These documents are fire alarm system drawings for a new hybrid operating room project at the VA Caribbean Healthcare System in San Juan, Puerto Rico. The drawings include fire alarm plans for multiple floors (main floor and penthouse) and provide detailed technical specifications for the fire alarm system installation. Key requirements include:
The fire alarm system must comply with NFPA 72 (2022 edition), NFPA 70, NFPA 101, and local VA codes. The system requires digital addressable devices compatible with the existing campus fire alarm standards, with specific installation notes mandating that all new devices tie into the closest existing notification appliance circuit panel. The contractor must provide complete shop drawings, perform functional testing, and coordinate with the VA's fire alarm maintenance contractor for device terminations and programming. Additional specifications cover device placement, wiring methods, conduit requirements (to be painted red and labeled), and system response protocols, including shutting down air handling units and opening locked egress doors upon fire alarm activation.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F
F
FR
FIRE ALARM SYSTEM RISER KEYNOTES
1. SEE FLOOR PLANS FOR QUANTITIES OF NEW DEVICES AND APPLIANCES, TYPICAL.
2. NEW SUPERVISION CIRCUIT [(2)CLASS B WIRING, TSP-#14 AWG, 3/4" C].
3. NEW SIGNALING LINE CIRCUIT [(2)CLASS B WIRING, TSP-#14 AWG, 3/4" C].
4. EXISTING POWER CIRCUIT (CLASS B WIRING, TSP-#14, 3/4" C).
5. EXISTING FIRE ALARM TERMINAL CABINET.6.
FIRE ALARM RELAY FOR HYBRID OR DOOR.
FIRE ALARM GENERAL NOTES
A. THIS BUILDING REQUIRES A FIRE ALARM SYSTEM THAT COMPLIES WITH NFPA 72 2022
EDITION, NFPA 70 ARTICLE 760, NFPA 101 AND LOCAL VA CODES AND ORDINANCES.
B. FIRE ALARM DOCUMENTS SHALL BE PROVIDED BY OTHERS UNDER SEPARATE
CONTRACT AND SHALL BE USED FOR IFC. THE DOCUMENTS SHALL INCLUDE COMPLETE
DRAWINGS SHOWING ALL EQUIPMENT, DEVICES LOCATIONS, BATTERY
CALCULATIONS, SEQUENCE OF OPERATIONS, POINT TO POINT WIRING, WIRING
LEGEND, FA RISER DIAGRAM, NON-LATCHING FIRE ALARM SYSTEM AND FIRE ALARM
MONITORING SHALL BE CONTACT ID POINT ADDRESSABLE TO THE REMOTE
SUPERVISING STATION VIA THE DIGITAL ALARM COMMUNICATOR BUILT-IN THE FACP
AND ALL OTHER DOCUMENTS REQUIRED BY THE VA.
REFER TO FINAL APPROVED MECHANICAL PLANS AND FIRE PROTECTION
SYSTEM PLANS FOR OTHER LOCATIONS OF FIRE ALARM EQUIPMENT AND/OR DEVICES
REQUIREMENTS AND ADDITIONAL INFORMATION.
C. THE FIRE ALARM CONTRACTOR SHALL BE AN AUTHORIZED
REPRESENTATIVE/DISTRIBUTOR BY THE MANUFACTURER. ACCEPTABLE DIGITAL
ADDRESSABLE SYSTEMS TO MATCH STATION'S STANDARDS.
D. THE EQUIPMENT AND DEVICES SHOWN ON THESE ELECTRICAL DRAWINGS
REPRESENTS A BASIS FOR DESIGN ONLY. THE SELECTED FIRE ALARM SYSTEM
CONTRACTOR IS EXPECTED TO BE FAMILIAR WITH THE ACCEPTED PRACTICES OF THE
VA AND SHALL INCLUDE ALL EQUIPMENT, MATERIALS AND LABOR TO MEET
ALL APPLICABLE CODES AND VA REQUIREMENTS AND SPECIFICATIONS.
E. IT IS THE SOLE RESPONSIBILITY OF THE FIRE ALARM SUBCONTRACTOR TO PROVIDE
A COMPLETE SET OF SHOP DRAWINGS REFLECTING A FULLY-FUNCTIONAL,
CODE-COMPLIANT INSTALLATION AS PER NFPA 72 2022, NFPA 70 ARTICLE 760,
NFPA 101 AND LOCAL VA CODES AND ORDINANCES. BIDS SHALL BE BASED UPON SUCH
A SYSTEM. CHANGE ORDERS FOR ADDITIONAL REQUIRED SYSTEM COMPONENTS
AND WIRING NOT SHOWN ON THE FIRE ALARM PLANS WILL NOT BE APPROVED.
