This is a bidding schedule and quantity summary document for the Trickel Park Road Asphalt project on the Grand Mesa, Uncompahgre, and Gunnison National Forest in Colorado, issued as RFQ 1240LT26Q0156 by the Department of Agriculture Forest Service.
The document outlines detailed estimated quantities for all pay items across multiple bid schedules (A, X, and optional schedules). Schedule A includes mobilization, survey and staking, clearing and grubbing, roadway excavation (450 cubic yards), asphalt concrete pavement (2,750 tons of PG 58-28), pipe culverts in multiple sizes totaling 590 linear feet, roadway aggregate (2,300 tons), concrete headwalls, pavement markings (4.5 miles), topsoil placement (1.0 acre), mulching, fertilizer, sign systems, object markers, and temporary traffic control. Schedule X (optional work) includes additional signing and striping work with 9.0 miles of pavement markings, 26 sign systems, and marker installations. Key specifications reference the Forest Service Supplemental Specifications (FSSS) and engineering maps and plans. This is a Total Small Business Set-Aside with a $45M size standard. Bidders must submit a 20% bid bond on SF 24 and 100% Performance and Payment Bonds on SF 25 and SF 25A. A mandatory site visit is required. This is a Request for Quotation for road rehabilitation services including asphalt pavement, subgrade improvement, and culvert installations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet and Description
B4 B5 B6 B7-B9 B10-B12 B13
Schedule A Surfacing Summary
Schedule A Approach Roads & Pullouts Summary
Schedule A Grading
Summary
Schedule A Miscellaneous
Quantities
Schedule A Signing and
Striping Summaries
Schedule A Temporary
Traffic Control Summary
Allowances Bid
Schedule
A0020 15101-0000 MOBILIZATION LPSM ALL
A0040 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE EACH 17 17
A0060 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING
CONTROL MILE 1.003 1.003
A0080 15236-2000 SURVEY CONTROL, GRADE FINISHING MILE 1.003 1.003
A0100 15301-0000 CONTRACTOR QUALITY CONTROL LPSM ALL
A0120 15401-0000 CONTRACTOR TESTING LPSM ALL
A0140 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL
A0160 15701-0000 SOIL EROSION CONTROL LPSM ALL
A0180 15720-0000 STORM WATER POLLUTION PREVENTION PLAN LPSM ALL
A0200 15802-0000 WATERING FOR DUST CONTROL LPSM ALL
A0220 20102-0000 CLEARING AND GRUBBING LPSM ALL
A0240 20120-1000 REMOVAL, INDIVIDUAL TREE EACH 2 2
A0260 20301-0700 REMOVAL OF DELINEATOR EACH 13 2 15
A0280 20301-1900 REMOVAL OF PIPE CULVERT EACH 15 15
A0300 20301-2400 REMOVAL OF SIGN EACH 2 2
A0320 20401-0000 ROADWAY EXCAVATION CUYD 437 13 450
A0340 20402-0000 SUBEXCAVATION CUYD 37 63 100
A0360 20815-0000 COFFERDAMS LPSM All ALL
A0380 20820-0000 DEWATERING LPSM All ALL
A0400 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2 CUYD 18 2 20
A0420 30202-2000 ROADWAY AGGREGATE, METHOD 2 TON 1,342 589 253 116 2,300
A0440 40301-0000 ASPHALT CONCRETE PAVEMENT (PG 58-28) TON 2,469 176 105 2,750
A0460 40601-0000 FOG SEAL TON 7.2 0.9 0.4 8.5
A0480 41101-1000 PRIME COAT, METHOD 1 TON 10.0 1.1 0.4 11.5
A0500 41105-0000 BLOTTER TON 5
A0520 41201-0000 TACK COAT TON 5.1 0.5 0.4 6.0
A0540 60103-0100 CONCRETE, HEADWALL FOR 18-INCH PIPE CULVERT EACH 1 1
A0560 60103-0140 CONCRETE, HEADWALL FOR 24-INCH PIPE CULVERT EACH 6 6
A0580 60201-0400 12-INCH PIPE CULVERT LNFT 176 59 235
A0600 60201-0600 18-INCH PIPE CULVERT LNFT 122 8 130
A0620 60201-0800 24-INCH PIPE CULVERT LNFT 215 10 225
A0640 60210-0400 END SECTION FOR 12-INCH PIPE CULVERT EACH 12 12
A0660 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT EACH 6 6
A0680 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT EACH 7 7
A0700 61401-0000 LEAN CONCRETE BACKFILL CUYD 66 4 70
A M E N D
Line Item No.
