This document is a Price Schedule for the GAOA Melstone Dam Reconstruction project (contract number 140L0625R0012). The bid schedule details 23 line items for dam reconstruction work, including mobilization, site clearing, excavation, embankment, spillway work, outlet structures, riprap protection, and ancillary construction activities. Quantities are specified in various units such as cubic yards (CY), tons (TON), square yards (SY), and lump sum (LS), with a note that quantities are not guaranteed. The pricing template requires contractors to provide unit prices and total prices for each line item, with total prices to be fully burdened and include overhead, profit, and bonding. The document also includes placeholder rows for overhead, profit, and bond rates to be specified by the bidder.
Key construction activities include 34,390 CY of common excavation, 47,150 CY of compacted embankment, 2,640 tons of new riprap slope protection, outlet works tower and conduit installation, stilling basin construction, and various other earthwork and infrastructure components. The document indicates that measurement and payment details for each item will be defined in Section 01150, and the total contract price will be calculated based on the submitted unit prices and specified rates for overhead, profit, and bonds.
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item
No. Description Unit Price Total Price**
1 Mobilization and Preparatory Work 1 LS
2 Site Clearing, Topsoil Stripping, & Restoration 1 LS
3 Existing Sructures Demolition 1 LS
4 Common Excavation 34,390 CY
5 Muck Excavation 4,300 CY
6 Compacted Embankment 47,150 CY
7 Lime Amended Embankment 1,140 CY
8 Spillway Excavation 1,030 CY
9 Spillway Training Dike Fill 205 CY
10 Filter Sand 3,100 CY
11 Drain Gravel 510 CY
12 Road Gravel 550 TON
13 Outlet Works Tower and Inlet Structure 1 LS
14 Outlet Works Conduit 1 LS
15 Stilling Basin 1 LS
16 New Riprap Slope Protection 2,640 TON
17 Salvage and Replace Existing Rock 144 CY
18 Riprap Bedding 2,740 TON
19 Water Control/Dewatering 1 LS
20 Toe Drain System 1 LS
21 Geotextile Fabric 1,500 SY
22 General Construction Operations 1 LS
23 Fence 1 LS
Rate***
** Total Price for each Item is fully burdened and includes Overhead, Profit, and Bond.
*** Overhead, Profit, and Bond rates used in the total price to be provided.
*Quantities are not guaranteed. Measurement and payment for each Item is defined in Section 01150, Measurement and
Payment.
140L0625R0012 GAOA MELSTONE DAM RECONSTRUCTION
Price Schedule
Quantity*
TOTAL CONTRACT PRICE
Overhead
Profit
Bonds
S:\bc\BC660\BC-664\Solicitations in Progress\FY 2026 AWARD 140L0625R0012 GAOA Melstone Dam MT - LM\B-SOLICITATION\B08
Solicitation\Archive\Att4_Price_Breakout_23Sep
BID SCHEDULE
File details come from the government source that posted it. Updated .