THE FIRE ALARM SYSTEM SUBCONTRACTOR SHALL SUBMIT A SEPARATE FIRE ALARM
SYSTEM DESIGN TO THE VA PER THE REQUIREMENTS OF THE LOCAL CODE AND
ORDINANCES TO HAVE A FULLY FUNCTIONAL FIRE ALARM SYSTEM.
F. THE BUILDING SHALL BE TESTED BY A PRIVATE COMPANY HIRED BY THE CONTRACTOR
TO COMPLY WITH ALL OF THE VA REQUIREMENTS.
G. SHOP DRAWINGS ARE REQUIRED BY A LICENSED AND CERTIFIED CONTRACTOR.
ALL SHOP DRAWINGS MUST BE REVIEWED BY THE ORIGINAL ENGINEER OF RECORD
FOR THE PROJECT FOR COMPLIANCE TO DESIGN. ENGINEER OF RECORD MUST
PROVIDE A SIGNED LETTER WITH THE SHOP DRAWING SUBMITTAL STATING THE
PROJECT IS REVIEWED AND APPROVED.
H. THIS CAMPUS HAS STANDARDIZED EXISTING FIRE ALARM SYSTEM AND
RESPONSIBLE FOR ALL INSPECTION, TESTING AND MAINTENANCE.
THE GENERAL CONTRACTOR SHALL DIRECTLY HIRE EXISTING CAMPUS PROVIDER
AND COORDINATE ALL WORK WITH EXISTING FIRE ALARM MANUFACTURER.
I. THE DESIGN INTENT IS TO TIE THE NEW FIRE ALARM DEVICES TO THE EXISTING FIRE
ALARM TERMINAL CABINET CLOSEST TO SCOPE OF WORK.
FIRE ALARM DEVICES SHALL WORK IN COLLABORATION WITH THE EXISTING FACP.
UPON OPERATION OF A FIRE ALARM INITIATING DEVICE WITHIN THAT ZONE, A TEMPORAL
THREE ALARM SIGNAL AND VISIBLE APPLIANCES SHALL ONLY ACTIVATE WITHIN THAT
ZONE WHILE SENDING A VOICE MESSAGE THROUGHOUT THE BUILDING TO PROVIDE
STAFF RESPONSE IN A TIMELY MANNER AS DESCRIBED IN THE VA FIRE PROTECTION
DESIGN MANUAL SECTION 7.3.F.2.
FF FR
EXISTING
TERMINAL
CABINET
EXISTING
CIRCUIT
EXISTING
FARA
EXISTING
FACP
7.
EXISTING FIRE ALARM ANNUNCIATOR PANEL.
1P 1 POLE (2P, 3P, 4P, ETC.)
A AMPERE
AC ABOVE COUNTER
ACLG ABOVE CEILING
ADO AUTOMATIC DOOR OPENER
AF AMP FRAME
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AFI ARC FAULT CIRCUIT
INTERRUPTER
AHU AIR HANDLING UNIT
AL ALUMINUM
ALT ALTERNATE
AMP AMPERE
AMPL AMPLIFIER
ANNUN ANNUNCIATOR
APPROX APPROXIMATELY
AQ-STAT AQUASTAT
ARCH ARCHITECT, ARCHITECTURAL
AS AMP SWITCH
AT AMP TRIP
ATS AUTOMATIC TRANSFER SWITCH
AUTO AUTOMATIC
AUX AUXILIARY
AV AUDIO VISUAL
AWG AMERICAN WIRE GAUGE
BATT BATTERY
BD BOARD
BLDG BUILDING
BMS BUILDING MANAGEMENT SYSTEM
C CONDUIT
CAB CABINET
CAT CATALOG
CATV CABLE TELEVISION
CB CIRCUIT BREAKER
CCTV CLOSED CIRCUIT TELEVISION
CKT CIRCUIT
CLG CEILING
COMB COMBINATION
CMPR COMPRESSOR
CONN CONNECTION
CONST CONSTRUCTION
CONT CONTINUATION OR CONTINUOUS
CONTR CONTRACTOR
CONV CONVECTOR
CP CIRCULATING PUMP
CRT CATHODE-RAY TUBE
