This document outlines a federal bulk petroleum purchase solicitation. The Defense Logistics Agency Energy is seeking annual bulk petroleum supplies for the Western Pacific and Middle East regions totaling approximately 638 million gallons of Naval Distillate (F76), Turbine Fuel Aviation (JP5), and Turbine Fuel Aviation (JA1) with some gallons requiring additives. Delivery is required between January 1, 2023 and December 31, 2023 via tanker, shallow draft tanker, tanker truck, railcar, and pipeline with FOB destination tanker offers not accepted. Offerors must submit pricing through the Offer Entry Tool by the closing date, and offers must be in English and U.S. dollars.

View the file

Other files for this federal contract opportunity

Other files attached to Western Pacific & Middle East Bulk Petroleum Purchase Program (WESTPAC), newest first.
File Type Posted
22R0707_Min_Cost_Solution_Contractor_Summary.pdf PDF
22R0707_Min_Cost_Bid_Award.pdf PDF
22R0707_Summary_of_Awards.pdf PDF
SPE60222R0707 AWARD SUMMARY.pdf PDF
22R0707_Min_Cost_Bid_Evaluation.pdf PDF
SF1449 SPE60222R0707 Conformed AMD 0006.pdf PDF
SF30 SPE60222R0707 AMD 0006.pdf PDF
SF1449 SPE60222R0707 Conformed AMD 0005.pdf PDF
SF30_SPE60222R0707 AMD 0005.pdf PDF
SF30 SPE60222R0707 AMD 0004.pdf PDF
SF1449 SPE60222R0707 Conformed AMD 0004.pdf PDF
SF1449 SPE60222R0707 Conformed AMD 0003 .pdf PDF
SF30 SPE60222R0707 AMD 0003.pdf PDF
Att 1 Fill-Ins WORD VERSION Conformed AMD 0002.docx DOCX document
SPE60222R0707 AMD 0002.pdf PDF
SF1449 SPE60222R0707 Conformed AMD 0002 .pdf PDF
Att 6 QAPs Conformed AMD 0002.pdf PDF
SPE60222R0707 Questions and Answers 2.pdf PDF
SPE60222R0707 PREPROPOSAL SLIDES.pdf PDF
SPE60222R0707 Questions and Answers 1.pdf PDF
SPE60222R0707 Conformed AMD 0001.pdf PDF
SPE60222R0707 AMD 0001.pdf PDF
Att 3 DL2019 Small Business.pdf PDF
Att 4 F76 Traceability Sheet.pdf PDF
Att 2 Equal Value Exchanges of Fuel.pdf PDF
Att 1 Fill-Ins WORD VERSION.docx DOCX document
Tab 09 RFP WP 22R0707.pdf PDF
Att 8 Map Coordinate Desk Guide.pdf PDF
Att 5 AFRICOM Foreign Vendor Info Sheet.pdf PDF
Att 7 OET Guidance.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

PDF (DLA)DLA FORM 1889, OCT 2011

SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)

SHEET 1 OF 2PREVIOUS EDITION IS USABLE Add Continuation Page

Print Form Email Form Clear Export Data Import Data About Check for Newer Version Contact Us

REV DESCRIPTION DATE APPROVED

NEW DLA ENERGY QAP E40.01

REVISIONS

QAP E40.01 MATERIAL INSPECTION AND RECEIVING REPORT (MIRR)/WIDE AREA WORKFLOW

(WAWF) ENERGY RECEIVING REPORT (ERR) (BULK FUEL/DIRECT DELIVERY AVIATION FUEL).

Required in all bulk fuel solicitations/contracts and direct delivery aviation fuel solicitations/contracts. DLA FORM 1889 dated .

QAP E40.01 MATERIAL INSPECTION AND RECEIVING REPORT (MIRR)/WIDE AREA WORKFLOW

(WAWF) ENERGY RECEIVING REPORT (ERR) (BULK FUEL/DIRECT DELIVERY AVIATION FUEL)

(DLA ENERGY JUL 2014)

(a) The requirements listed in paragraphs (b) and (c) are in addition to the other Wide Area Workflow (WAWF) requirements included in this contract. Whenever access to the WAWF system is limited or not available (i.e., during an extended loss of internet connectivity), the Contractor shall notify the Contracting Officer and request permission to submit documents manually until the WAWF system is again available for use. Manual documentation shall be completed in accordance with DFARS Appendix F.

(b) Test reports shall be entered into the WAWF system by means of the Statement of Quality tab.

Instructions for entering test information into the Statement of Quality Tab can be found in the WAWF Vendor Energy Receiving Report (ERR)/Combo Desktop Reference which can be downloaded at https://wawftraining.eb.mil/xhtml/ unauth/web/wbt/wawfra/vendor/VendorIndex.xhtml.

(c) Use the guidelines below for the submission of fuel quality testing data and supporting documentation for each ERR/Combo.

