Attach 1_SOW 85240 (16-1149A) Rev 3.pdf
PDF 293 KB Posted
- Solicitation number
- FA461024R0007
About this file
This solicitation is seeking proposals for a project to repair and upgrade the driveway and parking lot at Breakers located at XUMU. Key details include:
-
The project has a period of performance of 183 calendar days and is valued between $500,000 and $1,000,000. Proposals are due by 30 July 2024. The NAICS code is 238990 with a size standard of $19 million.
-
A pre-proposal site visit will take place on 7 March 2024. All requests for information must be submitted by 12 March 2024. Funds are not presently available and no award will be made until funding is secured.
-
This opportunity is set aside for total small businesses in accordance with FAR 19.805-1(b)(2). The issuing agency is the Department of the Air Force Space Command. The solicitation number is FA461024R0007.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) Rev 3 Project # / Title: XUMU 16-1149A, Repair/Upgrade Driveway and Parking Lot at Breakers Fac# / Project Location: 85240 Revised Date: 4 Feb 2024
1.0 INTRODUCTION:
1.1 This project is located off Oregon Avenue on L Street, Breakers Parking Lot, Vandenberg SFB, California.
1.2 The Contractor shall furnish all materials, equipment, labor, and personnel necessary to plan, design, manage, and perform service as required, in accomplishing the task order in accordance with the contract requirements as defined below. A complete and usable product shall be provided to the Government upon completion.
1.3 Under the scope of this requirement, the service of a registered architect or engineer will not be required. However, in accordance with contractual documents, the offeror shall provide detailed documentation to substantiate the proposed approach for the task required. Proposal documentation shall provide enough detail to verify the line-item quantities in the offeror cost proposal are accurate and reasonable detail to clearly convey what the Government will be receiving. All construction approaches shall clearly illustrate compliance with the latest local, state, and federal building guides and construction codes.
1.4 After completion of the initial project site visit or project effort validation; the offeror shall continue to conduct further research and field investigation prior to preparing a complete and usable construction approach for the effort described in this document and all attachments.
1.5 The repair and overlay effort shall comply with the latest Vandenberg SFB Facilities Excellence Standards requirement which can be found at https://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/vandenberg-afb-ifs.
2.0 BASIS OF DESIGN:
2.1 Provide a double seal coat or overlay in the areas indicated on the attached Site Plan. Herbicide shall be applied in accordance with the Statement of Work in all areas requiring a double seal coat or overlay. Seal all cracks greater than 1/4 inch and provide repairs to failed areas with pavement sections shown on the attached Site Plan. Prior to placing asphalt and base course in failed areas 12 inches below finished subgrade shall be recompacted to 95 percent of maximum density. The main entrance road, running between the parking areas, as well as the roundabout, is underbuilt for the trucks that bring food to the facility. This section shall be reconstructed with 8” of base course and 4” asphalt. Along with the paving effort, existing planters and walkways in the parking lot will be removed to add more parking space. The lines need to be restriped IAW Site Map.
3.0 SCOPE OF WORK / GENERAL DESCRIPTION OF PROJECT:
3.1 The contractor shall provide shop drawings before mobilization.
3.2 The Contractor shall herbicide (with both a pre-emergent and post-emergent herbicide) one foot beyond the edges of pavement and cracks prior to any asphalt repairs. Parking Lot #1 (UM) is roughly 81,630 square feet (9,070 square yards) plus the plant and curb area of 3630 square yards for a total of 12,700 square yards; the roadway and turnaround (UM) are roughly 14,400 https://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/vandenberg-afb-ifs.
https://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/vandenberg-afb-ifs.
square feet (1600 square yards). The Contractor shall validate all measurements. After two weeks all weeds and plant debris shall be cleared and removed. Pavement cracks shall be routed and cleaned out and filled with hot asphalt crack sealant prior to application of the double seal coat.
3.3 The existing planters/curbs and walkways in the parking lot will be removed to add more parking space.
3.4 Contractor shall properly rout, and seal all cracks greater than ¼ inch wide throughout the entire parking lot. Once all cracks have been sealed with hot asphalt sealant, power sweeping and cleaning of pavement surface is imperative to remove all dirt and debris prior to asphalt repairs and double seal coating application. The following are required product and specification (or equal):
1) Proposed Double (2) Seal Coat Product # Product Specification Specification # 1002 Ace Seal Parking / Storage Areas Seal Coat 37-4
2) Description: Ace Seal is an asphalt product combining selected fillers and suitable additives with emulsified asphalt. Ace Seal contains no coal tar and is therefore, acceptable on school playgrounds and tennis courts as well as any off highway asphalt surface.