CT CURRENT TRANSFORMER
CTR CENTER
CU COPPER
DCP DOMESTIC WATER CIRCULATING PUMP
DEPT DEPARTMENT
DET DETAIL
DIA DIAMETER
DISC DISCONNECT
DIST DISTRIBUTION
DN DOWN
DPR DAMPER
DS SAFETY DISCONNECT SWITCH
DT DOUBLE THROW
DWG DRAWING
EC ELECTRICAL CONTRACTOR
ELEC ELECTRIC, ELECTRICAL
ELEV ELEVATOR
ELU EMERGENCY LIGHTING UNIT
EM EMERGENCY
EMS ENERGY MANAGEMENT SYSTEM
EMT ELECTRICAL METALLIC TUBING
EP ELECTRIC PNEUMATIC
EQUIP EQUIPMENT
EWC ELECTRIC WATER COOLER
EXIST EXISTING
EXH EXHAUST
EXP EXPLOSION PROOF
FA FIRE ALARM
FABP FIRE ALARM BOOSTER POWER
SUPPLY PANEL
FACP FIRE ALARM CONTROL PANEL
FARA FIRE ALARM ANNUNCIATOR PANEL
FIXT FIXTURE
FLR FLOOR
FLUOR FLUORESCENT
FU FUSE
FUDS FUSED SAFETY DISCONNECT SWITCH
GA GAUGE
GAL GALLON
GALV GALVANIZED
GC GENERAL CONTRACTOR
GEN GENERATOR
GFI GROUND FAULT CIRCUIT INTERRUPTER
GFP GROUND FAULT PROTECTOR
GND GROUND
GRS GALVANIZED RIGID STEEL (CONDUIT)
GYP BD GYPSUM BOARD
HOA HANDS-OFF-AUTOMATIC SWITCH
HORIZ HORIZONTAL
HP HORSEPOWER
HPF HIGH POWER FACTOR
HT HEIGHT
HTG HEATING
HTR HEATER
HV HIGH VOLTAGE
HVAC HEATING, VENTILATING AND AIR
CONDITIONING
IC INTERRUPTING CAPACITY
IG ISOLATED GROUND
IMC INTERMEDIATE METAL CONDUIT
INCAND INCANDESCENT
IR INFRARED
I/W INTERLOCK WITH
J-BOX JUNCTION BOX
KV KILOVOLT
KVA KILOVOLT-AMPERE
KVAR KILOVOLT-AMPERE REACTIVE
KW KILOWATT
KWH KILOWATT HOUR
LOC LOCATE OR LOCATION
LT LIGHT
LTG LIGHTING
LTNG LIGHTNING
LV LOW VOLTAGE
MAX MAXIMUM
MAG.S MAGNETIC STARTER
M/C MOMENTARY CONTACT
MC MECHANICAL CONTRACTOR
ELECTRICAL ABBREVIATIONS LIST
MCB MAIN CIRCUIT BREAKER
MCC MOTOR CONTROL CENTER
MDC MAIN DISTRIBUTION CENTER
MDP MAIN DISTRIBUTION PANEL
MFR MANUFACTURER
MFS MAIN FUSED DISCONNECT SW
MH MANHOLE
MIC MICROPHONE
MIN MINIMUM
MISC MISCELLANEOUS
MLO MAIN LUGS ONLY
MMS MANUAL MOTOR STARTER
MOA MULTIOUTLET ASSEMBLY
MSP MOTOR STARTER PANELBOARD
MSBD MAIN SWITCHBOARD
MT MOUNT
MT.C EMPTY CONDUIT
MTS MANUAL TRANSFER SWITCH
MTR MOTOR, MOTORIZED
N.C. NORMALLY CLOSED
NEC NATIONAL ELECTRICAL CODE
NEMA NATIONAL ELECTRICAL
MANUFACTURER'S ASSOCIATION
NFDS NON-FUSED SAFETY DISCONNECT
SWITCH
NIC NOT IN CONTRACT
NL NIGHT LIGHT
N.O. NORMALLY OPEN
NPF NORMAL POWER FACTOR
NTS NOT TO SCALE
OH OVERHEAD
OL OVERLOADS
PA PUBLIC ADDRESS
PB PULL BOX OR PUSHBUTTON
PE PNEUMATIC ELECTRIC
PED PEDESTAL
PF POWER FACTOR
PH PHASE
PIV POST INDICATING VALVE
PNL PANEL
PP POWER POLE
PR PAIR
PRI PRIMARY
PROJ PROJECTION