(1) MARINE SHIPMENTS. Submit a completed ERR/Combo and test reports via the Statement of Quality tab for all products shipped. If more than one shipping tank was used for the lift, a complete laboratory analysis for each shipping tank must be entered in the Statement of Quality tab. Also, clearly indicate the quantity of product shipped from each tank in the block titled “Quantity shipped from this tank”. Upload scanned copies, via the Attachments tab, of quantity determination documents and other shipping documents requested by the Quality Assurance Representative (QAR).

(2) PIPELINE SHIPMENTS. Submit a completed ERR/Combo and input the test results via the Statement of Quality tab for the total quantity of product shipped from each shipping tank used to fill the order. If more than one shipping tank was used for the shipment, a complete laboratory analysis for each shipping tank must be entered in the Statement of Quality tab. Also, clearly indicate the quantity of product shipped from each tank in the block titled “Quantity shipped from this tank”. Upload scanned copies, via the Attachments tab, of quantity determination documents and other shipping documents requested by the QAR.

(3) TRUCK, RAIL CAR AND INTERMODAL CONTAINER SHIPMENTS. When loading from source tank has finished for each shipment, submit a completed ERR/Combo and input test results via the Statement of Quality tab, for product received from that source tank. If only one shipment is made from a shipping tank, enter that quantity in the “Quantity shipped from this tank” block located on the Statement of Quality tab. If more than one shipment is made from the same shipping tank, the “Quantity shipped from this tank” block can either be left blank or be annotated with the quantity shipped during each individual shipment. Upload scanned copies, via the Attachments tab, of quantity determination documents and other shipping documents requested by the QAR.

DISTRIBUTION

STATEMENT - A

APPROVED FOR

PUBLIC RELEASE

DISTRIBUTION IS

"UNLIMITED"

DATE

07/08/2014

APPROVED BY

07/08/2014

REVIEWED BY

07/07/2014

PREPARED BY

DRAWING NUMBERSCALE

CODE ID NO.

52838

SIZE

NSN

MULTIPLE

ITEM

DLA ENERGY QAP E40.01

DLA Land & Maritime DLA Troop Support DLA Aviation clear

DEFENSE LOGISTICS AGENCY ENERGY

8725 JOHN J. KINGMAN RD

FORT BELVOIR, VIRGINIA 22060-6222

DLA Energy

SHEET 2 OF 2PREVIOUS EDITION IS USABLE Add Continuation Page

NEW DLA ENERGY QAP E40.01

THIS PAGE INTENTIONALLY LEFT BLANK

DISTRIBUTION STATEMENT - A

APPROVED FOR PUBLIC RELEASE

DISTRIBUTION IS "UNLIMITED"

SUPPLEMENTAL QUALITY ASSURANCE PROVISION

(SQAP)

DRAWING NUMBERSCALE CODE ID NO.

PDF (DLA)

DLA FORM 1889, OCT 2011

SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)

SHEET OF

PREVIOUS EDITION IS USABLE

REV

DESCRIPTION

DATE

APPROVED

REVISIONS

REV

DESCRIPTION

DATE

APPROVED

REVISIONS

DISTRIBUTION STATEMENT - A

APPROVED FOR PUBLIC RELEASE

DISTRIBUTION IS "UNLIMITED"

SUPPLEMENTAL QUALITY ASSURANCE PROVISION (SQAP)

Supplemental Quality Assurance Provision (SQAP)

DSCC Form 2291, Feb 2004 online none standard

Quality Assurance

DLA

1 +

No

Tech Qual Deskbook n/a

No

Supplemental Quality Assurance Provision (SQAP) interactive

October 2011 (added Energy; updated supply center names)

CurrentPage:

PageCount:

btnPrint:

btnEmail:

btnClear:

btnExport:

btnImport:

btnAbout:

btnChkVersion:

btnContactUs:

Button1:

rev: NEW description: DLA ENERGY QAP E40.01 revdate:

revapproved:

revcomments:

apprdate: 07/08/2014 apprBy:

reviewdate: 2014-07-08 revBy:

prepdateA: 2014-07-07 prepbyA:

drawingNum:

scale:

codeIDNo: 52838 size:

nsn: MULTIPLE itemdesc: DLA ENERGY QAP E40.01 btnDSCC:

btnDSCP:

btnDSCR:

line1: DEFENSE LOGISTICS AGENCY ENERGY line2: 8725 JOHN J. KINGMAN RD line3: FORT BELVOIR, VIRGINIA 22060-6222 revcomments2:

totInstances: 1.00000000

DEFENSE LOGISTICS AGENCY ENERGY Page 1 of 1

8725 JOHN J. KINGMAN ROAD

DISTRIBUTION STATEMENT – A: APPROVED FOR PUBLIC RELEASE. DISTRIBUTION IS UNLIMITED

Signature

Prepared by:

Quality/Technical Support

Office Approval:

Contracting Approval:

