ATTACH 1_BridgeportSewer_Specs_Final_09.23.2020.pdf

PDF 2 MB Posted

Attached to
Bridgeport Sewer Replacement Federal contract opportunity
Solicitation number
1240LR21R0007
Issued by
Department of Agriculture Forest Service

About this file

This document is a solicitation for a sewer replacement project located on the Bridgeport Ranger District of the Humboldt-Toiyabe National Forest in Mono County, California. The project includes reconstructing the entire onsite wastewater system for a Forest Service administrative site housing employees. Key work includes installing new sewer lines, cleanouts, manholes, and RV sewer connections; new septic tanks and absorption fields; a new packaged effluent lift station; a new aggregate access road; removing an existing packaged sewage treatment system and steel building; and removing existing sewer system components. The estimated price for the project is between $250,000 and $500,000. The solicitation is being conducted by the Department of Agriculture Forest Service.

View the file

Other files for this federal contract opportunity

Other files attached to Bridgeport Sewer Replacement, newest first.
File Type Posted
BridgeportSewer.SOI_082021.xlsx XLSX spreadsheet
Copy of BridgeportSewer.SOI_082021.xlsx XLSX spreadsheet
Amendment 3.pdf PDF
BridgeportSewer-2019_Plans_Rev1_08.09.2021.pdf PDF
BridgeportSewer.SOI.Rev1-08.09.2021.xlsx XLSX spreadsheet
Amendment 2.pdf PDF
RFIBridgeportSewer072621.pdf PDF
ProfilePercs.pdf PDF
Amendment 1.pdf PDF
ATTACH 3_EngineeringReport_BridgeportSewer_09.24.2020.pdf PDF
ATTACH 4_WAGE DETERMINATION.pdf PDF
1240LR21R0007.pdf PDF
ATTACH 2_BridgeportSewer-2019_Plans_Signed_10.14.2020.pdf PDF
Attach_5_Determination of Responsibility.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

BRIDGEPORT SEWER REPLACEMENT PROJECT

1.1 SCOPE OF CONTRACT

A. This project includes reconstructing the entire onsite wastewater system for a Forest Service administrative site. The site is primarily employee housing and includes both single family homes, bunkhouses and RV pads.

B. The work includes:

1. Installing new sewerlines, cleanouts, manholes and RV sewer connections.

2. Installing new septic tanks and absorption fields.

3. Installing a new packaged effluent lift station

4. Installing a new aggregate access road.

5. Removing an existing packaged sewage treatment system and steel building.

6. Removing existing sewer system components, including manholes, cleanouts, and holding tanks.

7. Repairing existing aggregate roadways.

1.2 PROJECT LOCATION

A. The project is located in the Bridgeport Ranger District of the Humboldt-Toiyabe National Forest, Mono County, California, in Section 23, T 5 N, R 24 E. It is located approximately 4 miles west of Bridgeport, California, at the Bridgeport Ranger District Administration Site. The project may be accessed from US Highway 395.

1.3 GENERAL SITE CONDITIONS AND WEATHER

A. The elevation of the site is approximately 6575 feet above mean sea level. The construction site experiences typical weather for valleys in the high desert along the east side of the Sierra Nevada range. Moderate snowfall and extremely cold temperatures occur during the winter months. The ground is typically snow-free from April through October though isolated snowfall could occur most any month other than July and August. Summer temperatures rarely exceed 95 degrees, and daytime winter highs can stay below 0 degrees.

B. In-depth soil surveys have not been performed with the exception of test pits located at the leach field location. Rocks at the ground surface, and from past excavation work, are evident throughout the area. The Contractor should expect to encounter large rocks during excavation and grubbing operations, but not bedrock. Blasting of rocks will not be permitted without special permission.

ATTACHMENT #1 1240LR21R0007

C. In-depth water table surveys have not been performed; however, if water is encountered during excavation, the Contractor shall perform adequate dewatering to keep the excavation free from water and dispose of the water without damage to property.

1.4 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. However, Contractor's use of premises is limited to the extent that the work is within a functioning warehouse and residential setting and must remain open for that use. Portions of the site with active work may be cordoned off for construction purposes so long as regular functions of the site are able to continue. Contractor's use of premises is limited by the Government's right to perform work or to retain other contractors on portions of Project.

2. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees. Road closures will be permitted, when required, upon written approval of the Contracting Officer (CO). Short duration closures of plumbed facilities will be permitted, when required, upon written approval of the Contracting Officer (CO). Such closures should be timed to have the least impact on site operations.

3. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.

4. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

a. Provide temporary barriers to protect existing trees and plants and root zones.

b. Do not remove, injure, or destroy trees or other plants without prior approval.

Consult with CO and remove agreed-on roots and branches that interfere with construction.

c. Do not fasten ropes, cables, or guys to existing trees.

d. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

5. Contractor will provide all materials and labor necessary to protect streams, wet or dry, during construction activities. The Contractor will be required to submit a stream protection plan and receive approval from the COR, in writing, prior to the beginning of construction.

6. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

7. Existing Utilities: Notify CO and utility companies of proposed locations and times for excavation.

a. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

b. Interruption of Existing Utility Service: Notify CO, 48 hours in advance of any interruption of existing utilities.

8. Water is available at the site for construction purposes.

9. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.

1.5 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and California Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

1.6 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO.

B. With approval by the CO and the Bridgeport Ranger District, National Forest Service lands may be used by the Contractor to have one fully contained recreation vehicle which may remain at this site for security subject to availability

1. Approval for use is subject to availability after Forest Service employee housing needs are met.

1.7 CONSTRUCTION SEQUENCE

A. There is no specified construction sequence or season for this project.

B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.

1.8 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.9 FIELD VERIFICATION

A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.

1.10 PERMITS

A. The Forest Service will obtain a permit for construction of an onsite wastewater treatment system (OWTS) from Mono County Health Department. Other special permits for electrical work or any other permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.

1.11 ESTIMATED START DATE

A. August 30, 2021

1.12 CONTRACT TIME

A. 90 Calendar Days

1.13 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

Section 010250 - Construction Staking Section 011250 - Measurement And Payment Section 011500 - Archeological Protection Section 011900 - Mobilization Section 014100 - Quality Control Section 013300 - Submittal Procedures Section 017820 - Operation And Maintenance Data Section 022350 - Area Rehabilitation Section 022210 - Building Demolition Section 023701 - Sediment And Erosion Control Measures Section 024100 - Waste Material Disposal Section 033010 - Cast-In-Place Concrete (Limited Applications) Section 033540 - Concrete Sidewalk Section 221100 - Water Distribution Systems Section 221102 - Curb Valves And Boxes Section 221104 - Equipment Labeling For Water And Wastewater Systems Section 221105 - Water Hydrants Section 221300 - Onsite Wastewater Treatment Systems Section 260500 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260526 - Grounding And Bonding For Electrical Systems

Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 262726 - Wiring Devices Section 311000 - Clearing And Grubbing Section 312000 - Earthwork Section 312010 - Select Borrow Section 312225 - Excavation & Embankment Section 312100 - Project Site Preparation And Grading Section 321204 - Crushed Aggregate Base Or Surface Course Section 329206 - Seeding Section 330530 - Utility Locating System

END OF SECTION C

July 2021

USDA FOREST SERVICE, R4

SECTION 010250 - CONSTRUCTION STAKING

PART 1 - GENERAL

1.1 SUMMARY

A. This work shall consist of the construction staking of utilities, structures, and appurtenances in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.

1.2 QUALITY CONTROL

A. Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.

1.3 MEASUREMENT AND PAYMENT

A. Measurement shall be lump sum for surveying and staking the project through all phases of construction.

PART 2 - PRODUCTS

2.1 GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS

A. The Project Drawings include sufficient information on benchmark locations, planned utility line elevations, and necessary locations referenced off existing features. No other survey control is anticipated to be needed for this project. Meeting existing field conditions is of primary concern. Minor survey variations to meet field conditions are anticipated, but must be approved by the CO before construction.

1. Benchmarks shown have been created and used in prior surveys, but may no longer be present and undamaged. Verify all found benchmarks for horizontal and vertical accuracy.

a. To assist with benchmark verification, suggested check points are provided that are easily found, repeatable points. All are suggested for confirming horizontal accuracy. Manhole lids may have been adjusted for grade and are not advised for vertical accuracy checks.

2. A "best fit" of all reliable benchmarks and checkpoints will be considered suitable for a project coordinate system. For each found point, provide to the contracting officer:

a. The actual and calculated coordinates, and

b. The bearing and distance between the actual and calculated coordinates.

3. Continue with construction point stakeout only after approval of the coordinate system by the contracting officer.

2.2 STAKES

A. Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:

1. Roads, parking lots, and driveways -Yellow

2. Sewer lines, manholes, and cleanouts -Green

3. Electrical and other utilities -Orange

4. Control -Pink

2.3 SURVEY NOTE PAPER AND BOOKS

A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract.

The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.

B. Accuracy requirements:

1. Minimum position close; 1/1000

2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)

3. Cross section and slope stake precision:

a. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.

b. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross section points will not exceed: 1.0 ft.

c. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%. Clearing limits: 1.0 ft.