PRV POWER ROOF VENTILATOR
PT POTENTIAL TRANSFORMER
PVC POLYVINYL CHLORIDE (CONDUIT)
PWR POWER
QUAN QUANTITY
RCPT RECEPTACLE
REQD REQUIRED
RM ROOM
RSC RIGID STEEL CONDUIT
RTU ROOF TOP UNIT
SC SURFACE CONDUIT
SEC SECONDARY
SHT SHEET
SIM SIMILAR
S/N SOLID NEUTRAL
SPEC SPECIFICATION
SPKR SPEAKER
SP SPARE
SPD SURGE PROTECTION DEVICE
SS STAINLESS STEEL
SSW SELECTOR SWITCH
S/S STOP/START PUSHBUTTONS
STA STATION
STD STANDARD
SURF SURFACE MOUNTED
SW SWITCH
SWBD SWITCHBOARD
SYM SYMMETRICAL
SYS SYSTEM
TEL TELEPHONE
TEL/DATA TELEPHONE/DATA
TERM TERMINAL
TL TWIST LOCK
TR TAMPER RESISTANT
T-STAT THERMOSTAT
TTC TELEPHONE TERMINAL CABINET
TV TELEVISION
TVTC TELEVISION TERMINAL CABINET
TYP TYPICAL
UC UNDER COUNTER
UE UNDERGROUND ELECTRICAL
UG UNDERGROUND
UH UNIT HEATER
UT UNDERGROUND TELEPHONE
UTIL UTILITY
UV ULTRAVIOLET
V VOLT
VA VOLT-AMPERES
VDT VIDEO DISPLAY TERMINAL
VERT VERTICAL
VFD VARIABLE FREQUENCY DRIVE
VOL VOLUME
W WATT
W/ WITH
WG WIRE GUARD
WH WATER HEATER
W/O WITHOUT
WP WEATHERPROOF
XFMR TRANSFORMER
XFR TRANSFER
∠ ANGLE
@ AT
▲ DELTA
' FEET
" INCHES
# NUMBER
Ø PHASE
C CENTER LINE
P PLATE
FIRE ALARM NOTES, LEGEND
& ABBREVIATIONS
FA001
PROJECT GENERAL NOTES
1. THIS IS A LIST OF FIRE ALARM SYMBOLS AND ABBREVIATIONS FOR REFERENCE ONLY.
SYMBOLS AND ABBREVIATIONS SHOWN ON THIS DRAWING MAY NOT APPEAR ON THE
FOLLOWING DRAWINGS.
2. THE CONTRACTOR SHALL COORDINATE ALL REQUIRED SHUTDOWNS ON EXISTING
UTILITIES WITH COR DURING ALL CONSTRUCTION PHASES IN ORDER TO MINIMIZE IMPACT
TO OTHER AREAS. ENSURE ALL OTHER AREAS OUTSIDE PHARMACY SOW IS TO REMAIN
ACTIVE AND NOT DISTURBED.
3. PERFORM ALL WORK IN COMPLIANCE WITH ALL APPLICABLE FEDERAL, STATE, AND LOCAL
CODES, REGULATIONS, AND STANDARDS ADOPTED BY THE AUTHORITY HAVING
JURISDICTION. IF CONFLICTS EXIST BETWEEN THESE ENGINEERING DOCUMENTS AND
CODES, THE MOST STRINGENT REQUIREMENTS SHALL GOVERN.
4. ALL CONSTRUCTION WORK SHALL ALSO MEET THE FOLLOWING
CODE REQUIREMENTS:
- NFPA 101-2021, THE LIFE SAFETY CODE
- NFPA 70-2023, NATIONAL ELECTRICAL CODE
- NFPA 72-2022, NATIONAL FIRE ALARM CODE
5. THE FIRE ALARM DRAWINGS ARE SCHEMATIC IN NATURE. BEFORE STARTING THE WORK
THE CONTRACTOR SHALL REVIEW ALL OTHER DISCIPLINE DRAWINGS AND VERIFY FIELD
CONDITIONS AND SHALL MAKE ANY REQUIRED MINOR ADJUSTMENTS WITHOUT EXTRA
COST TO THE VA. ANY MAJOR DISCREPANCIES FOUND SHALL BE BROUGHT TO THE
ATTENTION OF THE ARCHITECT/ENGINEER.