C1.02 ASSIST DATABASE OF SPECIFICATIONS (DEC 2016)

Unless otherwise specified, current versions of defense or federal specifications and standards, military handbooks, commercial item descriptions, qualified product lists, and other related technical documents cited in this solicitation/contract can be accessed from the Department of Defense (DoD) Acquisition Streamlining and Standardization Information System

(ASSIST) database at https://assist.dla.mil under ASSIST-Quick Search or http://quicksearch.dla.mil. ASSIST is the official source for all Defense Standardization Program documents and contains the most current information on documents prepared by DoD, as well as information on how to acquire referenced non-Government standards that have been adopted for

DoD use. Note that commercial or foreign specifications are not located on ASSIST and must be obtained from the relevant sponsoring organization (e.g. ASTM, SAE, API, ISO, etc.). Registered ASSIST account holders may establish profiles to receive automatic E-mail alerts when changes are planned or made to documents of interest by selecting criteria on the [Alert

Portal Profile Maintenance] screens accessed from the [User Profile] menu. Users may also view or download a bi-monthly summary of changes to the ASSIST database under the [ASSIST Update] menu.

Basic instructions on how to use ASSIST:

1. Go to http://quicksearch.dla.mil/.

2. Type in the numeric portion of the specification or Qualified Product List (QPL) and click on the Search button.

3. Look through the search results to find the desired document and click on the Document ID.

a. For specifications: click on the .pdf link under Media.

b. For QPL information: click on the View Qualified Product Database (QPD) data link to open the QPD

i. Click on the link in the “Govt Designation” Column to view qualified products

1. To view qualified source plants, click on the Source Plants link under the Related Links column http://quicksearch.dla.mil/

2017-08-07T09:00:32-0400

TAYLOR.LORI.L.1391585080

2017-08-07T09:22:23-0400

SHEPHERD.SANDRA.S.1012568459

2017-11-20T09:19:52-0500

BANISZEWSKI.DANIEL.J.1287388698

DEFENSE LOGISTICS AGENCY ENERGY Page 1 of 2

C16.01 TURBINE FUEL, AVIATION (JP5) (DLA ENERGY APRIL 2018)

NATIONAL STOCK NUMBER PRODUCT NOMENCLATURE DLA ENERGY PRODUCT

9130-00-273-2379 Turbine Fuel, Aviation, JP-5 JP5

9130-01-499-9521 Turbine Fuel, Aviation, JP-5 (Bunker fuel overseas locations only) JP5

Product shall meet MIL-DTL-5624W, Turbine Fuel, Aviation, Grade JP-5, dated March 28, 2016.

(a) SPECIFICATION MODIFICATION: The requirements of Table I in the specification are modified as follows:

a. FILTRATION TIME TESTING. Round upwards when reporting the filtration time, in minutes. For example, a filtration time of 4 minutes, 22 seconds, would be reported as 5 minutes.

b. FLASH POINT TESTING. The referee procedure for performing flash point testing of JP-5 shall be the manual method of ASTM D93 as opposed to the automated version of ASTM D93.

c. FLASH POINT.

i. All batches of JP-5 that are presented for Government acceptance at origin and for subsequent shipment through a multiproduct pipeline, shall meet a minimum flash point requirement of 62.5°C.

ii. In the U.S. all JP-5 deliveries in California, Oregon, and Washington shall have a minimum Flash Point of 62.5 oC at the custody transfer point.

iii. In Australia all JP-5 deliveries shall have a minimum Flash Point of 61.5°C at the custody transfer point.

d. ACID NUMBER. For JP-5 delivered to Kodiak Island, Alaska, the maximum total acid number shall be 0.020 mg KOH/g.

e. MICRO-SEPAROMETER (MSEP) REQUIREMENTS.

i. Prior to initial production under this contract, the Contractor shall elect, on a one-time basis, which MSEP limit to meet for the balance of the contract. If the Contractor introduces Fuel System Icing Inhibitor (FSII) and/or Corrosion Inhibitor/Lubricity Improver (CI/LI) after verification of product conformance with the MSEP requirement, the product is not required to meet a fixed limit on subsequent MSEP tests.

ii. If the Contractor elects to verify conformance with the MSEP requirement on a sample of product that does not contain FSII and CI/LI, an additional MSEP test shall be performed on a hand blend containing jet fuel, FSII, CI/LI, and Antioxidant (only if required). The FSII shall be added to this hand blend at a concentration range between 0.08 volume percent minimum and 0.11 volume percent maximum. The amount of the CI/LI added to this hand blend shall be within the concentration range specified in QPL-25017.

f. ADDITIONAL REQUIREMENT APPLICABLE TO DEEP FREEZE PROGRAM ONLY. The Deep Freeze Program is for Antarctic operations of the Department of Defense and other federal agencies; whereby JP-5 sulfur content shall not exceed 0.0015 mass-percent (15 ppm).