3.2 ESTABLISHING AND REFERENCING IMPROVEMENT LOCATIONS

A. Roads and Parking lots:

1. Pavement cut limits shall be established on both sides of the pipe centerline at each station established. Stake references shall be located on a line at right angles to tangents and on radial lines or curves. Cut limits shall be located by using the pipeline grades and typical trench cross-sections as shown on the drawings and the information provided with staking points.

2. Cut limit stakes shall be set at each end of cut and wherever cut alignment changes.

Paint matching the stake color may be substituted for stakes on paved surfaces subject to traffic.

B. Waterline, Sewerline, & other Utilities

1. Waterline, Sewerline, & other Utilities shall be staked at the locations shown on the drawings with the specified minimum burial depth. Waterline and sewerline elevations shall be accurately staked to provide for drainage as indicated on the drawings. Grade stakes shall be established as necessary to provide the control for the construction work.

3.3 DISCREPANCIES

A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.

B. Discovered variations in existing utility depth and location which require change in proposed pipeline or fixture grades shall be referred to the Contracting Officer along with new grades and locations proposed by the contractor. Staking of these areas shall be deferred until the Contacting Officer approves the changes.

3.4 VERTICAL CONTROL

A. Vertical control for construction shall be as referenced on the Drawings.

3.5 MARKING STAKES

A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;

PI Point of Intersection of tangents PC Point of curvature POC Point on curve Pt Point of tangency POT Point on tangent RP Reference point P P-line (preliminary location line) L L-line (final location line) BM Bench mark TBM Temporary bench mark BT Begin taper (any) ET End taper (any) C Cut F Fill L Centerline D Ditch W Width

3.6 SURVEY NOTES

A. All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.

B. Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey was performed, and survey data or sketched that cannot be electronically recorded. The party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.

END OF SECTION 010250

July 2021

SECTION 011250 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

1.2 DETERMINATION OF QUANTITIES

A. The following measurements and calculations shall be used to determine contract quantities for payment.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

1. Acre: Make longitudinal and transverse measurements for area computations horizontally.

2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.

3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

4. Cubic Yard (CY): A measurement computed by one of the following methods:

a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

5. Each (EA): One complete unit, which may consist of one or more parts.

6. Gallons (GAL): The quantity shall be measured by any of the following methods:

a. Measured volume in container.

b. Metered volume by approved metering system.

c. Commercially package volume.

7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

8. Linear Foot (LF): Measurement of work along its length from point-to-point;

parallel to the base or foundation. Do not measure overlaps.

9. Lump Sum (LS): One complete unit.

10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

12. Square Foot (SF): Measured on a plane parallel to the surface being measured.

13. Square Yard (SY): Measured on a plane parallel to the surface being measured.

14. Ton: Measured as a short ton consisting of 2,000 pounds.

1.4 METHOD OF MEASUREMENT

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.

5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

July 2021

SECTION 011500 - ARCHEOLOGICAL PROTECTION

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of protecting archeological resources contained in soil deposits.

1.2 DEFINITIONS

A. Resources: Prehistoric, historic, and recent 20th century artifacts, including charcoal, human bones, ash, fire rocks, and building materials that indicate the presence of past human occupation.

B. Archeologically Sensitive Areas: Areas that have been determined to contain significant in-the-ground archeological resources.

C. Nonsensitive Areas: Areas that have a low likelihood of containing significant in-the-ground archeological resources.

D. Archeological Monitor: Representative of the Government designated to record and collect cultural resources for compliance with Government regulations to protect in-the-ground resources.

1.3 SUBMITTALS

A. As specified in Section 013300 “Submittal Procedures.”

B. 14 days before start of ground-disturbing site work, submit a Daily Work Schedule, detailing construction work in archeologically sensitive areas. Key schedule to drawings and include the following information.

1. Starting and ending dates of ground-disturbing construction.

2. Locations of temporary facilities, such as barriers, field offices, staging areas, sanitary facilities, borrow pits, and haul and access roads.

3. Types of construction, such as clearing, topsoil stripping, structure of trench excavation, landscaping, and post construction clean up.

4. Methods and equipment used for each type of construction.

5. Plan for relocating work in the event of temporary work stoppages at each archeologically sensitive area.

1.4 QUALITY ASSURANCE

A. At least one week before on-site work begins, Contractor shall meet with Contracting Officer (CO) and Archeological Monitor to discuss Daily Work Schedule and equipment and special methods to be used in archeologically sensitive areas. Contractor shall ensure that approved Daily Work Schedule is followed throughout construction.

