriorated wood sleepers, installation of synthetic shake/shingles and all appurtenances.
2. Measurement for payment will be the percentage of completion for each line item
3. Payment will be made at the contract per lump sum price.
C. Contract Line-Item No. 03 Boyhood Home - Reroof Barn
1. This item consists of demolition of existing wood shakes, repairs to deteriorated wood sleepers, installation of synthetic shake/shingles and all appurtenances.
2. Remove existing corrugated metal roof and replace with new corrugated metal roof
3. Remove and replace gutter and downspout. Provide and install new matching gutter and downspouts along with all appurtenances.
4. Measurement for payment will be the percentage of completion for each line item
5. Payment will be made at the contract per lump sum price.
D. Contract Line-Item No. 04 Boyhood Home - Reroof Smokehouse
1. This item consists of demolition of existing wood shakes, repairs to deteriorated wood sleepers, and installation of synthetic shake/shingles and all appurtenances.
2. Measurement for payment will be the percentage of completion for each line item
3. Payment will be made at the contract per lump sum price.
LYJO 241282- 241283- 250239
Page 1 - SECTION 01 27 00 Definition of Contract Line Items
E. Contract Line-Item No. 05 Remove and Reinstall Lightning Protections Systems on Bruckner Barn.
1. This item consists of removal of existing lightning protection cables, rods, and fasteners prior to removal of existing cedar shingles.
2. Installation of new cables, clips, fasteners, grounding rods, grounding loop, and towers after new roofs are completed.
3. Measurement for payment will be the percentage of completion for each line item
4. Payment will be made at the contract per lump sum price.
F. Contract Line-Item No. 06 Remove and Reinstall Lightning Protections Systems on Stubbs Cooler Building.
1. This item consists of removal of existing lightning protection cables, rods, and fasteners prior to removal of existing cedar shingles.
2. Installation of new cables, clips, fasteners, grounding rods, grounding loop, and towers after new roofs are completed.
3. Measurement for payment will be the percentage of completion for each line item
4. Payment will be made at the contract per lump sum price.
G. Contract Line-Item No. 07 Remove and Reinstall Lightning Protections Systems on the Barn at the Boyhood Home Unit.
1. This item consists of removal of existing lightning protection cables, rods, and fasteners prior to removal of existing cedar shingles.
2. Installation of new cables, clips, fasteners, grounding rods, grounding loop, and towers after new roofs are completed.
3. Measurement for payment will be the percentage of completion for each line item
4. Payment will be made at the contract per lump sum price.
H. Contract Line-Item No. 08 Install New Lightning Protections Systems on the Smokehouse at the Boyhood Home Unit.
1. Installation of new cables, clips, fasteners, grounding rods, grounding loop, and towers after new roofs are completed.
2. Measurement for payment will be the percentage of completion for each line item
3. Payment will be made at the contract per lump sum price.
I. Bid Option Line-Item No. 01 Reroof Settlement Cabin.
1. This item consists of demolition of existing wood shakes, repairs to deteriorated wood sleepers, and installation of new synthetic shakes/shingles.
2. Measurement for payment will be the percentage of completion for each line item
3. Payment will be made at the contract per lump sum price.
J. Bid Option Line-Item No. 02 Remove and Reinstall Lightning Protections Systems on the Settlement Cabin.
1. This item consists of removal of existing lightning protection cables, rods, and fasteners prior to removal of existing cedar shingles.
2. Installation of new cables, clips, fasteners, grounding rods, grounding loop, and towers after new roofs are completed.
3. Measurement for payment will be the percentage of completion for each line item
4. Payment will be made at the contract per lump sum price.
K.
END OF SECTION 01 27 00
REQUEST FOR INFORMATION #
Project:
Contract No.: Date:
To:
cc:
From:
Subject:
Please provide the following information or clarification:
Response required by
Date:
To:
From:
Subject: Response to RFI No
LYJO 241282 241283 250239
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on the Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. Project meetings.
7. Environmental Coordination.
8. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and report deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches(750 by 1000 mm).
a. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.
b. Refer to individual Sections for Coordination Drawing requirements for Work in those Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
LYJO 241282-241283-250239
SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
3. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
4. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches (32 mm) in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
5. Review: Contracting Officer (CO) will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform Contractor, who shall make changes as directed and resubmit.
C. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 Submittal Procedures.
D. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Preparation Format: AutoCAD, Version, operating in Microsoft Windows operating system.
3. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
4. Contracting Officer (CO) will furnish Contractor one set of digital data files (AutoCAD) of Drawings for use in preparing coordination digital data files.
a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCAD dwg format.
E. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Indoor Air Quality (IAQ) Management Plan.
11. Historic Preservation Treatment Plan.
12. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
F. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form attached at the end of this section.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution.
8. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
9. Contractor's signature.
10. Requested date for response.
11. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form attached at the end of this Section as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed according to the terms and conditions of the contract.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an onsite meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Liquidated damages.
12. Contractor Performance Evaluation.
13. Display of Hotline posters.
14. Notice to proceed.
15. Correspondence procedures.
16. Acceptance/rejection of work.
17. Progress meetings.
18. Submittal procedures.
19. NPS Final Accessibility Inspection.
20. Environmental requirements.
21. Permit requirements.
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials.
25. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections,
h. Construction Schedule update (provide updated CPM).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Sustainable design requirements.
i. Review of mockups.
j. Possible conflicts.
k. Compatibility requirements.
l. Time schedules.
m. Weather limitations.
n. Manufacturer's written instructions.
o. Warranty requirements.
p. Compatibility of materials.
q. Acceptability of substrates.
r. Temporary facilities and controls.
s. Space and access limitations.
t. Regulations of agency(ies) with jurisdiction.
u. Testing and inspecting requirements.
v. Installation procedures.
w. Coordination with other work.
x. Required performance results.
y. Protection of adjacent work.
z. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; familiarity with Environmental Management Systems (EMSs) such as ISO 14001; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Waste Management Plan (WMP).
c. Implementation of the Indoor Air Quality (IAQ) Management Plan.
d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.
e. Training for Contractor personnel in accordance with their position requirements.
f. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Indoor Air Quality (IAQ) Management.
4. Noise & Acoustics Management.
5. Construction Waste Management.
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
1. Overview of environmental issues related to the building industry.
2. Overview of environmental issues related to the Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management.
b. Indoor Air Quality (IAQ) Management.
c. Noise & Acoustics Management.
4. Pollution Prevention (P2) practices: Submit evidence of familiarity with P2practices and training.
5. Green Building Rating Programs: Submit evidence of familiarity with ASTM E2432.
6. Compliance with environmental regulations: As specified in Regulatory Requirements. Submit Contractor 40 CFR employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.
1.8 PERMITS
A. General:
1. Permits and Responsibilities: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract the Contractor will not be considered an agent of the Government. Therefore, the Contractor will comply with the appropriate Federal, State and local laws.
B. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(es) with Jurisdiction, Construction Manager, Contracting Officer and Park to avoid conflicts and to ensure orderly execution of the Work.
2. Supply all needed information to Agency(es) with Jurisdiction issuing permits, pay any fees required and provide all material needed to comply with the permit’s conditions and provisions.
PART 2 - PRODUCTS (Not Used) PART 3 -…