(b) ADDITIVES.

a. Additives are required for deliveries of JP-5, per MIL-DTL-5624W, unless addition is excluded by specific solicitation line item, applicable contract clause, or other contractual requirement. FSII included in jet fuel shall conform to MIL-DTL- 85470B, Inhibitor, Icing, Fuel System, High Flash, Notice 1 dated June 15, 1999 and revalidated March 24, 2004.

b. The CI/LI additive(s) used shall conform to MIL-PRF-25017H Inhibitor, Corrosion/Lubricity Improver, Fuel Soluble, w/Amendment 1, dated August 4, 2011

c. Line injection of additives (FSII and CI/LI) from shipping tank to delivery conveyance or other free on board (FOB) point is permitted under the following conditions:

i.Additives must be proportionately injected throughout the entire loading process to ensure the additive is homogeneously blended into the jet fuel. The Contractor shall maintain records evidencing the homogeneous blending of all line injected additives. Such methods may include meter or tank gauge readings or test results taken at intervals to provide confidence in the injection process.

ii. When FSII is required, additive concentration must be verified based on a representative sample from each shipping conveyance.

(c) Conformance to specification requirements at the custody transfer point is required, however, prior to shipment, a laboratory hand blend of JP-5 fuel with all additives required by this contract shall be tested to verify compliance with the required specification (except for MSEP). MSEP analysis shall be performed per the Contractor’s election in MIL-DTL-5624W.

(d) BATCH SAMPLING: The Contractor shall provide one 20 mL sample per each individual tank in a procurement batch.

NOTE: This sample is in addition to those required in accordance with Quality Assurance Provision (QAP) E1

QUANTITY OF SAMPLE WHEN SAMPLED SUBMISSION PERIOD

20 mL Upon completion of each individual procurement batch Shipped within 30 days of procurement batch delivery

“Batch” Definition in accordance with MIL-STD-3004, 3.1.9: A specific quantity of product that is processed or utilized as a single unit and tested to meet test criteria and specifications.

DEFENSE LOGISTICS AGENCY ENERGY Page 2 of 2

The sample from each tank/batch shall be either an all-level sample or a composite of upper, middle, and lower samples. A copy of the batch’s full-specification test report shall accompany each sample. The sample container shall be any 20 mL amber borosilicate vial with a polytetrafluoroethylene (PTFE) lined screw cap. A tracking number for the samples shall be provided to: Thomas Loegel at thomas.loegel@nrl.navy.mil or (202) 767-1716. Samples shall be shipped to:

US Naval Research Laboratory ATTN: Thomas Loegel, Code 6181

JP-5 Component Analysis Library Project 4555 Overlook Ave., S.W.

Washington D.C. 20375-5320

The paperwork provided with these samples shall include the following information:

• Contract Number

• Contractor’s Name

• Product

• Refinery Location

• Quantity of Tank/Batch

• For samples containing synthetic components, include the following additional information:

• Manufacturer of synthetic component

• Batch Number

• Date of Test Report

• Quantity of Tank/Batch

• Percent Composition

• Production Process of Synthetic Component

• Feedstock

Prepared by

Quality Technical Support Office Approval

Contracting Approval mailto:Robert.morris@nrl.navy.mil

C16.01 TURBINE FUEL, AVIATION (JP5) (DLA ENERGY APRIL 2018)

c. FLASH POINT.

e. MICRO-SEPAROMETER (MSEP) REQUIREMENTS.

(b) ADDITIVES.

c. Line injection of additives (FSII and CI/LI) from shipping tank to delivery conveyance or other free on board (FOB) point is permitted under the following conditions:

2018-04-25T09:13:12-0400

YEN.CHENG.H.1539446041

2018-04-25T09:18:48-0400

BANISZEWSKI.DANIEL.J.1287388698

2018-04-26T16:45:01-0400

SHEPHERD.SANDRA.S.1012568459

DEFENSE LOGISTICS AGENCY ENERGY Page 1 of 1

Quality/Technical Support Office Approval

C16.09 TURBINE FUEL, AVIATION (JET A1) (DLA ENERGY OCT 2017)

NATIONAL STOCK NUMBER PRODUCT NOMENCLATURE

DLA ENERGY PRODUCT

CODE

9130-00-753-5026 Turbine Fuel, Aviation, Jet A-1 JA1

Supplies delivered under this contract shall conform to all Federal, State, and local environmental requirements applicable to the geographic location of the receiving activity on the date of delivery. This includes delivery of fuel and documentation in a manner consistent with any existing or after-imposed Title V (Clean Air Act) Permits. The list of such requirements contained in this contract is not intended to be a complete list, and the Contractor shall be responsible for determining the existence of all such requirements. Selected regional environmental requirements are highlighted in the SPECIFICATIONS (CONT’D) clause. In the event that a Federal, State, or local environmental requirement is more stringent than a fuel specification contained in this contract, the Contractor shall deliver product that complies with the more stringent fuel specification. Product that fails to meet the more stringent fuel specification will be considered to be a nonconforming supply. Product(s) to be supplied shall fully meet the requirements of the applicable specification(s) as cited above. In the event that compliance with the more stringent fuel specification causes the contractor to incur additional costs, the contractor may request an equitable adjustment.

