This document is a Schedule of Items for a federal contract opportunity to provide professional water system operation and maintenance services for eleven water systems owned by the USDA Forest Service, Pike and San Isabel National Forests, Cimarron and Comanche National Grasslands (PSICC). The contract includes a base year from January to December 2025, with four one-year option periods through December 2029. The contractor must have a minimum level "B" water treatment license and level "1" distribution license valid for the contract duration in Colorado. The contract covers operation and maintenance of both non-community and transient non-community public and administrative water systems, which must comply with Colorado drinking water regulations. The Schedule of Items lists the various water system locations and associated monthly operational costs for both the first and second halves of each month. It also includes optional items for filters, water quality testing, water hauling, and storage tank inspections.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base

Item 0001 - Base Year - Mandatory Items
Item No.DescriptionMethod of MeasurementUnitQtyUnit PriceTotal
0001AMonument Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
0001BMonument Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
0001CLake George Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
0001DLake George Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
0001EEleven Mile Canyon DwellingWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
0001FEleven Mile Canyon DwellingWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
0001GLake Isabel Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
0001HLake Isabel Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
0001ICarrizo Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
0001JCarrizo Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
0001KAG RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
0001LAG RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
0001MCrystal Lakes Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
0001NCrystal Lakes Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
0001OBrown House Cystal LakesWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
0001PBrown House Cystal LakesWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
0001QIndian Creek Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
0001RIndian Creek Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach7$0.00
0001SBassam Guard StationONE MONTH of water system operation at the Bassam Guard StationEach7$0.00
0001TRourke RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach8$0.00
0001URourke RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach8$0.00
Base Year - Optional Items
Optional Items - FiltersUnitQtyUnit PriceTotal
0002Pre FilterSTC3-30NNEach1$0.00
0003Final FilterCartridge Filter (1.0 micron)Each1$0.00
0004KDFEach1$0.00
0005Green SandsEach1$0.00
0006CarbonEach1$0.00
0007QCREach1$0.00
Optional Items - Water Quality Testing
0008Total ColiformSM 9223Each1$0.00
0009NitrateEPA 300.0Each1$0.00
0010NitriteEPA 300.0Each1$0.00
0011Lead and CopperEPA 200.8Each1$0.00
0012Langelier IndexSM 2330-BEach1$0.00
0013MPAMicroparticulate AnalysisEach1$0.00
0014PFASPFOA, PFOS, PFHxS, PFNA, PFBS, GenXEach1$0.00
Optional Items - Water Hauling
0015Troubleshooting MobilizationMiles1$0.00
0016Troubleshooting LaborHours1$0.00
0017Supplying Potable Water3000 gallonsEach1$0.00
Optional Items - Storage Tank Inspections
00018Storage Tank InspectionEach1$0.00

Total: $0.00

OY1

Item 1000 - Option Year 1 - Mandatory Items
Item No.DescriptionMethod of MeasurementUnitQtyUnit PriceTotal
1000AMonument Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
1000BMonument Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
1000CLake George Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
1000DLake George Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
1000EEleven Mile Canyon DwellingWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
1000FEleven Mile Canyon DwellingWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
1000GLake Isabel Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
1000HLake Isabel Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
1000ICarrizo Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
1000JCarrizo Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
1000KAG RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
1000LAG RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
1000MCrystal Lakes Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
1000NCrystal Lakes Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
1000OBrown House Cystal LakesWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
1000PBrown House Cystal LakesWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
1000QIndian Creek Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
1000RIndian Creek Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach7$0.00
1000SBassam Guard StationONE MONTH of water system operation at the Bassam Guard StationEach7$0.00
1000TRourke RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach8$0.00
1000URourke RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach8$0.00
Option Year 1 - Optional Items
Optional Items - FiltersUnitQtyUnit PriceTotal
1001Pre FilterSTC3-30NNEach1$0.00
1002Final FilterCartridge Filter (1.0 micron)Each1$0.00
1003KDFEach1$0.00
1004Green SandsEach1$0.00
1005CarbonEach1$0.00
1006QCREach1$0.00
Optional Items - Water Quality Testing
1007Total ColiformSM 9223Each1$0.00
1008NitrateEPA 300.0Each1$0.00
1009NitriteEPA 300.0Each1$0.00
1010Lead and CopperEPA 200.8Each1$0.00
1011Langelier IndexSM 2330-BEach1$0.00
1012MPAMicroparticulate AnalysisEach1$0.00
1013PFASPFOA, PFOS, PFHxS, PFNA, PFBS, GenXEach1$0.00
Optional Items - Water Hauling
1014Troubleshooting MobilizationMiles1$0.00
1015Troubleshooting LaborHours1$0.00
1016Supplying Potable Water3000 gallonsEach1$0.00
Optional Items - Storage Tank Inspections
1017Storage Tank InspectionEach1$0.00