3) Surface Preparation: The surface to be sealed should be properly repaired before being sealed. Any places where the asphalt does not have good structural integrity should be saw-cut out and replaced before it is sealed. Sealer is not designed to increase the structural characteristics of the asphalt. New asphalt surfaces should be allowed to cure a minimum of seven days before application, three to six months is recommended. Surface must be clean and free from all loose material, so that the sealer can adhere to the asphalt surface.
4) Mixing: Normally 20 to 30 percent water is needed in the first coat and 20 to 25 percent in the second coat. A good mixer is required to mix the sealer thoroughly after water is added to ensure a consistent concentration before applying. The amount of water needed will vary depending on the temperature of the pavement and the temperature and humidity of the air. There should be enough water added so that the sealer will flow into the pavement and give good adhesion. Dilute the concentrated Ace Seal with water as required to achieve ease of application. Ace Seal already contains 3 pounds per gallon of ground slate aggregate to achieve a non-skid surface. Up to three pounds of additional aggregate per gallon of undiluted sealer can be added; (Refer to Technical Bulletin #1243 for mixing instructions).
5) Suggested Mixing:
Coat Sealer Water Aggregate* Polymer Modifier 1st Coat 100 gallons 20-30 gallons 100-300 lbs. 1-3 gallons 2nd Coat 100 gallons 20-25 gallons None None
*#30 Manufactured Silica Sand Recommended
6) Application: Two coats applied evenly over the entire surface are recommended. Apply by squeegee, brush, or mechanical spray. Apply second coat in cross direction of the first coat if this is practical. Allow two to four hours drying time between the first and second coats making sure the first coat is dry to the touch or will support equipment without tracking before the second coat is applied. It is recommended that coated surface be allowed to dry
24 hours before opening to traffic. Painting and striping can be applied as soon as the sealer is dry.
a. For ease of application in hot weather, air temperatures exceeding 95 degrees Fahrenheit, the surface should be fogged with water immediately prior to sealer application. Ambient temperatures should be at least 60 degrees and rising and below 110 degrees for Ace Seal application. Ace Seal should not be applied in temperatures below 60 degrees, or when ambient temperatures are forecast to be 37 degrees Fahrenheit or lower during the next 48 hours. Ace Seal should not be applied when rain is imminent or forecast within the next 48 hours. Ace Seal that is applied in temperatures below 70 degrees will take longer to cure and will be more sensitive to water until cured.
7. Coverage: Depending on the porosity and roughness of the surface and the method of application, coverage for a two-coat application will vary between 25 and 45 square feet per gallon.
8. General: Concentrated Ace Seal must be kept from freezing. Wash tools in water after use. Use mineral spirits to clean tools if material has dried. Containers should be kept tightly closed when not in use.
a. Before placing the double seal coat, the pavement surface shall be cleaned by sweeping, flushing or by other means necessary to remove all loose particles of paving, all dirt and all other extraneous material. Forty-eight (48) hours prior to the double seal coat operations, the contractor shall notify all residents, businesses and agencies with an approved written notice detailing the streets and limits of work to be done along with the hours of work. The contractor shall also post on all streets with temporary "No Parking - Tow Away" signs at 75-foot staggered intervals. These signs shall also state the day of the week and hours of no parking.
b. Immediately before commencing the double seal coat operations, all surface metal utility covers (including survey monuments) shall be protected by thoroughly covering the surface with an appropriate adhesive and paper or plastic. No adhesive material shall be permitted to cover, seal, or fill the joint between the frame and cover of the structure.