Product shall conform to the latest version of ASTM D1655: Standard Specification for Aviation Turbine Fuels with the following modifications. For European, Middle Eastern, and Asian Locations Only: product shall conform to the latest revision of Defence Standard 91-091.

(a) SPECIFICATION MODIFICATIONS

(1) Microseparometer (MSEP).

(i) The following MSEP ratings apply in the presence of the additives listed below. Values apply at point of manufacture:

Jet A-1 Additive MSEP Rating, min.

Fuel System Icing Inhibitor (FSII) 85

Corrosion Inhibitor/Lubricity Improver (CI/LI) 80 Fuel System Icing Inhibitor (FSII) and Corrosion Inhibitor/Lubricity Improver (CI/LI) 70

(b) ADDITIVES: Additives shall not be premixed with other additives before injection into the fuel.

(1) FUEL SYSTEM ICING INHIBITOR (FSII). When FSII is required by contract line item—

(i) The fuel shall contain 0.07 to 0.10 percent by volume FSII.

(ii) FSII shall be added to the fuel and shall be Diethylene Glycol Monomethyl Ether (DIEGME) conforming to ASTM D4171, Standard Specification for FSIIs, Type III or MIL-DTL-85470B, dated June 15, 1999 Inhibitor, Icing, Fuel System, High Flash, NATO Code Number S-1745.

(iii) When using the 20-ounce aerosol can to introduce FSII during over the wing refueling, determine the fuel quantity and calculate the amount of required additive. This additive shall be added gradually during filling to permit proper blending in the fuel. One can of aerosol additive will inhibit 180 gallons of fuel to 0.087 percent by volume. The use of aerosol FSII is not permitted for U.S. Navy aircraft refueling.

(2) CORROSION INHIBITOR/LUBRICITY IMPROVER (CI/LI). When CI/LI is required by contract line item the additive shall conform to the latest revision of MIL-PRF-25017H with amendment 1 dated August 4, 2011, and be listed in Qualified Products List (QPL)-25017. In order to obtain dosage data for QPL-25017 additives, log into ASSIST Online, access the Qualified Products Database (QPD), do a search for QPL number 25017, and click the MIL-PRF-25017 Category 1 link. The dosage information is located in the "source notes" for each qualified additive as minimum effective and maximum allowable concentrations in grams per cubic meter (g/m3).

(3) STATIC DISSIPATER ADDITIVE (SDA). When required by contract line item-

(i) SDA shall be added to the fuel and the conductivity limits of 50 to 600 picosiemens per meter (pS/m) at ambient temperature or

29.4oC (85oF), whichever is lower, unless otherwise directed by the procuring activity.

(4) METAL DEACTIVATOR ADDITIVE (MDA). MDA shall not be used unless the supplier has obtained written consent from the procuring activity and user.

(i) Product shall be homogeneously mixed. Until all aviation turbine fuel tanks are coated, it is acceptable to perform stratification tests in lieu of circulating tanks to achieve homogeneity.

2017-10-24T08:07:38-0400

WEDDELL.MARGARET.E.1502957461

2017-10-24T08:14:48-0400

BANISZEWSKI.DANIEL.J.1287388698

2017-10-24T09:00:27-0400

SHEPHERD.SANDRA.S.1012568459

DEFENSE LOGISTICS AGENCY ENERGY Page 1 of 5

C16.23 FUEL, NAVAL DISTILLATE (F-76) (DLA ENERGY APRIL 2020)

NATIONAL STOCK NUMBER PRODUCT NOMENCLATURE DLA ENERGY PRODUCT CODE

9140-00-273-2377 Fuel, Naval Distillate F76

For supplies delivered under this contract, the Contractor shall conform to all International, Federal, State, and local environmental requirements applicable to the geographic location of the receiving activity on the date of delivery. The Contractor shall also comply with all applicable International Agreements, Treaties, Conventions, and the like to which the United States is a signatory or with whose terms the receiving activity has otherwise agreed to comply, including but not limited to, the requirements of MARPOL 73/78 Annex VI Regulations 14 and 18. The Contractor shall be responsible for determining the existence of all such requirements prior to the time deliveries are made. This includes delivery of fuel and documentation in a manner consistent with any existing or after-imposed Title V (Clean Air Act) Permits. The list of such requirements contained in this contract is not intended to be a complete list, and the Contractor shall be responsible for determining the existence of all such requirements. In the event that an International, Federal, State, and/or local environmental requirement, as identified above, is more stringent than a requirement contained in this contract, the Contractor shall deliver product(s) that complies with the more stringent requirement. Product(s) that fails to meet the more stringent requirement will be considered nonconforming supply. Product(s) to be supplied shall fully meet the requirements of the applicable specification(s). In the event that compliance with the more stringent requirement causes the contractor to incur additional costs, the contractor may request an equitable adjustment.