Total: $0.00

OY2

Item 2000 - Option Year 2 - Mandatory Items
Item No.DescriptionMethod of MeasurementUnitQtyUnit PriceTotal
2000AMonument Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
2000BMonument Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
2000CLake George Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
2000DLake George Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
2000EEleven Mile Canyon DwellingWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
2000FEleven Mile Canyon DwellingWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
2000GLake Isabel Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
2000HLake Isabel Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
2000ICarrizo Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
2000JCarrizo Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
2000KAG RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
2000LAG RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
2000MCrystal Lakes Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
2000NCrystal Lakes Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
2000OBrown House Cystal LakesWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
2000PBrown House Cystal LakesWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
2000QIndian Creek Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
2000RIndian Creek Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach7$0.00
2000SBassam Guard StationONE MONTH of water system operation at the Bassam Guard StationEach7$0.00
2000TRourke RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach8$0.00
2000URourke RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach8$0.00
Option Year 2 - Optional Items
Optional Items - FiltersUnitQtyUnit PriceTotal
2001Pre FilterSTC3-30NNEach1$0.00
2002Final FilterCartridge Filter (1.0 micron)Each1$0.00
2003KDFEach1$0.00
2004Green SandsEach1$0.00
2005CarbonEach1$0.00
2006QCREach1$0.00
Optional Items - Water Quality Testing
2007Total ColiformSM 9223Each1$0.00
2008NitrateEPA 300.0Each1$0.00
2009NitriteEPA 300.0Each1$0.00
2010Lead and CopperEPA 200.8Each1$0.00
2011Langelier IndexSM 2330-BEach1$0.00
2012MPAMicroparticulate AnalysisEach1$0.00
2013PFASPFOA, PFOS, PFHxS, PFNA, PFBS, GenXEach1$0.00
Optional Items - Water Hauling
2014Troubleshooting MobilizationMiles1$0.00
2015Troubleshooting LaborHours1$0.00
2016Supplying Potable Water3000 gallonsEach1$0.00
Optional Items - Storage Tank Inspections
2017Storage Tank InspectionEach1$0.00