Covers are to be uncovered and cleaned of double seal coat material by the end of the same workday.
c. Hand tools shall be available in order to remove spillage. Ridges or bumps in the finished surface will not be permitted. The mixture shall be uniform and homogeneous after spreading on the existing surface and shall not show separation of the emulsion and aggregate after setting.
d. Adequate means shall be provided to protect the double seal coat from damage from traffic until such time that the mixture has cured sufficiently so that the double seal coat will not adhere to and be picked up by the tires of the vehicles.
e. For the purpose of this project, the construction zone is defined to include all stockpile staging areas and travel routes to/from streets where the double seal coat is to be applied. The Contractor shall abide, at all times, to the State of California, Department of Transportation's "Manual of Traffic Controls for Construction and
Maintenance Work Zones" as applicable to this project.
3.5 Parking Lot: Asphalt repairs shall consist of removing deteriorated asphalt and base course materials and provide 2 inches with Caltrans Type-A hot asphalt ½” inch mix over 6 inches of Class-II aggregate base course compacted to 95% relative density and compact 12 inches below finished subgrade soils to 95% maximum density. Prior to providing the double seal coat government personnel shall inspect the entire parking lot.
3.6 Roadway and turnaround: Asphalt repairs shall consist of removing deteriorated asphalt and base course materials and provide 4 inches with Caltrans Type-A hot asphalt ½” inch mix over 8 inches of Class-II aggregate base course compacted to 95% relative density and compact 12 inches below finished subgrade soils to 95% maximum density.
3.65 Relocate handicap parking so that it can be all in the front of the parking lot and stipe for handicap parking meeting all codes including the signs.
3.7 There are two areas on the road going from the roundabout to the facility. The contractor shall patch these two areas with 4 inches of Caltrans type A Asphalt over 8 inches of base course. (dips in road that go all the way across). The contractor shall clean out the drainage pipe under the road in this area and ensure proper drainage.
3.8 Contractor shall provide a double seal coat (the first coat shall contain an additional 1 to 3 percent liquid latex binder, in addition 2% of #30 mesh silica sand shall be added to each coat) throughout the parking lot using ace seal or approved equal.
3.9 After all asphalt deep lift repairs and skim patches have been accomplished a double seal coating application shall be performed, see double seal coat specification.
3.10 Once the double seal coating had been properly dried and cured; the Contractor shall then perform new striping for handicap stall(s), parking stalls and directional markings per approved parking lot layout plan by the base Civil Traffic Engineer.
3.11 The current/existing parking spaces for this the Parking Lot is 202 (6 are handicapped) and 9 motorcycle parking spaces. After the parking lot repairs and double slurry seal are completed, the Contractor shall re-stripe the parking lot to accommodate more parking lot spaces.
3.12 The contractor is to re-map the entire parking lot with consideration of the removal and pavement of existing planters’ spaces and submit to the Government as part of their proposal the new plan.
3.13 Immediately upon repair and construction completion, the project site shall be properly cleaned and demobilized prior to opening access to the parking lot for vehicle and pedestrian access.
3.14 The contractor shall divide the project into two phases as the parking lot is currently heavily used during dinning hours.
3.15 The contractor shall keep the concrete for the road in the exit area of the parking lot.
3.16 The contractor shall change the road with an exit only to an entrance and exit. The entrance/exit will road addition shall be added in the area opposite side of the exit of the parking lot light. The parking lot already is wide enough for two-way traffic except near the exit only area.
The contractor shall match the existing cement on the exit and change to entrance/exit with Class II aggregate 6-inch concrete on 4-inch type 2 portland cement 4000 psi. The contractor shall use #4 rebar, grade 60, 18 inches on center each way. The contractor shall use ¾ inch diameter, dowels 18 inches long, grade 60 steel, every 12 inches on center between new and old concrete. The road shall be at least 26 feet across.
4.0 GENERAL GUIDANCE:
4.1 Historical drawings: if provided, shall not be construed as complete or accurate records of existing conditions. The Contractor shall perform research into the historical records located at the 30th Civil Engineer Squadron, Engineering Flight, Execution Support section, Bldg. 11433, Drawing Vault as well as performing an actual on-site investigation is required for the Contractor to prepare a complete and accurate design. Contractor shall visit the project site and truly verify existing conditions prior to submitting a sound proposal. Contractor shall fully acquaint themselves with the preliminary design and all conditions affecting installation and/or modification of the proposed system. Failure to do so shall not relieve the Contractor of the responsibility of providing a complete, operating, and acceptable system or product.