Unless otherwise indicated by the Contractor in writing, prior to award, the product offered shall be required to fully meet all applicable specifications. The supplier shall provide to the receiving vessel a “Statutory Sample” of at least 400 mL in volume, taken from the receiving vessel’s inlet bunker manifold, together with a Bunker Delivery Note (BDN). This sample will be sealed and carry a sample tag that provides the documentation required per MARPOL 73/78, Annex VI Regulation 18.

a) Naval Distillate Fuel (F-76) shall conform to the requirements of Military specification MIL-DTL-16884P dated 26 Sept 2017.

Nomenclature for Naval Distillate Fuel (F-76) is shown above.

b) SPECIFICATION MODIFICATIONS:

1) Flash Point: All batches of F-76 that are presented for Government acceptance at origin shall meet a minimum flash point requirement of 62.5 degrees Celsius (°C).

2) F-76 offered from a location other than where refined (excludes synthesized material as defined in section 3.2.2 and 3.2.3 of MIL- DTL-16884P) requires testing for FAME content by test method ASTM D7963, BS EN 14078, or IP 579. ASTM D7963 is considered to be the referee test method.

3) In Australia, all deliveries of F-76 shall have a minimum Flash Point of 62.5°C at the custody transfer point.

c) MATERIALS: The F-76 supplied under this contract shall not contain un-hydrotreated light cycle oils or contain any stabilizer additives, or any other additive or material not explicitly allowed per section 3.2 of MIL-DTL-16884P.

For F-76 containing a synthetic component, the synthetic component shall be certified to Tables A-I and A-II of MIL-DTL-16884P. It is not necessary to analyze each batch of the synthetic component for compliance with Table A-II once it is demonstrated that the process scheme is adequately controlled and if no significant changes to existing production operations have been made, such as a turnaround event on a refinery unit used to produce the synthetic component or a change in feedstock material. The signed F-76 synthetic component certification page shall be supplied for each shipment which includes synthetic paraffinic materials attesting that no changes to the production process have been made and certifying that the last certificate of analysis, dated and including Table A- II results, is still valid.

d) ADDITIVES:

1) Lubricity Improver Additive (LIA) – Lubricity additives are allowed in F-76. The LIA additive(s) used shall conform to MIL-PRF-

32490A, Performance Specification, Additive, Lubricity Improver, Diesel, dated 24 May 2019 and found in ASSIST and shall be listed in the electronic Qualified Products List (QPL)-32490, located in the Qualified Products Database (QPD) found at https://assist.dla.mil/ (or http://quicksearch.dla.mil) . Instructions on how to use ASSIST are located in QAP C1.02. Either Grade A.

Grade B, or Grade C material is suitable for treatment of de-sulfurized F-76. Additive concentration shall not exceed the maximum allowable concentration applicable to the specific additive selected for inclusion in finished F-76.

2) Information pertaining to qualification of additives not currently listed on QPL-32490 may be obtained from Commander, Naval Sea Systems Command, ATTN: SEA 05S, 1333 Isaac Hull Avenue, SE, Stop 5160, Washington Navy Yard, DC 20376-5160, USA, or by e-mailing CommandStandards@navy.mil.

3) Dyes and Markers - Red dye required in off-highway diesel fuel in accordance with 40 CFR Part 80 as modified by the

DEFENSE LOGISTICS AGENCY ENERGY Page 2 of 5

Environmental Protection Agency's interim final rule published in the Federal Register dated July 14, 1994 shall not be added to F-

76. The finished product shall show no visual evidence of red dye. This F-76 product is for military, off-highway use only and must be segregated at all times from any diesel fuel used on-highway. NOTE: Red dye does not apply to Atlantic/Europe/Mediterranean or Western Pacific Overseas Bulk purchase programs unless offering refinery is located in the United States or one of its possessions.

e) BATCH SAMPLING: The Contractor shall provide one 20 mL sample per each individual tank in a procurement batch.

NOTE: This sample is in addition to those required in accordance with Quality Assurance Provision (QAP) E1

QUANTITY OF SAMPLE WHEN SAMPLED SUBMISSION PERIOD

20 mL Upon completion of each individual

Shipped within 30 days of delivery of

“Batch” Definition in accordance with MIL STD 3004, 3.1.9: A specific quantity of product that is processed or utilized as a single unit and tested to meet test criteria and specifications.

The sample from each tank/batch shall be either an all-level sample or a composite of upper, middle, and lower samples. A copy of the full-specification test report shall accompany each sample. The sample container will be any 20 mL amber borosilicate vial with a polytetrafluoroethylene (PTFE) lined screw cap. A tracking number for the samples shall be provided to: Thomas Loegel at Thomas.loegel@nrl.navy.mil or (202) 404-1157. Samples shall be shipped to:

US Naval Research Laboratory ATTN: Thomas Loegel, Code 6181 F76 Component Analysis Forensic Project 4555 Overlook Ave., S.W.