Total: $0.00

OY3

Item 3000 - Option Year 3 - Mandatory Items
Item No.DescriptionMethod of MeasurementUnitQtyUnit PriceTotal
3000AMonument Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
3000BMonument Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
3000CLake George Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
3000DLake George Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
3000EEleven Mile Canyon DwellingWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
3000FEleven Mile Canyon DwellingWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
3000GLake Isabel Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
3000HLake Isabel Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
3000ICarrizo Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
3000JCarrizo Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
3000KAG RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
3000LAG RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
3000MCrystal Lakes Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
3000NCrystal Lakes Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
3000OBrown House Cystal LakesWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
3000PBrown House Cystal LakesWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
3000QIndian Creek Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
3000RIndian Creek Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach7$0.00
3000SBassam Guard StationONE MONTH of water system operation at the Bassam Guard StationEach7$0.00
3000TRourke RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach8$0.00
3000URourke RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach8$0.00
Option Year 3 - Optional Items
Optional Items - FiltersUnitQtyUnit PriceTotal
3001Pre FilterSTC3-30NNEach1$0.00
3002Final FilterCartridge Filter (1.0 micron)Each1$0.00
3003KDFEach1$0.00
3004Green SandsEach1$0.00
3005CarbonEach1$0.00
3006QCREach1$0.00
Optional Items - Water Quality Testing
3007Total ColiformSM 9223Each1$0.00
3008NitrateEPA 300.0Each1$0.00
3009NitriteEPA 300.0Each1$0.00
3010Lead and CopperEPA 200.8Each1$0.00
3011Langelier IndexSM 2330-BEach1$0.00
3012MPAMicroparticulate AnalysisEach1$0.00
3013PFASPFOA, PFOS, PFHxS, PFNA, PFBS, GenXEach1$0.00
Optional Items - Water Hauling
3014Troubleshooting MobilizationMiles1$0.00
3015Troubleshooting LaborHours1$0.00
3016Supplying Potable Water3000 gallonsEach1$0.00
Optional Items - Storage Tank Inspections
3017Storage Tank InspectionEach1$0.00

Total: $0.00

OY4

Item 4000 - Option Year 4 - Mandatory Items
Item No.DescriptionMethod of MeasurementUnitQtyUnit PriceTotal
4000AMonument Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
4000BMonument Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
4000CLake George Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
4000DLake George Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
4000EEleven Mile Canyon DwellingWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
4000FEleven Mile Canyon DwellingWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
4000GLake Isabel Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
4000HLake Isabel Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
4000ICarrizo Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
4000JCarrizo Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
4000KAG RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
4000LAG RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
4000MCrystal Lakes Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
4000NCrystal Lakes Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
4000OBrown House Cystal LakesWater System Operation Cost for the FIRST 15 calendar days of the monthEach12$0.00
4000PBrown House Cystal LakesWater System Operation Cost for the SECOND 15 calendar days of the monthEach12$0.00
4000QIndian Creek Work CenterWater System Operation Cost for the FIRST 15 calendar days of the monthEach7$0.00
4000RIndian Creek Work CenterWater System Operation Cost for the SECOND 15 calendar days of the monthEach7$0.00
4000SBassam Guard StationONE MONTH of water system operation at the Bassam Guard StationEach7$0.00
4000TRourke RanchWater System Operation Cost for the FIRST 15 calendar days of the monthEach8$0.00
4000URourke RanchWater System Operation Cost for the SECOND 15 calendar days of the monthEach8$0.00
Optional Items
Optional Items - FiltersUnitQtyUnit PriceTotal
4001Pre FilterSTC3-30NNEach1$0.00
4002Final FilterCartridge Filter (1.0 micron)Each1$0.00
4003KDFEach1$0.00
4004Green SandsEach1$0.00
4005CarbonEach1$0.00
4006QCREach1$0.00
Optional Items - Water Quality Testing
4007Total ColiformSM 9223Each1$0.00
4008NitrateEPA 300.0Each1$0.00
4009NitriteEPA 300.0Each1$0.00
4010Lead and CopperEPA 200.8Each1$0.00
4011Langelier IndexSM 2330-BEach1$0.00
4012MPAMicroparticulate AnalysisEach1$0.00
4013PFASPFOA, PFOS, PFHxS, PFNA, PFBS, GenXEach1$0.00
Optional Items - Water Hauling
4014Troubleshooting MobilizationMiles1$0.00
4015Troubleshooting LaborHours1$0.00
4016Supplying Potable Water3000 gallonsEach1$0.00
Optional Items - Storage Tank Inspections
4017Storage Tank InspectionEach1$0.00

Total: $0.00

Total Bid Price

Base Price$0.00
OY1 Price$0.00
OY2 Price$0.00
OY3 Price$0.00
OY4 Price$0.00
Total Bid Price:$0.00

File details come from the government source that posted it. Updated .