Attach 16_Preaward Survey.pdf

PDF 148 KB Posted

Attached to
TH-1H Depot Level Maintenance Federal contract opportunity
Solicitation number
FA8552-24-R-0001
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

This document is a pre-award survey checklist for a prospective contractor's accounting system. It contains 22 questions for the contractor to answer regarding its accounting practices and compliance with Cost Accounting Standards and Generally Accepted Accounting Principles. The questions address topics such as whether the contractor's accounting system has been audited by the Defense Contract Audit Agency, whether it properly segregates direct and indirect costs and charges labor to appropriate cost objectives, and whether it can provide necessary cost data and financial information for cost reimbursement contracts. The contractor must provide explanatory narratives for its responses. This checklist appears to be a template used by government agencies to evaluate a contractor's accounting system for cost reimbursement contracts prior to award.

View the file

Other files for this federal contract opportunity

Other files attached to TH-1H Depot Level Maintenance, newest first.
File Type Posted
Attach 04_Sections LandM Provisions_Rev3.pdf PDF
RFP Amendment FA855224R0001-0003.pdf PDF
Attach 04_Sections LandM Provisions_Rev2.pdf PDF
Attach 01_PerformanceWorkStatment_Rev1.pdf PDF
RFP Amendment FA855224R0001-0002.pdf PDF
Consolidated QA_FA855224R0001 (16Nov23).pdf PDF
Attach 08_Past Performance QuestionnaireRev1.pdf PDF
RFP Amendment FA855224R0001-0001.pdf PDF
Attach 12_Client Authorization LetterRev1.pdf PDF
Attach 04_Sections LandM ProvisionsRev1.pdf PDF
Attach 10_Transmittal LetterRev1.pdf PDF
Attach 06_Engineering Scenarios.pdf PDF
Attach 08_Past Performance Questionnaire.pdf PDF
Attach 11_Subcontractor Consent Form.pdf PDF
Attach 12_Client Authorization Letter.pdf PDF
Attach 15_TH-1H Price Matrix.xlsx XLSX spreadsheet
Attach 03_CDRLs.pdf PDF
Attach 04_Sections LandM Provisions.pdf PDF
Attach 09_Relevancy Table.pdf PDF
Attach 18_Transportation Requirements.pdf PDF
Attach 02_PDM Work Specification.pdf PDF
RFP FA855224R0001.pdf PDF
Attach 07_FACTS Sheet.pdf PDF
Attach 10_Transmittal Letter.pdf PDF
Attach 17_Packaging Requirements.pdf PDF
Attach 19_GFP Attachment.pdf PDF
Attach 01_Performance Work Statement.pdf PDF
Attach 05_Cross-Reference Matrix.pdf PDF
Attach 13_Subcontractor Committment Form.pdf PDF
Attach 14_Labor Categories Description.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-AWARD SURVEY OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM CHECKLIST

PRE-AWARD SURVEY OF PROSPECTIVE CONTRACTOR ACCOUNTING SYSTEM

Date:

Company Name, Contract Number, and Full Address:

Commercial and Government Agency (CAGE) Code

Number: (Found at https://cage.dla.mil/)

Cognizant Defense Contract Audit Agency (DCAA) office info (Address/phone number/E-mail) -

(Found at http://www.dcaa.mil/Home/Locator)

Company Point of Contact:

(Name, Title, Phone Number, and E-mail address

If the accounting books and records are located at a physical address other than the address provided above, please indicate address here:

Name, Title, and signature of Company Principal (President/VP/Controller, etc) responsible for the design of the Accounting System.

NAME

TITLE

E-MAIL ADDRESS

SIGNATURE DATE

PLEASE ANSWER THE QUESTIONS BELOW:

HAVE YOU READ THE REQUIREMENTS IN THE SF1408? (YES/NO)

HAVE YOU READ THE DCAA PUBLICATION DCAAM 7641.90 - "Information for Contractors"

DCAA'S WEBSITE at http:www.dcaa.mil/? (YES/NO)

For each question, check only one box. ALL questions must have explanatory narrative text entered in the boxes. Please provide sufficient detail to describe the process (Including Account Numbers/Process Flow etc.) Each Question must be complete. Do NOT refer to previous answers, (i.e. "See Question 3 Above").

http://www.dcaa.mil/Home/Locator) http://www.dcaa.mil/

Pre-award Survey of Prospective Contractor Accounting System Checklist

1. Has your organization's Accounting System ever been audited by DCAA?

YES (if Yes, the Offeror should attach a copy of their most recent DCAA audit report to this Modified Pre-Award Survey) or provide the DCAA Report number or DCAA POC info.

NO (if NO, answer N/A to Questions 1.A., 1.B., and 1.C. below)

1.A. If the answer is "Yes" to Question 1 above, when was the audit performed?

Within the past Year

Within the past 3 Years

Greater than 3 Years (PROVIDE THE YEAR THE AUDIT WAS PERFORMED HERE - ).