Washington D.C. 20375-5320

The paperwork provided with these samples shall include the following information:

Contract Number Contractor’s Name Product Refinery Location Quantity of Tank/Batch

For samples containing synthetic components, include the following additional information:

Manufacturer of synthetic component Batch Number Date of Test Report Quantity of Tank/Batch Percent Composition Production Process of Synthetic Component Feedstock

f) TRACEABILITY:

1) F-76 fuel supplied under this contract shall maintain traceability with respect to additives and materials, which is defined as the ability to trace the individual batch of fuel back to the original point of manufacture through documentation.

2) All traceability documentation shall be sufficient to guarantee that at no point have any unauthorized materials or additives been blended into the final product or any of its associated blend components per section 3.2 Material of MIL-DTL-16884P.

3) For all F-76 supplied, the traceability documentation shall consist of statement(s) attesting to the materials composition, which includes materials derived from non-petroleum sources, additives and their concentration levels. Additives and concentrations to be reported include LIAs outlined in section d.1 above and any trace additives resulting from existing tank heels, product trail-back in a multiproduct system, all product blending operations, etc.

DEFENSE LOGISTICS AGENCY ENERGY Page 3 of 5

4) If F-76 is produced by means of blending, the traceability requirement and documentation for additives and materials shall apply to each blending component used from the point of manufacture through the blend operation. Materials composition, additives and their concentration levels shall be included. The requirement and intent of traceability for blend components is not to obtain full certificates of analysis of each individual blend component, but for certification that no unapproved additives or materials are present in blend components used.

5) The form titled: “F-76 Traceability Signature Page” (attached below) shall be used to document conformance with the provisions of this traceability paragraph. The offeror/supplier shall comply with this requirement utilizing one of the three options below and notification shall be provided to both the contracting office and QT@dla.mil during the pre-award phase which option was chosen for compliance. Documents provided in conjunction with individual shipments shall be uploaded into Wide Area Work Flow as attachments under the quality tab.

i) OPTION 1 – As part of the offeror submission package the offeror shall provide the traceability signature page from each entity in the supply chain providing and/or handling F-76 product and/or blending components all the way back to the point of manufacture. For each individual shipment, the supplier will submit a traceability page signed only by the awardee.

ii) OPTION 2 – As part of the offer submission package the offeror shall provide the traceability signature page, signed only by the offeror. Upon award and prior to the first shipment the awardee shall provide the signed traceability signature page from each entity in the supply chain providing and/or handling F-76 product and/or blending components all the way back to the point of manufacture. For each individual shipment, the supplier will submit a traceability page signed only by the awardee.

iii) OPTION 3 – As part of the offeror submission package, the offeror shall provide the traceability signature page, signed only by the offeror. For each individual shipment, the awardee shall provide the signed traceability signature page from each entity in the supply chain providing and/or handling F-76 product and/or blending components all the way back to the point of manufacture.

Regardless of the option chosen, the traceability sheet signed by offeror shall be submitted to both the contracting office and to QT@dla.mil during pre-award phase.

For OPTION 1 or OPTION 2, the purpose of the awardee submitting a signed traceability page with each shipment is to confirm that the initial traceability certification is still valid at the time of F-76 product shipment.

6) If at any point during the contract period the traceability information provided under OPTION 1 or OPTION 2 becomes invalid (i.e.

the supply chain is altered or the source of F-76 product or a blending component changes), the supplier shall notify both the contracting office and QT@dla.mil and updated documentation shall be provided.

Quality / Technical Support Office Approval:

DEFENSE LOGISTICS AGENCY ENERGY Page 4 of 5

F-76 Traceability Signature Page

Contract or Solicitation Number:

CLIN:

Order Number:

Shipment Number:

Traceability OPTION selected per paragraph e.5 (circle or otherwise indicate which one of the three options is chosen):

OPTION 1 OPTION 2 OPTION 3

F-76 fuel supplied under the above contract, CLIN, order number and shipment number maintains traceability with respect the materials composition, additives and their concentration levels. This signed statement certifies that at no point have any unauthorized un- hydrotreated light cycle oils, other unauthorized materials, or additives been blended into the final product or any of its associated blend components per the most recent revision of MIL-DTL-16884 at date of contract award. All materials and additives are listed below. The percentage of each material as defined in sections 3.2, 3.2.2, and 3.2.3 (i.e. refined hydrocarbon distillate fuel, Fischer-Tropsch, Hydroprocessed Renewable Diesel, etc.) and the concentration level for each additive are also shown. For the purposes of the offeror submission this signed statement attests that no unapproved additives or materials will be added to batches or components of batches of F- 76 for delivery under government contracts.

