This document is an Amendment (0001) to Solicitation 36C24825R0026 for the construction of a new Hybrid Operating Room at the VA Caribbean Healthcare System in San Juan, Puerto Rico. The amendment provides responses to 23 request for information (RFI) items covering critical project details such as work hours (recommended 6:00 a.m. to 4:00 p.m.), asbestos removal specifications (approximately 2,200 sq. ft. of ceiling fireproofing and 2,000 sq. ft. of vinyl floor tiles), temporary facility logistics, and contractor requirements. Key contractor obligations include providing a dedicated Project Superintendent with hospital/clinic construction experience, a Site Safety Health Officer, obtaining necessary permits for asbestos abatement, and submitting detailed plans for equipment rigging and movement.
The RFI responses address technical, logistical, and operational aspects of the project, including equipment placement, HEPA filtration solutions, temporary exhaust systems, parking arrangements, and crane pick locations. The VA will provide limited temporary storage space for materials used within a two-week period and potentially a dumpster location. Contractors must comply with specific requirements such as using manual punch code locks for construction access doors, coordinating with existing facility operations, and following VA specifications for plumbing fixtures, HVAC design, and construction processes. The amendment also includes attachments such as a site visit sign-in sheet, rigging plan, and additional specification documents.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0001 36C24825R0026
Amendment 0001
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
672-CSI-124
36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) VA Caribbean HCS (Admin Bldg) #10 Calle Casia Suite #4M440 San Juan PR 00921-3201
36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8) VA Caribbean HCS (Admin Bldg) #10 Calle Casia Suite #4M440 San Juan PR 00921-3201 To all Offerors/Bidders
X
Project Title: Construct New Hybrid Operating Room (Construction Services)
The purpose of this amendment is to respond to RFIs and provide a copy of the site visit sign-in sheet.
All offerors are required to acknowledge receipt of this amendment. RFIs/Questions due date has closed.
See continuation page for RFI responses.
Ana G. Alvarado Contracting Officer
NCO815L3-0313
CONTINUATION PAGE
AMENDMENT 0001 36C24825R0026 – RFIs responses:
| # |
| RFIs/QUESTIONS |
| VA RESPONSES |
| 1. |
| Please advise which is the minimum hourly rate for the construction workers. |
| The offeror should contact the Department of Labor for labor rates related questions. |
| 2. |
| Please provide the location for the Contractor’s temporary facilities (storage trailer, office, dumpster) |
| Due to the high volume of projects currently underway at the facilities, we do not have available staying area for office trailers and storage. However, during the construction process, we could designate a temporary space to store the materials that will be used within a two-week period, as well as a temporary space to install a dumpster if such a requirement is needed. |
| 3. |
| If the temporary exhaust air system could not be directed outdoors due to the existing conditions, please advise if the HEPA-filtered air could be directed into an existing exhaust system. |
| Yes, HEPA Filtrated Air equipment could be tie in into the existing ductwork distribution as a Temporary solution to be in compliance with the room pressurization during the construction process, and compliance with the ICRA permits. |
| 4. |
| As per work statement section 3-3.6, the work is to be performed on night shifts, weekends or out of the regular hours of operation of the Outpatient Clinic. As per specification 01 00 00-1.2-F, the normal working hours for this contract will be from 7:30am to 5:00pm. Please advise. |
| The recommended schedule is from 6:00 a.m. to 4:00 p.m. (AST), but it is necessary and flexible to operate at any other time as needed, based on the contractor’s recommendations, to minimize the impact on adjacent areas due to noise, equipment movement, or waste disposal. |
| 5. |
| As per Specification 02 82 11, section 1.1.2 (extent of work), item B indicates the following: Removal, clean-up and disposal of asbestos containing materials (ACM) and asbestos/waste contaminated elements in the project work area, for the following approximate quantities: 2,200 s.f. area above ceilings, pipe insulation |
| Contractors must remove, clean-up and disposal of asbestos containing materials (ACM). |
| 6. |
| a. Please provide the quantities for each ACM to be removed (fireproofing, hvac duct sealant, insulation, etc) for the proposed 1st floor work and basement structural improvement work. |
b. According to what was discussed in the pre-auction, it was indicated that asbestos and lead must be removed, we want to know if the Owner has the report or if the Contractor should carry out the study.
fireproofing friable 2,200 sq. ft.(ceiling), non-friable floor tile vinyl 2,000 sq. ft. ) duct mastic and pipe insulation must be assumed by lineal ft.