PART 2 - EXECUTION

2.1 BARRICADES

A. Construct as specified in Section C “Statement of Work.” Locate as directed by CO.

2.2 OBSERVATION

A. Archeological Monitor will observe all ground-disturbing site work, including construction of temporary facilities, at all archeologically sensitive areas, from a safe location mutually agreed on by Contractor and Monitor. As new ground is broken, Monitor will examine excavated materials, using construction layout centerline and perimeter staking as a reference point to record locations of findings.

2.3 DISCOVERY OF RESOURCES

A. If Archeological Monitor discovers resources, immediate relocation of the work to a nonsensitive area may be required to allow Monitor to take soil samples and record resources. While Archeological Monitor is documenting resources in sensitive areas, Contractor shall relocate work to nonsensitive areas where monitoring is not normally required.

B. If resources are discovered while Archeological Monitor is absent, stop work immediately and report the discovery to the Contracting Officer.

2.4 WORK STOPPAGE

A. The Contractor shall plan, schedule, and execute the work to prevent stoppage at one area from stopping all work at the construction site.

END OF SECTION 011500

July 2021

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

July 2021

SECTION 014100 - QUALITY CONTROL

PART 1 - GENERAL

1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.

1.2 QUALITY CONTROL

A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.

B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:

1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.

2. Testing agency will re-test and re-inspect corrected work.

C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.

1.3 SUBMITTALS

A. Contractor Quality Control Plan

B. Permits, Licenses, and Certificates

C. Test and Inspection Reports

D. As-Built Drawings

1.4 MEASUREMENT AND PAYMENT

A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 QUALITY CONTROL SYSTEM

A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.

3.2 CONTRACTOR QUALITY CONTROL PLAN

A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.

1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.

2. The Government reserves the right to require changes in the plan during the contract period as necessary.

3. No change in the approved plan may be made without written concurrence by the Contracting Officer.

4. At a minimum, the plan shall include the following:

a. A list of personnel responsible for quality control and assigned duties.

Include each person's qualifications.

b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.

c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

d. Methods of performing, documenting, and enforcing quality control of all work.

e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.

3.3 TEST AND INSPECTION REPORTS

A. Submit three copies of complete test results no later than three calendar days after the test was performed.

B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.

C. Testing and Inspection Reports shall include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples, tests, or inspections.

5. Names of individuals performing tests and inspections.

6. Reference Specification Section(s).

7. Complete test or inspection data.

8. Test and inspection results and an interpretation of test results.

9. Ambient conditions at time sample was taken, tested, or inspected.

10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.

11. Name and signature of laboratory inspector.

12. Recommendations on retesting and reinspecting.

3.4 PERMITS, LICENSES, AND CERTIFICATES

A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the performance of the work.

3.5 AS-BUILT DRAWINGS

A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.

These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. The location of existing underground utilities and structures discovered during the course of the work shall be indicated in red or another contrasting color on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.

3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS

A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:

TABLE 014100-1

Item

Subsection Certification or Test Required

Frequency 033010 3.9 Concrete – Slump, Air, Temperature 1 composite first 9 cy, 1 per 25 cy after 033010 3.9 Concrete - Compression Test

Specimens (at 7 and 28 days) 1 set first 9 cy, 1 per

25 cy after 221100 3.2N HDPE Pipe - Bent Strap Test Once Daily 221100 3.4A Pressure and Leakage Test – Water

Line See Spec.

221100 3.5A Bacteriological Examination After disinfection, before use

221300 3.14B Gravity Line Hydrostatic Test Prior to Backfill 221300 3.15A Pressure Line Hydrostatic Test Until Passing 221300 3.16B Structure Leakage Test Until Passing 221300 3.16C Pump Test Until Passing

TABLE 014100-1

Item

Subsection Certification or Test Required

Frequency 221300 3.12D Balance Test See Spec.

221300 3.12E System Test See Spec.

312000 3.14C Compaction Test – at Pipe Zone One per 300 feet of trench 312000 3.14C Compaction Test – at Pipe Zone One test – at each road crossing 312000 3.14D Compaction Test – above Pipe

Zone One every other lift per 300 ft of trench

312000 3.17A Compaction Test – Backfill/Fills One per Tank, Util-ity Building or Util-ity Box 312000 3.21C Compaction Test – Backfill/Fills and Subgrade under Buildings and Driveways

One test every 1000

sq. yd. area per lift and at Subgrade 312225 1.3B Moisture-Density Relationship One Test for Each

Soil Type Encoun-tered

312225 3.12B Compaction – Road Embankment (Method 4)

One test every 300

sq. yd. of embank-ment per lift 312225 3.12B Compaction – Subgrade One test every 1000

sq. yd. of subgrade 321204 3.4A Compaction Tests – Road Base and

Surface Course One test for every

300 sq. yd. of aggregate

330530 4.1A Tracing Verification Testing Until passing

END OF SECTION 014100

July 2021

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.

