Attachment 0003_Schedule B Bid Schedule_Final.xlsx
XLSX spreadsheet 13 KB Posted
- Solicitation number
- W912HY24B0021
About this file
This document appears to be the Attachment 0003_Schedule B Bid Schedule from a Request for Proposal (RFP) for the Sabine-Neches Waterway Channel Improvement Project (SNWWCIP) in Jefferson County, Texas. The RFP is being issued by the U.S. Army Corps of Engineers, Galveston District.
The Bid Schedule provides a format for bidders to submit pricing and technical details related to the dredging work. Key details include the expected period of performance, average production rates, dredge information, labor requirements, equipment (booster pumps, tugs, scows), and any subcontractors. Bidders are required to provide unit pricing for general items such as fuel and profit, as well as specific details for each dredge to be utilized. The pre-solicitation indicates that a pre-bid conference will be held on June 28, 2024, and all questions must be submitted by June 27, 2024.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Project Title: |
| Contract Number: |
| U.S. Army Corps of Engineers, Galveston District |
| Schedule B |
| General Items | |||||
| Item # | Description | Quantity | Unit | Unit Rate | Total |
| B.1 | Fuel (Total for Contract) | Gal | $ - 0 | $ - 0 | |
| B.2 | Profit (Total for Contract) | % | $ - 0 | ||
| B.3 | Expected Period of Performance | Calendar Days | |||
| B.4 | Average Expected Production Rate | CY/Day |
| Dredge 1 (Repeat per Dredge) | |||
| Item # | Description | Unit | Total |
| B.5 | Dredge | Name | |
| B.6 | Average Expected Operating Cost | $/Day | |
| B.7 | Average Expected Standby Cost | $/Day | |
| Mobilization and Demobilization | |||
| B.8 | Mobilization Distance | mi | |
| B.9 | Demobilization Distance | mi | |
| B.10 | Tug(s) in Transit (if any) | Tug(s) | |
| B.11 | Barge(s) in Transit (if any) | Barge(s) | |
| Labor | |||
| B.12 | Crew Size per Shift | Crewmates | |
| B.13 | Shift Schedule | Shifts x Hours per Shift | |
| Equipment | |||
| B.14 | Number of Booster(s) (if any) | Booster(s) | |
| B.15 | Disposal Tug(s) (if any) | Tug(s) | |
| B.16 | Disposal Scow(s) (if any) | Scow(s) |
| Subcontractor 1 (Repeat Per Subcontractor) | ||
| Item # | Description | Response |
| B.17 | Subcontractor | |
| B.18 | Work Performed by Subcontractor |
| Dredge 2 (Repeat per Dredge) | |||
| Item # | Description | Unit | Total |
| B.5 | Dredge | Name | |
| B.6 | Average Expected Operating Cost | $/Day | |
| B.7 | Average Expected Standby Cost | $/Day | |
| Mobilization and Demobilization | |||
| B.8 | Mobilization Distance | mi | |
| B.9 | Demobilization Distance | mi | |
| B.10 | Tug(s) in Transit (if any) | Tug(s) | |
| B.11 | Barge(s) in Transit (if any) | Barge(s) | |
| Labor | |||
| B.12 | Crew Size per Shift | Crewmates | |
| B.13 | Shift Schedule | Shifts x Hours per Shift | |
| Equipment | |||
| B.14 | Number of Booster(s) (if any) | Booster(s) | |
| B.15 | Disposal Tug(s) (if any) | Tug(s) | |
| B.16 | Disposal Scow(s) (if any) | Scow(s) |
| Subcontractor 2 (Repeat Per Subcontractor) | ||
| Item # | Description | Response |
| B.17 | Subcontractor | Name? |
| B.18 | Work Performed by Subcontractor | % |
File details come from the government source that posted it. Updated .