6. ALL DEVICES, EQUIPMENT MATERIAL AND LABOR SHALL BE PROVIDED BY THE
CONTRACTOR UNLESS NOTED OTHERWISE.
7. ALL ELECTRICAL EQUIPMENT AND DEVICES SHALL BE MOUNTED AS PER EQUIPMENT AND
DEVICE MANUFACTURER RECOMMENDATIONS.
8. CONTRACTOR SHALL PROVIDE SUBMITTALS TO VA COR FOR REVIEW AND APPROVAL OF
ALL ELECTRICAL EQUIPMENT AND DEVICES DESCRIBED IN THE SUBMITTAL REGISTER.
SUBMITTALS SHALL INCLUDE CUT SHEETS, DIMENSIONS, WIRING DIAGRAMS,
ACCESSORIES, OPERATION MANUALS, AND ALL NECESSARY INFORMATION FOR
REVIEWER TO MAKE A SOUND EVALUATION.
9. PROVIDE STARTUP OF ALL FIRE ALARM SYSTEMS AND ENSURE THE VA COR IS IN
ATTENDANCE TO WITNESS THE STARTUP.
10. CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING A COMPLETE SET OF RECORD
DRAWINGS TO THE VA AT THE END OF THE CONSTRUCTION.
11. ALL MATERIALS AND EQUIPMENT TO BE INSTALLED SHALL BE NEW AND FREE OF DEFECTS.
ALL ELECTRICAL EQUIPMENT SHALL COMPLY WITH NATIONAL ELECTRICAL
MANUFACTURERS ASSOCIATION (NEMA) STANDARDS AND SHALL BE UL LABELED. ALL
ELECTRICAL EQUIPMENT AND MATERIALS SHALL BE INSTALLED IN A WORKMANLIKE
MANNER.
12. WHERE JOB CONDITIONS REQUIRE CHANGE FROM THE CONTRACT DOCUMENTS THAT DO
NOT CHANGE THE SCOPE OR NATURE OF WORK REQUIRED, THE CONTRACTOR SHALL
MAKE SUCH CHANGES WITHOUT ADDITIONAL COST TO THE VA. NO OTHER CHANGES MAY
BE MADE WITHOUT WRITTEN PERMISSION FROM THE ENGINEER.
13. CLOSE OUT DOCUMENTS: THE CONTRACTOR IS TO MAINTAIN ONE SET OF CONSTRUCTION
DRAWINGS ON SITE AND KEEP CURRENT WITH MARK UP AS-BUILT CONDITIONS DURING
CONSTRUCTION OF THE PROJECT. THIS SET IS TO INCLUDE ALL CONTRACT CHANGES,
MODIFICATIONS AND CLARIFICATIONS. THIS SET ALONG WITH ALL SHOP DRAWINGS SHALL
BE TURNED OVER TO THE ARCHITECT/ENGINEER AFTER CONSTRUCTION COMPLETION.
14. CONTRACTOR SHALL FURNISH U.L. APPROVED DRAWINGS FOR EACH TYPE OF FIRE AND
SMOKE RATED ASSEMBLY PENETRATIONS BY DUCTS, PIPES, OR CONDUITS, AND SHALL
DISPLAY THESE DRAWINGS ON THE JOB SITE AT ALL TIMES DURING CONSTRUCTION.
FIRE ALARM SYMBOLS
(MOUNTING HEIGHT TO CENTER LINE OF BOX UNLESS NOTED OTHERWISE)
FIRE ALARM STROBE LIGHT (80" AFF) (SAME AS MANUFACTURER AND MODEL
AS EXISTING DEVICES) (75 CANDELA)
FIRE ALARM SPEAKER/STROBE COMBINATION (80" AFF) (SAME AS
MANUFACTURER AND MODEL AS EXISTING DEVICES) (75 CANDELA)
FIRE DAMPER
FIRE ALARM RELAY
SMOKE DETECTOR
DUCT DETECTOR
U.S. Department of Veterans Affairs strollo & strollo 718 Virginia Drive
Orlando, FL. 32803 T: (407) 423-5355 F: (407) 422-5994
MES Group, Inc.