5.0 Project Deliverables:
5.1 Project deliverables shall be as shown in the table below. A description of each deliverable follows:
PROJECT DELIVERABLES
Document Title
Copies Per Addressee
Delivery Date
C us to m er
Pr oj ec t
M an ag er
C on tra ct in g O ffi ce r & C
S
El ec tro ni c H ar d
C op y El ec tro ni c
H ar d C op y
El ec tro ni c H ar d
C op y
Performance and Payment Bonds (ref.
Master Spec. 01 00 00, para. 1.4.7.1 c.)
0 0 0 0 1 1 Within 10 calendar days after contract award
Construction Site Superintendent/Site Foreman letter (ref. Master Spec. 01 31 01, para. 1.1.1.4)
Within 14 calendar days after contract award
Record Drawing “Shop Drawings” (ref.
Master Spec. 01 00 00, para.
1.10.1)
Within 14 calendar days after contract award
Approved AF103, BCE Work Clearance Request w/drawing(s)/layout plan (ref.
Master Spec. 01 00 00, para. 1.7.1)
Minimum 14 calendar days prior to site mobilization or start of on-site construction
AF592, Hot Work Permit (ref. Master Spec. 01 00 00, para. 1.7.1.4 and 01 35 29, para. 1.9.1.2) as if required
Must have approval a minimum 5 calendar days prior to mobilization, or start of work
AF66, Schedule of Material Submittals or approved equivalent (ref. Master Spec. 01 00 00, para. 1.4.13.1 e (1) or 01 33 00 1.6.1)
A revised detailed AF66, SMS or equivalent within 10 calendar days after contract award
AF3064, Contract Progress Schedule, or approved equivalent (ref. Master Spec.
01 00 00, para. 1.4.13.1 f (1&2)
Within 10 calendar days after award or immediately after the Pre-construction conference, whichever is later? Updated form shall be submitted on or about the 5th day of next month for work completed during the previous month
AF3065, Contract Progress Report, or approved equivalent (ref. Master Spec.
01 00 00, para. 1.4.13.1 f (1&2)
Within 10 calendar days after contract award or immediately after the Pre- construction conference, whichever is later? An updated form shall be submitted on or about the 5th day of next month for work completed during the previous month
Accident Prevention Plan (APP) with Activity Hazard Analysis (AHA) (ref.
Master Spec. 01 35 29, para. 1.7, 1.7.1 through 1.7.1.2.1 (d) and para. 1.8, 1.8.1 through 1.8.3) as if required
Submit 15 calendar days prior to Pre-construction meeting or after receipt of In-lieu of Preconstruction Letter. On-site work cannot proceed without pre-construction letter of acceptance
Crane Lift Plan (ref. Master Spec. 01 35 29, para. 3.5.2.2) as if required
Submitted 14 calendar days prior to mobilization or on-site construction
Site Specific Solid Waste Management Plan (ref. Master Spec. 01 57 20, para.
3.5)
Within 14 calendar days prior to mobilization or on-site construction
Solid Waste Management and Report (Monthly) (ref. Master Spec. 01 57 20, para. 3.5, 3.5.1 and 3.5.2 a through g)
Receipts of landfill disposal shall be submitted immediately or the next duty date after each occurrence
Display of Safety Information (ref.
Master Spec. 1 35 29, para. 1.9.1)
0 0 1 0 1 0 Within 1 calendar day after commencement of work
Quality Control Documentation “Dailies/Weekly Progress Report” (ref.
Master Spec. 01 45 00, para. 1.4 -
1.4.1.6 through 1.4.4)
A collection of 1-weeks’ worth of daily reports shall be submitted by COB Monday the week after
Monthly Status Report
Contractor shall submit report within 2 duty-days at the ending of each construction month(s)
Pre-Final Inspection (ref. Master Spec.
01 78 00, para. 1.1.1.3 & 1.1.1.4) and Beneficial Occupancy (01 78 00, para 1.2, 1.2.1 through 1.2.2.6 (b)
Contractor shall submit a request minimum 7-10 duty days prior to the requested date(s)
Record of Drawing and “As-builts” Batch Check (ref. Master Spec. 01 00 00, para. 1.10.2.1)
Contractor shall submit a CD ROM with a date directly to the Drawing Vault Technician to request a “batch check”. NOTE: It must be hand delivered to a person assigned at the Drawing Vault. A cleared “batched check” with a batch check report shall be completed and accompanied with a final submittal to the CO
Final Inspection (ref. Master Spec. 01 78 00, para. 1.1.2)
Contractor shall submit a request a minimum 7-10 duty days prior to the requested date(s)
10.0 SUBMITTAL PROCEDURES
The Contractor shall follow the steps found in the Submittal Procedures Specification, 01 33 00, for all of the items noted in the "Tables of Deliverables".