Pay Item Number
SUMMARY OF QUANTITIES - Schedule A
Remarks and/or Determination of Estimated QuantityPay Item Description Unit
Estimated Quantities
STATE PROJECT
B1
FTFS 121(1)
TRICKEL PARK ROADCO
SHEET
NUMBER
Sheet and Description
B4 B5 B6 B7-B9 B10-B12 B13
Schedule A Surfacing Summary
Schedule A Approach Roads
& Pullouts Summary
Schedule A Grading
Summary
Schedule A Miscellaneous
Quantities
Schedule A Signing and
Striping Summaries
Schedule A Temporary
Traffic Control Summary
Allowances Bid
Schedule
A0900 62406-0100 PLACING CONSERVED TOPSOIL, 2-INCH DEPTH ACRE 0.91 0.09 1.00
A0920 62510-2000 ACRE 0.91 0.09 1.00
A0940 62515-3000 MULCHING, HYDRAULIC METHOD, BONDED FIBER
MATRIX ACRE 0.91 0.09 1.00
A0960 62520-0000 FERTILIZER ACRE 0.91 0.09 1.00
A0980 63301-0000 SIGN SYSTEM EACH 1 1
A1000 63308-2000 OBJECT MARKER, TYPE 2 EACH 38 38
A1040 63402-0300 MILE 4.014 0.486 4.500
A1060 63501-0000 TEMPORARY TRAFFIC CONTROL LPSM All ALL
A1100 64620-0400 REMOVE AND RESET MAILBOX EACH 3 3
SUMMARY OF QUANTITIES - Schedule A
A
M
E
N
Line
Item
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated Quantity
STATE PROJECT
B2
FTFS 121(1)
TRICKEL PARK ROAD
CO
SHEET
B14 B15-B17
Option X Miscellaneous
Quantities
Option X Signing and
Striping Summaries
Allowances Bid
Schedule
X0020 15101-0000 MOBILIZATION LPSM ALL
X0040 20301-2400 REMOVAL OF SIGN EACH 5 5
X0060 63301-0000 SIGN SYSTEM EACH 26 26
X0080 63308-2000 OBJECT MARKER, TYPE 2 EACH 6 6
X0100 63308-3000 OBJECT MARKER, TYPE 3 EACH 1 1
X0120 63402-0300 PAVEMENT MARKINGS, TYPE B, SOLID MILE 8.334 0.666 9.000
SUMMARY OF QUANTITIES - Schedule X
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated Quantity
STATE PROJECT
B3
FTFS 121(1)
TRICKEL PARK ROADCO
SHEET
Option
4. Existing geogrid may be encountered during subexcavation;
remove and dispose of geogrid from subexcavation limits.
Overlap existing geogrid per CO with the separation-stabilization geotextile prior to backfilling subexcavation area with roadway aggregate.
FTFS 121(1)
TRICKEL PARK ROADCO T1
TRICKEL PARK ROADCO T2
TRICKEL PARK ROADCO T3
TRICKEL PARK ROADCO T4
TRICKEL PARK ROADCO T5
TRICKEL PARK ROADCO T6
TRICKEL PARK ROADCO T16
TRICKEL PARK ROAD
8. Signs, channeling devices, traffic control supervisor hours, pilot car hours, and flagger hours paid for under 63501-0000 Temporary Traffic Control.
CO T17
TRICKEL PARK ROADCO T18
File details come from the government source that posted it. Updated .