550 North Reo Street, Suite 203 Tampa, FL, 33609 813.289.4700 mes group
COA # 8304
SD
Fire Alarm System Input Output Matrix
*While NFPA 101 does not require some detectors to notify building occupants, VA requires all smoke detectors, other than duct smoke detectors, to notify building occupants. Only install smoke detectors when required by NFPA 101 or its references.
** Those doors that are required to be tied to the fire alarm system such as delayed egress electrical locking systems and sensor release electrical locking systems.
*** This applies to Ambulatory Health Care Occupancies that require smoke barriers per NFPA 101 or are designed with multiple smoke zones.
OUTPUT →
INPUT DEVICE
Duct Smoke Detector*
Area Smoke Detector*
XB
X
XB
X
XB
X
XB
A – Do not provide duct detectors in dedicated (100%) exhaust fans, they should continue to run. Unless otherwise noted.
B – The facility is permitted to sound the general alarm/notify necessary staff or initiate a supervisory signal to be consistent with the operation of existing systems/fire plan.
X XA
X
1.
So un d ge ne ra l b ui ld in g al ar m fo r O th er a nd N on -H ig h
R is e (n on -H ea lth
C ar
e) . S ee S ec tio n 7.
2.
2.
N ot ify n ec es sa ry s ta ff fo r re sp on se fo r H ea lth
C ar e, Am bu la to ry
H ea lth C ar e* an d
H ig h R is e bu ild in gs o nl y (a la rm s ig na l m ay b e di ffe re nt on d iff er en t f lo or s)
3.
N ot ify
F ire
D ep ar tm en t.
4.
In iti at e su pe rv is or y si gn al to a
-h ou r m an ne d po in t f or im m ed ia te re sp on se
5.
C lo se d am pe rs o n fa n pr ox im at e to d et ec to r.
6.
S hu t d ow n ai r h an dl er s er ve d by th e de te ct or
7.
O pe n lo ck ed e gr es s do or s on fl oo r o f f ire o rig in
N.T.S.D4 FIRE ALARM SYSTEM RISER
N.T.S.E4 FIRE ALARM SYSTEM INPUT AND OUTPUT MATRIX
DD
Sheet List Table Sheet Number Sheet Title
FA001 FIRE ALARM NOTES, LEGEND & ABBREVIATIONS
FA100 FIRE ALARM PLAN
FA200 FIRE ALARM PENTHOUSE PLAN
04/03/2024
WAITING AREA
CONTROL
ROOM
CLOSET
FILES
RADIOGRAPHIC
C O R R I D O R
109.86n.s.f.
100.92n.s.f.
OFFICE
BUDGET
A-160
500 n.s.f.
CARDIAC.
ROOM
A-158
OFFICE
A-159
PHYSICS
MEDICAL
163.62n.s.f.
A-158
ROOM
CONTROL
A-
8a
ST
O
31.41n.s.f.
H.A.C.
A-171
149.64n.s.f.
A-172b
TOILET
A-172 ECOCARDIO-
GRAPHY RM.
B-117 B-115
B-114
LOUNGE STAFF RM.
A-172a
LOCK RM.
ELEC.
CLOS.
MALE LOCKERS
SIGNAL
SHOWER
CLOS. FEMALE LOCKERS
PHYSICIAN'S
LOCKERS
C O
R R
I D
O R
25.58n.s.f.
25.75n.s.f.
152.44n.s.f.122.11n.s.f.
194.94n.s.f.
DN.DN.
C O R R I D O R C1-8
NO WORK IN THIS ROOM
NO WORK IN
THIS ROOM
NO WORK
IN THIS
ROOM
PANEL
1LA1C
(E)
HYBRID
OPERATING
ROOM
CONTROL
ROOM
SCRUB STN.
IMAGING
COMPONENT
ROOM
STERILE
SUPPLY
GURNEY
1 (TYP)
F
F
75cd
75cd
F 75cd
75cd
F 75cd
F75cd
F 75cd
F 75cd
F
FR
B-117a
ELECTRICAL CLOSET
U.S. Department of Veterans Affairs strollo & strollo 718 Virginia Drive
Orlando, FL. 32803 T: (407) 423-5355 F: (407) 422-5994
MES Group, Inc.
550 North Reo Street, Suite 203 Tampa, FL, 33609 813.289.4700 mes group
COA # 8304
FIRE ALARM PLAN
1/4" = 1'-0"
FA100
FIRE ALARM PLAN
FA100
KEYNOTES
1. REFER TO SHEET E501 AND E502 FOR DETAILS AND LEGEND OF
EQUIPMENT.