11.0 PROJECT MANAGEMENT PLAN (PMP)
The Contractor shall submit a Project Management Plan that includes a description and flowchart of personnel involved with the project and a thorough description of construction management. The construction management narrative shall include timing of permitting, lead time for material, use date for user, etc.
12.0 ACCIDENT PREVENTION PLAN (APP)
The Contractor shall submit an Accident Prevention Plan that analyzes and addresses all safety concerns according to all specifications and other requirements.
13.0 QUALITY CONTROL PLAN (QCP)
The Contractor shall submit a Quality Control Plan that analyzes and addresses all safety concerns according to all specifications and other requirements. The Quality Control Plan shall include a copy of a certificate of training in Construction Quality Management for Contractors (US Army Corps of Engineers (ACoE) and/or NAVFAC) for each of the Quality Control Managers (QCM).
14.0 CONTRACT PROGRESS SCHEDULE (AF Form 3064)
The Contractor shall submit a signed AF Form 3064, Contract Progress Schedule, depicting an overall contract progress schedule for the main elements of work for the period of performance as described in the Table of Deliverables above. The Contractor shall also provide a line graph depicting actual construction progress (solid line) versus scheduled construction progress (dotted line) throughout the period of performance. The BCE PM will sign the AF Form 3064 and send to the Contract Specialist (or COR) for coordination and approval by the CO.
15.0 CONTRACT PROGRESS REPORT (AF Form 3065)
The Contractor shall submit AF Form 3065 as described in the Table of Deliverables above.
This report shall be signed by the contractor’s on-site representative in the Remarks section of the AF Form 3065. The work elements and percentages of the total job identified on the AF Form 3065 shall be identical to the work elements and percentages on the AF Form 3064. If the Contractor is more than 5% behind schedule, the Contractor shall note in the “Remarks section” the reason why and what is being done to get back on schedule. The BCE PM will sign the AF Form 3065 and send to the Contract Specialist for coordination and approval by the CO. If the Contractor requires reimbursement of a high dollar value item, the item shall be identified on the AF Form 3065, an appropriate percentage applied, and the item must be received and stored on site.
16.0 MONTHLY STATUS REPORT (MSR)
The Contractor shall submit Monthly Status Reports that communicate activities accomplished during the previous period, document discussions, identification of problems, proposed solutions, corrective actions taken, outstanding issues, and record issues or concerns. The Monthly Status Report shall include a financial tracking table containing columns with the following headings:
16.1 Task Breakout
16.2 Current Project Status (summary of work previously completed and completed during the current reporting period).
16.3 Task Value
16.4 Effort % Complete
16.5 Dollars % Expensed To Date
16.6 Dollars Earned This Month
16.7 Dollars Earned To Date
16.8 Expected work activities for the following month
16.9 Problems and/or concerns
16.10 RFI’s and Statuses
16.11 Updated Submittal Register
16.12 Safety
16.13 Photographic Log of Pervious Period Operations
An AF Form 3064 and an AF Form 3065 reviewed and approved/signed by the assigned PM and the CO. A Monthly Status Report shall accompany each invoice. The AF Form 3064, AF Form 3065, Monthly Status Report, and the invoice shall all cover the same period of time.
17.0 KICK-OFF MEETING
It is the responsibility of the Contractor to coordinate the date and time of pre-construction (i.e., Kick-Off) meeting with the PM and CO. During the meeting, the Contractor shall present a complete overview of the project and review the schedule, highlighting any issues (review periods, material submittals, etc.) which are key to maintaining the schedule. The Contractor shall take meeting minutes to include the recording of the attendance list.
18.0 PROGRESS MEETINGS
The Contractor shall perform Progress Meetings as described in the Table of Deliverables. These meetings will include all relevant base POC’s and Contracting Personnel on an as needed basis.
