About this file
This solicitation is for a sewer replacement project located at the Bridgeport Ranger District Administration Site in Mono County, California. The project includes reconstructing the entire onsite wastewater system through installing new sewer lines, cleanouts, manholes, RV sewer connections, septic tanks, absorption fields, and an aggregate access road. Additionally, an existing packaged sewage treatment system and steel building will be removed along with other existing sewer system components. The estimated price for the project is between $250,000 and $500,000. The solicitation was issued by the US Department of Agriculture Forest Service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BridgeportSewer.SOI_082021.xlsx | XLSX spreadsheet | |
| Copy of BridgeportSewer.SOI_082021.xlsx | XLSX spreadsheet | |
| Amendment 3.pdf | ||
| BridgeportSewer-2019_Plans_Rev1_08.09.2021.pdf | ||
| BridgeportSewer.SOI.Rev1-08.09.2021.xlsx | XLSX spreadsheet | |
| Amendment 2.pdf | ||
| RFIBridgeportSewer072621.pdf | ||
| ProfilePercs.pdf | ||
| Amendment 1.pdf | ||
| ATTACH 3_EngineeringReport_BridgeportSewer_09.24.2020.pdf | ||
| ATTACH 1_BridgeportSewer_Specs_Final_09.23.2020.pdf | ||
| ATTACH 4_WAGE DETERMINATION.pdf | ||
| 1240LR21R0007.pdf | ||
| Attach_5_Determination of Responsibility.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTES:
EXISTING ELECTRICAL
SERVICE
1. 4 CIRCUIT PANEL (SQUARE D, QO TYPE, LOAD CENTER) HAS 100 AMP
FOR FEEDING SEWAGE TREATMENT BUILDING AND 30 AMP FOR SURGE
ARRESTOR.
2. INSTALL NEW FEEDER TO PACKAGED LIFT STATION AND THEN REMOVE
FEEDER TO SEWAGE TREATMENT BUILDING TO LIMIT DISRUPTION OF
SERVICE TO SITE.
DOUBLE THROW DISCONNECT
".ii b co
UNISTRUT SUPPORT
(TYPICAL OF 5)
2-1/2" GALVANIZED STEEL
POST (TYPICAL)
LIFT STATION CONTROL MOUNTING DETAIL
REPLACE 100 AMP BREAKER SERVING SEWAGE
TREATMENT BUILDING IN EXISTING SQUARE D
PANEL WITH NEW 00230 AMP BREAKER WITH
NEW UNDERGROUND FEEDER TO NEW LIFT
STATION CONTROLS. LOCATION OF CONTROLS
MAY VARY, AND THOUGH NEXT TO LIFT STATION,
SHALL BE FAR ENOUGH AWAY TO ALLOW PULLING
OF PUMPS AND OTHER MAINTENANCE WORK.
SZ 1C,3#8&1#8GND.
BURY 24" MINIMUM
DOUBLE THROW SAFETY SWITCH,
3-POLE, NON-FUSIBLE, WITH
GROUND, SEIMENS GNF322RA.
LABELS "ELECTRIC FEEDER",
"GENERATOR", "WARNING - DO
NOT SWITCH UNDER LOAD"
,-;:;---7
I I I L2 I
I I I L1
I I I I
N I I L--...J"":"'=-i-
---'---'--1 _____ __
SZ 0.5C,3#10&1#10GND.
SZ 0.5C,3#10&1#10GND.
S/N
GRD BAR
1#6 GND.
GROUND, SEE
SPECIFICATIONS
CAB LE STORAGE NOTES
1. INSTALL THE SYSTEM AS SHOWN ON THIS DRAWING AND
ACCORDING TO THE SPECIFICATIONS.
2.
3.
4.
THE STRAIN RELIEF (HUBBELL "I-GRIP" TYPE) SHALL BE SIZED
FOR AND INSTALLED ON THE FLEXIBLE CABLE. MOUNT TO
PREVENT STRAIN ON THE CABLE TERMINATIONS WHEN CABLE
IS FULLY EXTENDED OUT OF THE BOX, TO THE BACK INSIDE OF
THE CABLE STORAGE BOX SO AS TO EXTEND 1 "-2" FROM THE
EXIT POINT DESCRIBED ABOVE.
LABEL BOX "GENERATOR CONNECTION, 30 AMP 240/120VAC,
3.125 KVA MINIMUM (MAY REQUIRE 5 KVA IF CHEAP GENERATOR
IS USED)."
THE FLEXIBLE CABLE SHALL EXTEND 6' MINIMUM BEYOND THE
EXIT POINT DESCRIBED ABOVE, OF TYPE W, STOOW, SOOW, OR
SEOOW.
LIFT STATION PANEL, SQUARED
[QO612L 100RB AND PK?GTA
GROUND BAR]
CKT1,2 CKT3
00220 00115
SZ 0.5C,2#12&1#12GND.
CABLE STORAGE BOX HOFFMAN NEMA 3R HINGED
COVER ENCLOSURE #A10R106HCR W/ SQUARE D
CLASS 9080 #LBA361101 AND LBA161101 POWER
DISTRIBUTION BLOCKS AND LB13 AND LB11
COVERS; AND HUBBELL "I-GRIP" STRAIN RELIEF
ATTACHED TO BOX INTERIOR TO PREVENT CORD
STRAIN TO TERMINAL BLOCK.
SZ 0.5C,2#14&1#14GND.
iii>
#10/3 W/GND FLEXIBLE CABLE
WITH STRAIN RELIEF (SEE
CABLE STORAGE NOTES),
TERMINATE CABLE WITH 30
AMP, 3-POLE, 4-WIRE, NEMA
L 14-30P TWISTLOCK PLUG
ONE-LINE SCHEMATIC
LIFT STATION CONTROLS,
SEE SPECIFICATIONS
FOR PACKAGED LIFT
STATION
GFCI
RECEPTACLE
United States Department of Agriculture Forest Service
REGION4
INTERMOUNTAIN REGION
STAMPS, LOGOS, AND SEALS
APPROVED:
DIRECTOR OF ENGINEERING
NO. REVISION/ ISSUE
PROJECT NAME
DATE
DATE
BRIDGEPORT
SEWER SYSTEM
REPLACEMENT
PROJECT
HUMBOLDT-TOIYABE
NATIONAL FOREST
BRIDGEPORT DISTRICT
DRAWING TITLE
ELECTRICAL
DATE
I
ARCHIVE NO.
DESIGNER
S.BROWN
DRAWN
S.BROWN
CHECKED
D.JEPPSEN
PROJECT NO.
DRAWING SHEET NO.
E-1
SHEET 22 OF 22
| BridgeportSewer_Elec-Electrical.pdf |
| Sheets and Views |
| Electrical |
| 2020-10-30T10:45:45-0700 | |
| KENDAL YOUNG |
| 2020-11-02T16:01:11-0700 | |
| CHRISTOPHER CAMPBELL |
| 2020-11-02T16:01:40-0700 | |
| CHRISTOPHER CAMPBELL |
File details come from the government source that posted it. Updated .