2. FIRE ALARM ANSUL NOTIFICATION APPLIANCE MODULE.
8.8
9.8
CBA
GENERAL NOTES
A. CONTRACTOR SHALL BE RESPONSIBLE FOR IDENTIFICATION OF ALL
RATED WALLS, CEILINGS, AND SLAB AND THEIR SPECIFIED RATING ON
THE ARCHITECTURAL DRAWINGS. ALL DEVICES AND MATERIAL SHALL
MEET THE UL RATING OF THE RATED WALL ASSEMBLY. CONTRACTOR
SHALL PROVIDE AN ASSEMBLY INSTALLED IN ACCORDANCE WITH UL FOR
THE RATED APPLICATION.
B. EXISTING CONDITIONS ARE BASED ON RECORD DOCUMENTS AND FIELD
OBSERVATION. ELECTRICAL CONTRACTOR SHALL REPORT
DISCREPANCIES TO ENGINEER PRIOR TO DISTURBING EXISTING
INSTALLATION.
C. ENSURE EXISTING FIRE ALARM RESPONSE IS COMPATIBLE WITH THE
EXISTING FIRE ALARM SYSTEM FOR ALL NEW FIRE ALARM DEVICES TO
TIE INTO CLOSEST EXISTING NOTIFICATION APPLIANCE CIRCUIT PANEL.
D. CONTRACTOR SHALL PROVIDE ALL NEW FIRE ALARM DEVICES, WIRING,
CONDUIT, ETC. FROM POINT OF CONNECTION OF NEW DEVICES TO
EXISTING NOTIFICATION APPLIANCE CIRCUIT (NAC PANEL). FIRE ALARM
CONTRACTOR SHALL PERFORM FUNCTIONAL TESTING, PROGRAMMING
AND CONNECTION OF THE NEW FIRE ALARM DEVICES AND COMPONENTS
WITHIN THE AREA OF SCOPE. ALL NEW DEVICES SHALL BE UNDER
WARRANTY SEPARATE FROM THE ORIGINAL SYSTEM.
E. PROVIDE JUNCTION BOXES, WIRE, CABLING, CONDUIT, ETC, AS
REQUIRED TO MAINTAIN CONTINUITY TO EXISTING TO REMAIN DEVICES,
FIXTURES, EQUIPMENT, ETC.
F. MAGNETIC LOCKS SHALL BE CONNECTED TO THE FIRE ALARM SYSTEM
THROUGH A SET OF NORMALLY CLOSED, DRY CONTACTS SUPPLIED BY
FIRE ALARM CONTRACTOR.
G. DOOR HARDWARE SHALL BE COORDINATED WITH FIRE ALARM SYSTEM
TO DISENGAGE UPON FIRE ALARM SYSTEM ACTIVATION. COORDINATE
FINAL LOCATION OF CONDUIT AND JUNCTION BOXES WITH SUCCESSFUL
DOOR SECURITY HARDWARE PROVIDER PRIOR TO CONSTRUCTION.
H. GC TO ENGAGE SERVICES OF VA'S FIRE ALARM MAINTENANCE
CONTRACTOR TO PERFORM DEVICE TERMINATIONS, PROGRAMMING
CHANGES AND TESTING. IF THE VA DOES NOT HAVE A CURRENT SERVICE
CONTRACTOR, GC SHALL ENGAGE SERVICES FROM ENTITY CERTIFIED
BY MANUFACTURER AND ACCEPTABLE TO THE VA.
I. ENSURE ALL FIRE ALARM CONDUIT, JUNCTION BOXES, ETC. ARE PAINTED
RED. ALL CONDUIT IS TO BE LABELED EVERY 10 FEET POINTING
TOWARDS THE FACP. ALL JUNCTION BOXES ARE TO BE LABELED TO
THEIR CONTENTS (SLC OR NAC, ETC.).
F G H J K
P-2
P-1
10.1
STAIR # 1
UP. DN.
P-3
P-4
9.4
8.9
S-5 S-6 S-7
NL M
DN.
5.9
STAIR # 2
SERV. ELEV.
LOBBY
ROOM
A-309-X
ROOM
B-340-X
F G H J K NL MFE
DD DD
COORDINATION NOTE:
PENTHOUSE IS AN ENCLOSED
AREA FROM ELEMENTS.