These meetings will cover the progress made in the past period and will include any pertinent issues which could affect future contract progress. The following items shall be covered:
18.6.1.1 Meeting Attendees and Contact Information
18.6.1.2 Project Percent Complete (Actual and Scheduled)
18.6.1.3 RFI’s and Statuses
18.6.1.4 Material Submittals and Statuses
18.6.1.5 Three Week Look Ahead
18.6.1.6 Schedule
18.6.1.7 Safety
18.6.1.8 Resolution of Existing Issues
18.6.1.9 New Business
19.0 FORMAT OF DELIVERABLES
The Contractor shall provide an electronic copy of all deliverables, formatted for use on the latest version and compatible with the Government’s version of Microsoft Word, Excel, Adobe Acrobat, and AutoCAD. The Contractor shall date all deliverables. The Contractor will be provided samples of the deliverables, upon request.
20.0 PRE-FINAL INSPECTION
The Contractor shall conduct a pre-final walk-through inspection with Base personnel and publish the pre-final inspection findings in a pre-final inspection (punch list) report.
21.0 FINAL INSPECTION
The Contractor shall conduct a final inspection with base personnel and publish the findings in a final inspection report. The inspection shall concentrate on the items identified at the pre-final inspection and recorded in the pre-final inspection (punch list) report. A final inspection shall not be performed until the pre-final inspection (punch-list) report has been resolved.
22.0 CONTRACT CLOSEOUT BOOK
Upon completion of the project and prior to final payment, the Contractor shall provide to the Government a Contract Closeout Book submittal. The Contract Closeout Book shall contain:
the completed AF Form 103; a completed submittal register; a completed AF Form 3064; a copy of the approved as-built drawings in Adobe Acrobat format; manufacturers’ and/or product warranty data; certificates attesting the product, system, and/or materials meet specification requirements; operation manuals, commissioning reports, and test reports not previously submitted on an AF Form 3000; recovered/salvageable materials and/or landfill disposal tickets, if applicable; any other documentation necessary to record compliance with technical requirements, administrative requirements or terms and conditions of the contract.
23.0 MAILING ADDRESSES
23.1 SPACE FORCE PROJECT MANAGER
30th Civil Engineer Squadron (30CES/CENMP) Engineering Flight, Project Management, Project Execution 1172 Iceland Ave (Bldg. 11433)
Vandenberg SFB, CA 93437
(805) 606-6133
23.2 SPACE FORCE CONTRACTING OFFICER (CO)
TSgt. Mark Wheeler
30th Contracting Squadron (30CONS/PKA) Infrastructure Support Flight (Construction) 1515 Iceland Ave, Bldg. 8500, Room 150 Vandenberg SFB, CA 93437
(805) 606-1506 Mark.Wheeler.10@spaceforce.mil
24.0 OTHER REQUIREMENTS
The Contractor is also responsible for the following:
24.1 WRITTEN SUMMARIES
The Contractor shall prepare written summaries of all meetings, field investigations, and design review conferences held in conjunction with this contract. The Contractor shall submit them tthe Space Force Project Manager for concurrence. All action items shall clearly state the requested information and the party responsible for providing the information. This summary should be submitted within two (2) calendar days.
24.2 RECYCLABLE MATERIALS
The Contractor shall make every effort to use recyclable materials for all submittal documentation.
24.3 CONTRACTOR PAYMENT INVOICE
The Contractor shall submit an invoice for payment in accordance with (IAW) DFARS Clause 252.232-7006 Wide Area Workflow (WAWF).
24.4 ENERGY EFFICIENCY
Energy-efficient technology and equipment is required for all projects at Vandenberg SFB as mandated by the Energy Policy Act of 1992.
24.5 SUSTAINABLE FACILITY DEVELOPMENT
In an effort to comply with the affirmative procurement requirements of Section 6002 of Resource Conservation and Recovery Act (RCRA) and Executive Order 13101, the Government strongly promotes the use of recycled and recovered materials and products identified in the Environmental Protection Agency's Comprehensive Procurement Guidelines. These materials and products must meet the requirements of the Specifications, must not delay the progress of work, and must not be cost prohibitive. EPA guideline items are seen as the minimum that should be considered when evaluating recycled/reuse materials. Other materials and products not listed, but commonly used in industry outside of the Government should also be considered.
Material and product submittals for all recycled-content items should list the recycled and recovered materials used and the percentage content.