· Room A164: Door, Sink, Sink Drain pipe, Sink Water Pipe, Sink Support Frame, Drain Cap, Bathroom Door, toilet, Door frame, lavatory drain pipe, lavatory faucet, lavatory, toilet water valve,
· Room A165: door frame, door,
· Room A166a: Lavatory Water Valves, Lavatory water valve
· Room A166b: Lavatory Water Valves,
· Room A166d: Lavatory Drain Pipe, Lavatory Water valve
· Room A166e: Lavatory Water valve,
· Room A166f:Lavatory faucet, Lavatory water valve, toilet water valve
· Room A167: Sink faucet, sink, Sink drain pipe, Sink water valve, drain cap, door, lavatory drain pipe, toilet water valve, lavatory water valve
Continuation of RFI #6 VA response:
| 7. |
| If the existing fireproofing will be part of the ACM abatement, new fireproofing must be applied to replace the existing fireproofing? If yes, please provide fireproofing specifications. |
| Construction Specification 02-08-11. See attached Specification 02 82 11 Abatement Final. |
| 8. |
| Drawing AQ-100 included the equipment schedule identifying with equipment to be CC and VC. There is some equipment that does not have the ACQ/INS information. Please advise. |
| These equipment’s will be provided by VA. See attached AQ-100 Arch PR VA Hybrid OR 100 Percent Final S-S. |
| 9. |
| Please provide the make and model for plumbing fixture P-519. |
| Drawing AQ-100, Equipment’s must comply with the VA Specifications, 22-40-00. |
Continuation of RFI#9 VA response:
| 10. |
| As per drawing G-004 – during construction project note 9 indicates to see the plans for proposed location of HEPA Exhaust. We could not find the proposed location for the temporary exhaust fan. Please advise. |
| HEPA Filtrated Air equipment should be tie in into the near existing exhaust ductwork distribution. |
| 11. |
| What will be the working hours for noisy demolitions? |
| The recommended schedule is from 6:00 a.m. to 4:00 p.m., but it is necessary and flexible to operate at any other time as needed, based on the contractor’s recommendations, to minimize the impact on adjacent areas due to noise, equipment movement, or waste disposal. |
| 12. |
| To lift the equipment to the Penthouse we will need a crane. To use such crane, will Contractor need to require a test boring study? |
| The contractor is responsible for reviewing all structural studies, site conditions, and necessary coordination to ensure that the equipment can be safely lifted to the penthouse. Prior to any equipment movement, the contractor must submit a detailed rigging plan for VA approval. No equipment shall be moved until this plan has been reviewed and approved by the VA .I’m not certain if a boring study is required for this specific task, but, if necessary, the contractor should take it into consideration and include it in their planning and submittals. |
| 13. |
| Please indicate if Contractor will have access to cargo elevator to lift materials? |
| Yes, the cargo could be available as long they are operational. |
| 14. |
| Please indicate what staging area will be designated for Contractor use. |
| Due to the high volume of projects currently underway at the facilities, we do not have available staying area for office trailers and storage. However, during the construction process, we could designate a temporary space to store the materials that will be used within a two-week period, as well as a temporary space to install a dumpster if such a requirement is needed. |
| 15. |
| Will the owner provide designated parking for employees working on the project? |
| There are no Contractor/contractor’s employee reserved parking spaces. Contractor/contractor’s employee may use any available parking space in the adjacent surround areas (legal parking space). Government will not be responsible for any contractor’s Privately Owned Vehicle (POV) for damage or lost. Parking in “no parking” areas or “reserved” spots could result in a ticket being issued and/or vehicle being towed away. |
| 16. |
| After reviewing the specifications downloaded from sam.gov we did not find the following sections. Please advise or send specs. a. Section 01 42 19 Reference Standard, b. Section 10 44 13 Fire Extinguisher Cabinets |
| Attached are specs 04 42 19, and 10 44 13. |
| 17. |
| Will a permit be required to abate the asbestos? |
| The contractor needs to provide all the required certifications and permits required by the law. |
| 18. |
| Must the Project Superintendent be on site at all times and be employed directly by the Prime Contractor? |
| Yes. The contractor shall designate a dedicated Project Superintendent to manage and oversee all |
construction activities for this project. The Project Superintendent shall have proved experience in construction projects of similar or major complexity to this one in an active hospital/clinic environment (Refer to SOW page 18, paragraph 3.2. Refer to FAR clause 52.236-6. Superintendence by the Contractor www.acquisition.gov/far/52.236-6.
| 19. |
| Must the Site Safety Health Officer be on site at all times and be employed directly by the Prime Contractor? |
| Yes. |
| 20. |
| Can the VA provide a detail for the ductwork going up elevator shaft for the air handlers (stainless steel from operating room to hepa filters) |
| Refer to the VA HVAC Design Manual and construction specs. |
| 21. |
| Can all temporary construction doors accessing construction work zones from the existing hospital be equipped with Manual punch code locks vs card reader security pads? |
| No. |
| 22. |
| Will the VA provide an acceptable laydown area for materials, storage containers, and equipment for the contractors outside? Please provide the possible locations. |
| Due to the high volume of projects currently underway at the facilities, we do not have available staying area for office trailers and storage. However, during the construction process, we could designate a temporary space to store the materials that will be used within a two-week period, as well as a temporary space to install a dumpster if such a requirement is needed. |
| 23. |
| Can the VA provide the designated Crane Pick Locations? |
| 2 locations that will go into the penthouse. See attached “rigging plan” for a copy of below image. |
Continuation of RFI #23 response:
See attached documents:
S06 - Amendment 0001 Attachment - Rigging Plan - 1 Page.
S06 - Amendment 0001 Attachment - Specification 01 42 19 - 9 pages.
S06 - Amendment 0001 Attachment - Specification 10 44 13 - 2 pages.
S06 - Amendment 0001 Attachment - 02 82 11 Abatement FINAL - 1 page.
S06 - Amendment 0001 Attachment - AQ-100 Arch PR VA Hybrid OR 100 Percent Final S-S - 1 page.
S06 - Amendment 0001 Attachment - Site Visit sign-in sheet 4-21-2025 - 36C24825R0026 BB 672-CSI-124 Hybrid OR.
This amendment 0001 to solicitation 36C24825R0026 is to respond to RFIs/Questions and provide a copy of the site visit sign-in sheet. RFIs/Questions due date has closed.
image2.png image3.png image4.png image1.png
File details come from the government source that posted it. Updated .