U.S. Department of Veterans Affairs strollo & strollo 718 Virginia Drive
Orlando, FL. 32803 T: (407) 423-5355 F: (407) 422-5994
MES Group, Inc.
550 North Reo Street, Suite 203 Tampa, FL, 33609 813.289.4700 mes group
COA # 8304
FIRE ALARM PENTHOUSE PLAN
1/8" = 1'-0"
FA200
FIRE ALARM PENTHOUSE
PLAN
FA200
KEYNOTES
1. CONTRACTOR SHALL COORDINATE ALL CONDUIT RUNS IN FIELD. ALL
CONDUIT SHALL BE CEILING SUSPENDED OR WALL MOUNTED. NO
CONDUIT SHALL RUN ALONG THE FLOOR.
2. FIRE ALARM CONTRACTOR SHALL COORDINATE WITH HVAC CONTROLS
CONTRACTOR TO ENSURE THAT AIR MOVING DEVICES SHUT DOWN IN
THE EVENT OF ACTIVATION OF INITIATION DEVICES. GENERAL
CONTRACTOR SHALL INCLUDE IN BID ALL PROGRAMMING, TESTING,
HARDWARE AND DEVICES NEEDED TO ACHIEVE A FULLY FUNCTIONAL
SYSTEM.
GENERAL NOTES
A. CONTRACTOR SHALL BE RESPONSIBLE FOR IDENTIFICATION OF ALL
RATED WALLS, CEILINGS, AND SLAB AND THEIR SPECIFIED RATING ON
THE ARCHITECTURAL DRAWINGS. ALL DEVICES AND MATERIAL SHALL
MEET THE UL RATING OF THE RATED WALL ASSEMBLY. CONTRACTOR
SHALL PROVIDE AN ASSEMBLY INSTALLED IN ACCORDANCE WITH UL FOR
THE RATED APPLICATION.
B. EXISTING CONDITIONS ARE BASED ON RECORD DOCUMENTS AND FIELD
OBSERVATION. ELECTRICAL CONTRACTOR SHALL REPORT
DISCREPANCIES TO ENGINEER PRIOR TO DISTURBING EXISTING
INSTALLATION.
C. ENSURE EXISTING FIRE ALARM RESPONSE IS COMPATIBLE WITH THE
EXISTING FIRE ALARM SYSTEM FOR ALL NEW FIRE ALARM DEVICES TO
TIE INTO CLOSEST EXISTING NOTIFICATION APPLIANCE CIRCUIT PANEL.
D. CONTRACTOR SHALL PROVIDE ALL NEW FIRE ALARM DEVICES, WIRING,
CONDUIT, ETC. FROM POINT OF CONNECTION OF NEW DEVICES TO
EXISTING NOTIFICATION APPLIANCE CIRCUIT (NAC PANEL). FIRE ALARM
CONTRACTOR SHALL PERFORM FUNCTIONAL TESTING, PROGRAMMING
AND CONNECTION OF THE NEW FIRE ALARM DEVICES AND COMPONENTS
WITHIN THE AREA OF SCOPE. ALL NEW DEVICES SHALL BE UNDER
WARRANTY SEPARATE FROM THE ORIGINAL SYSTEM.
E. PROVIDE JUNCTION BOXES, WIRE, CABLING, CONDUIT, ETC, AS
REQUIRED TO MAINTAIN CONTINUITY TO EXISTING TO REMAIN DEVICES,
FIXTURES, EQUIPMENT, ETC.
F. GC TO ENGAGE SERVICES OF VA'S FIRE ALARM MAINTENANCE
CONTRACTOR TO PERFORM DEVICE TERMINATIONS, PROGRAMMING
CHANGES AND TESTING. IF THE VA DOES NOT HAVE A CURRENT SERVICE
CONTRACTOR, GC SHALL ENGAGE SERVICES FROM ENTITY CERTIFIED
BY MANUFACTURER AND ACCEPTABLE TO THE VA.
G. ENSURE ALL FIRE ALARM CONDUIT, JUNCTION BOXES, ETC. ARE PAINTED
RED. ALL CONDUIT IS TO BE LABELED EVERY 10 FEET POINTING
TOWARDS THE FACP. ALL JUNCTION BOXES ARE TO BE LABELED TO
THEIR CONTENTS (SLC OR NAC, ETC.).