N/A (Answer to Question 1 is NO)

1.B. If the answer is "Yes" to Question 1 above, did DCAA determine the Accounting System acceptable for award of prospective contracts?

YES

NO (If NO provide an explanation in the box below)

1.C. If the answer is "Yes" to Question 1 above, have there been any changes to the Accounting System since the DCAA audit?

YES (If YES, describe the changes in the box below

NO

2. Is your organization subject to CAS (48 CFR Chapter 99)?

YES (If YES, is it FULL or MODIFIED CAS?) FULL MODIFIED

(If YES (FULL or MODIFIED), the Offeror MUST attach a copy of their most recent audit reports/documentation regarding all CAS compliance or non-compliance issues to this Modified Pre-Award Survey)

NO (If NO provide an explanation in the box below why your organization is exempt and answer N/A to Questions 2.A., 2.B., and 2.C. below)

2.A. Has your organization submitted a CASB disclosure statement (CASB DS-1) to DCAA and has it been determined adequate?

YES (If YES, provide an explanation that validates your answer in the box below)

N/A (Answer to Question 2 is NO)

2.B. Has your organization been notified by DCAA that it is (or may be in) non-compliance with its disclosure statement or CAS?

N/A (N/A, if the answer to Question 2 is NO)

2.c. Is any aspect of this proposal inconsistent with your organization’s disclosed practices or applicable CAS?

N/A (N/A, if the answer to Question 2 is NO or if you have no current, active proposal being considered)

Instruction: If the Contractor is planning on bidding on Cost Type Contracts, the contractor MUST provide explanatory narrative for all of the following questions:

3. Has your organization's Accounting System been audited by an outside Certified Public Accountant/Consultant or other Cognizant

Federal Agency other than DCAA?

YES (If YES, the Offeror MUST attach a copy of their most recent audit report to this Modified Pre-Award Survey) NOTE: Do not submit your

Annual Financial Audit.

4. Is your organization's Accounting System currently in full operation?

YES (If YES, provide an explanation that validates your answer in the box below).

NO (If NO, provide an explanation in the box below which portions are (1) in operation, (2) set up, but not yet in operation, (3) anticipated, or (4) non-existent)

N/A (If N/A, provide an explanation in the box below)

5. Is your organization's Accounting System in accord with Generally Accepted Accounting Principles (GAAP) Applicable in the

Circumstances?

YES (If YES, provide an explanation that validates your answer in the box below)

N/A (N/A, provide an explanation in the box below)

6. Is your organization's Accounting System ready for a DCAA audit?

NO (If NO provide an explanation in the box below as to when you will be ready for an audit)

7. Are the loaded hourly labor rates proposed consistent with your established estimating and accounting principles and procedures and

FAR Part 31, Cost Principles? (Answer this Questions "N/A" if you do not have an active proposal)

8. Does the Accounting System provide for the proper segregation of Direct Costs from Indirect Costs?

9. Does the Accounting System provide for the identification and accumulation of Direct Costs by contract?

10. Does the Accounting System provide for a logical and consistent method for the allocation of Indirect Costs to intermediate and final cost objectives? (A contract is a final cost objective.)

YES (If YES, provide an explanation that validates your answer in the box below)

11. Does the Accounting System Provide for the accumulation of costs under general ledger control?

12. Does the Accounting System provide for a timekeeping system that identifies employees' labor by intermediate or final cost objectives?

13. Does the Accounting System provide for a labor distribution system that charges Direct and Indirect labor to the appropriate cost objectives?

YES (If YES, provide an explanation that validates your answer in the box below)

14. Does the Accounting System provide for an interim (at least monthly) determination of costs charged to a contract through routine posting of books of account?

YES (If YES, provide an explanation that validates your answer in the box below)

15. Does the Accounting System provide for an exclusion of costs charged to government contracts of amounts which are not allowable in terms of FAR 31, Contract Cost Principles and Procedures, or other contract provisions?

YES (If YES, provide an explanation that validates your answer in the box below)

16. Does the Accounting System provide for the identification of costs by contract line item and by units (as if each unit or line item were a separate contract) if required by the proposed contract?

YES (If YES, provide an explanation that validates your answer in the box below)

17. Does the Accounting System provide for the segregation of preproduction costs from production costs?

18. Does the Accounting System provide financial information required by contract clauses concerning limitation of cost (FAR 52.232.20) or limitation on payments (FAR 52.216-16)?

YES (If YES, provide an explanation that validates your answer in the box below)

19. Does the Accounting System provide financial information required to support requests for Progress Payments?

20. Is the Accounting System designed, and are the records maintained, in such manner that adequate, reliable data are developed for use in pricing follow-on acquisitions?

21. Is your organization planning on submitting proposals on Cost-Type (FAR 16.3) contracts/task orders?

22. Is your organization currently performing on Cost-Type (FAR 16.3) contracts/task orders?

N/A