Att.1 - C04 - Statement of Work.pdf
PDF 159 KB Posted
- Attached to
- Trickel Park Road Asphalt Grand Mesa, Uncompahgre, and Gunnison National Forest, Colorado
- Solicitation number
- 1240LT26Q0156
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Statement of Work (SOW) for road rehabilitation services on Trickel Park Road located in the Grand Mesa, Uncompahgre, and Gunnison National Forest in Colorado, issued by the U.S. Department of Agriculture (USDA) with an effective date of July 20, 2026.
The project encompasses comprehensive road rehabilitation including asphalt concrete pavement construction, subgrade improvement, and culvert installations. Technical requirements span 17 specific tasks including construction surveying and staking, contractor sampling and testing, soil erosion and sediment control, clearing and grubbing, excavation and embankment work, riprap installation, asphalt concrete pavement construction, fog seal installation, and pipe culvert installation with concrete headwalls. The contractor must provide all material sources from off-National Forest System lands. Key personnel requirements include a Project Superintendent (minimum two years equivalent experience, must be on-site throughout the project), Quality Control Manager, Traffic Control Supervisor, Geotechnical Engineer/Consultant, Public Information Officer, and Qualified Biologist/Consultant, with allowances for the Project Superintendent to assume multiple roles. Deliverables include a Project Plan (due within five business days of award), monthly updated schedules, weekly status reports via TEAMS meetings, sampling and testing reports per specifications, and monthly invoices. The contractor bears all travel costs with no government reimbursement. All electronic information must comply with Section 508 accessibility standards. Attachments include Forest Service Supplemental Specifications, Map and Plans, Schedule of Items, Sustainable Products requirements, and Wage Determination documentation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work Trickel Park Road Asphalt
Grand Mesa, Uncompahgre, and Gunnison National Forest, Colorado July 20, 2026
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards Attachments
Project
Trickel Park Road Asphalt Grand Mesa, Uncompahgre, and Gunnison National Forest, Colorado
General Information
1.0 Scope of Work
Project consists of road rehabilitation including asphalt concrete pavement, subgrade improvement, and culvert installations. Refer to FP-14, the Forest Service Supplemental Specifications (FSSS) and the engineering map and plans for technical requirements and tasks.
Work activities and roads are specified in the Map and plans, FP-14, Forest Service Supplemental Specifications (FSSS) and Schedule of Items.
Project Location
The nearest town to the project location is Cedaredge, CO.
Directions from the Grand Mesa, Uncompahgre, and Gunnison (GMUG) National Forests (NF), Supervisors’ Office, 2250 South Main, Delta, Colorado.
Travel north on Highway 50 for 2.3 miles. Turn east onto Highway 92 E. Travel east for 3.8 miles to the intersection with Highway 65 N. Turn north onto Highway 65 N. Travel north for 26.8 miles. Turn east onto National Forest System Road (NFSR 121) Trickel Park (the Grand Mesa Visitors Center is adjacent to the Trickel Park Road). Drive to the beginning of the project. Project begins at the end of the existing asphalt.
Station 251+94, Latitude: 39.044872°, Longitude: -107.946735°
2.0 Background
Refer to General Information section 1.0 Scope of Work for the general description of the requirement.
Contractor Requirements
3.0 Technical Requirements / Tasks
Technical requirements and tasks for this project include the following.
1) Construction Surveying and Staking
2) Contractor Sampling and Testing
3) Soil Erosion and Sediment Control
4) Watering for Dust Control
5) Clearing and Grubbing
6) Removal of Structures and Obstructions
7) Excavation and Embankment
8) Structure Excavation and backfill
9) Installation of Riprap
10) Placement of Minor Crushed Aggregate
11) Construction of Asphalt Concrete Pavement
12) Installation of Fog Seal
13) Asphalt Prime Coat and Blotter
14) Installation of Concrete Headwalls for Pipe Culverts
15) Installation of Pipe Culverts
16) Installation of Pipe Culvert End Sections
17) Temporary Traffic Control
Information for this project resides within the Map and Plans, FP-14, Forest Service Supplemental Specifications, and Schedule of Items. The contractor will be required to provide a construction schedule (GANTT chart or other acceptable schedule) to ensure technical expertise and understanding of specified work to meet the technical requirements of the project.
4.0 Government Furnished
There is no Government-Furnished Property for this project.
All material sources shall be contractor-located sources and shall be sources off of National Forest System (NFS) lands.
5.0 Deliverables / Schedule
Key Deliverables
Item No.
Deliverable / Item Title
Description Frequency Delivery Format Due
1 Project Plan Define the responsibilities and timeline of the contract technical requirements and tasks.
Once Via email to the Contracting Officer (CO) and the Contracting Officers Representative
(COR)
No later than five
(5) business days after contract award
2 Updated schedule and timeline
Revised timeline of the contract tasks
Once per month
Via email to the CO and COR
No later than the end of the first week of each month during the entirety of the project
1 Weekly Status Report
Weekly status report documenting tasks and issues identified during the week
Once per week
TEAMS meeting with the CO and
COR
Once a week. 30- 60 minutes total meeting time.
2 Sampling and Testing
Sampling and Testing of materials
Refer to the Specifications
Report provided by Geotechnical Engineer Firm to the CO and COR
Refer to the Specifications
3 Monthly Invoice
Invoice for review and approval
Once per month
Via email to CO and COR before submittal to Invoice Processing Platform (IPP)
The first week of each month after contract award
6.0 Travel
The Contractor shall be responsible for all costs associated with travel; the Government will not reimburse the Contractor for travel expenses.
7.0 Contractor’s Key Personnel
Contractors Key Personnel include but are not limited to the following per specifications.
1) Project Superintendent
2) Quality Control Manager
3) Traffic Control Supervisor
4) Geotechnical Engineer / Consultant
5) Public Information Officer
6) Qualified Biologist / Consultant
The Project Superintendent can also act as the Quality Control Manager and Public Information Officer. The project superintendent must always be on-site during the entirety of the project. If the project superintendent is not available due to unforeseen or emergency needs, then an alternative project superintendent must be identified and a written designation letter from the Contractor to the Contracting Officer must be provided within 24 hours and limited to the unforeseen / emergency need.
The Project Superintendent must have a minimum of two years’ equivalent experience in work similar in scope.
8.0 Security Requirements
N/A
9.0 Data Rights
N/A
10.0 Section 508 – Electronic and Information Technology Standards
All electronic information provided shall be accessible to persons with disabilities. And comply with Section 508.
Attachments
• Forest Service Supplemental Specifications (FSSS)
• Map and Plans
• Schedule of Items
• Sustainable Products
• Wage Determination
| Project |
| General Information |
| 1.0 Scope of Work |
| Project Location |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |
| Attachments |
File details come from the government source that posted it. Updated .