B. See other specification section within this package for additional requirements on submittal.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Notation of dimensions established by field measurement.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 days of commencement of work, and 14 days before the start of ground disturbing activities in archeologically sensitive areas.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.

Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project - the table is to assist the Contractor and may not be all inclusive

– additional submittals may be required by specific specifications:

TABLE 013000-1

Spec.

Section Section Title

Sub-sec-tion

Required Submittal

C General Specifications 1.3A Stream Protection Plan C General Specifications 1.4A Traffic Control Plan

010250 Construction Staking 2.1 A Control Coordinate System 010250 Construction Staking 3.6 A Survey Notes 013300 Submittal Procedures 2.1D Construction Schedule 014100 Quality Control 1.3 A Contractor quality control plan 014100 Quality Control 1.3 B Permits, Licenses, and Certificates 014100 Quality Control 1.3 C Test and inspection reports 014100 Quality Control 1.3 D As-Built drawings 017820 Operation and Maintenance Data 1.2 A O&M Manuals 023701 Sediment & Erosion Control

Measures 1.2A Sediment & Erosion Control Plan

033010 Cast-in-Place Concrete 1.3B Product Data 033010 Cast-in-Place Concrete 1.3C Design Mix 221100 Water Distribution Systems 1.3A Product Data 221100 Water Distribution Systems 1.3B Water Disposal Plan 221100 Water Distribution Systems 1.3C Operation and Maintenance Data 221105 Water Hydrants 1.3A Manufacturer’s Literature and

Maintenance Data 221105 Water Hydrants 1.3B Washed Rock Certification 221105 Water Hydrants 1.3C Maintenance Data 221300 Onsite Wastewater Treatment System 1.3A Product Data 221300 Onsite Wastewater Treatment System 1.3B Shop Drawings 221300 Onsite Wastewater Treatment System 1.3C Coordination Drawings 221300 Onsite Wastewater Treatment System 1.3D O&M Data 221300 Onsite Wastewater Treatment System 1.3E Certificates 260500 Common Work Results for Electrical 1.2A Product Data 260533 Raceway and Boxes for Electrical

Systems 1.3A Product Data

312000 Earthwork 1.3A Aggregate and Backfill Sources 312000 Earthwork 1.3A Sieve Analysis 312000 Earthwork 1.3B Product Data 312225 Excavation and Embankment 1.3A Density Test Results 321204 Crushed Aggregate Base or Surface

Course 1.2A Aggregate Base – Source, Gradation 321204 Crushed Aggregate Base or Surface

Course 1.2B Compaction Test Results and Proctor 321204 Crushed Aggregate Base or Surface

Course 1.2C Aggregate Base – Material

Properties

END OF SECTION 013300

July 2021

SECTION 017820 - OPERATION AND MAINTENANCE DATA

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for preparing operation and maintenance manuals, including the following:

1. Emergency manuals.

2. Operation manuals for systems, subsystems, and equipment.

3. Maintenance manuals for the care and maintenance of products, materials, finishes systems and equipment.

B. Related Sections include the following:

1. Divisions 2 through 33: Sections for specific operation and maintenance manual requirements for products in those sections.

1.2 SUBMITTALS

A. Manual: Submit two of each manual in final form at least 15 days before final inspection.

Contracting Officer (CO) will return copy with comments within 15 days after final inspection.

1. Correct or modify each manual to comply with CO’s comments. Submit 3 copies of each corrected manual within 15 days of receipt of CO’s comments.

1.3 DEFINITIONS

A. System: An organized collection of parts. Equipment, or subsystems united by regular interaction.

B. Subsystem: A portion of a system with characteristics similar to a system.

PART 2 - PRODUCTS

2.1 MANUALS, GENERAL

A. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain a title page, table of contents, and manual contents.

B. Title Page: Enclose title page in transparent plastic sleeve. Include the following information:

1. Subject matter included in manual.

2. Name and address of Project.

3. Name and address of District or Forest.

4. Date of submittal.

5. Name, address, and telephone number of Contractor.

C. Table of Contents: List each product included in manual, identified by product name, indexed to content of volume, and cross-referenced to Specification Section number in Project Manual.

D. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.

1. Binders: Heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch (115-by-280-

mm) paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.

a. Identify each…