Signature:

Printed Name:

Title:

Company Name:

Date:

Material Percent

Additive Concentration Responsible Party for Injection

DEFENSE LOGISTICS AGENCY ENERGY Page 5 of 5

F-76 Synthetic Component Certification

Contract or Solicitation Number:

CLIN:

Order Number:

Shipment Number:

Synthetic paraffinic materials supplied as indicated with the above contract, CLIN, order number, and shipment number is derived from either Fischer-Tropsch (FT) or Hydroprocessed Renewable Diesel (HRD) methods. This signed statement certifies that since the last certificate of analysis (COA), including table A-II or B-II results of MIL-DTL-16884P, Appendix A or B, no changes, including feedstock material, production location, or production processes have been made. In addition, no turnaround events have been executed on any units utilized to produce the synthetic paraffinic materials since the last COA, including table A-II or B-II, properties were tested. Please supply the date of the most recent COA and an identifying number for that report in the space provided below.

DATE OF COA: _

LAB REPORT ID NUMBER

Signature:

Printed Name:

Title:

Company Name:

Date:

2020-03-31T13:58:31-0400

GRIECO.DAVID.FRANK.1385613233

2020-03-31T14:07:44-0400

BANISZEWSKI.DANIEL.J.1287388698

2020-04-03T09:35:44-0400

CATLIN.JOSHUA.D.1276289540

SHEET 1 OF 11PREVIOUS EDITION IS USABLE Add Continuation Page

ENERGY QAP E1 September 2013

E1 CONTRACTOR INSPECTION RESPONSIBILITIES

(a) This contract provision applies to:

(1) All aviation fuel, lubricating oil, and additive shipments.

(2) All Bulk and Posts, Camps, and Stations non-aviation fuel shipments via pipeline or waterborne transport.

(b) QUALITY CONTROL PLAN.

(1) The Contractor is required to provide and maintain an inspection system, and a written description (Quality Control Plan

(QCP)) of that system, acceptable to the Government. The Contractor has the option to provide and maintain an inspection system that, as a minimum, incorporates the requirements of ISO9001, Quality Management Systems. If the Contractor chooses to comply with the ISO9001 quality system requirements and format, all the specific Quality Assurance Provisions of this contract must be included in the resulting ISO9001 document that will serve as the QCP. A copy of the QCP, in English, shall be presented to the Government Quality Assurance Representative (QAR) for their review and acceptance prior to commencement of production or services. An acceptable QCP is required prior to Government inspection and acceptance of supplies or services. The QCP shall be reviewed and updated when deemed necessary by the Contractor or the Government, to include changes necessary to prevent the recurrence of quality problems. The Contractor must sign and date the original QCP, as well as each subsequent revision. Revisions shall also be presented to the QAR for review and acceptance prior to implementation. When acceptable to the Government, the original QCP, and any revisions, shall be signed and dated by the QAR.

(2) The Contractor shall require subcontractors to provide and maintain inspection systems adhere to all the requirements in this contract provision.

(3) The QCP shall include the identification of key operational positions, a schematic diagram of plant facilities pertinent to the inspection system, indicating all inspection points, and a description of the following operations related to the supplies or services to be furnished under the contract:

(i) RECEIVING, BLENDING AND COMPOUNDING. Procedures used to ensure the quality of additives blended into product supplied under this contract. Procedures to identify and ensure the quality of component base stocks used to produce finished product.

Procedures to be used for adding, prior to batching, all required additives at all locations. When procedures for in-line blending of non-aviation products in accordance with the IN-LINE BLENDING OF NON-AVIATION PETROLEUM PRODUCTS contract provision are used, the QCP will provide for establishing blend ratios, and identify the responsible personnel within the Contractor's organization authorized to establish the blend ratios. When line injection of additives is required by the contract, the QCP will provide procedures for proportionately injecting additives throughout the entire loading process to ensure the additive is homogeneously blended into the product, as well as procedures for maintaining records evidencing the homogeneous blending of all line injected additives. In addition to the testing in (iii) below, a laboratory hand blend of jet fuel with all additives required by the contract shall be tested, prior to shipment, to verify compliance with the specification;

(ii) SAMPLING. Procedures for sampling additives, blend tanks, shipping tanks, lines, and conveyances/containers in accordance with API Manual of Petroleum Measurement Standards (MPMS), Chapter 8, Section 1, (ASTM D 4057) Manual Sampling of Petroleum and Petroleum Products, and/or Section 2, (ASTM D 4177) Automatic Sampling of Liquid Petroleum and Petroleum Products.

Procedures include sample location, frequency, quantity, and retention. For all tanker, barge, and pipeline shipments, a flow-proportional sample taken in accordance with MPMS Chapter 8, Section 2, is preferred at the custody transfer point. However, manual samples taken in accordance with MPMS Chapter 8, Section 1 are acceptable provided that they are taken hourly throughout the shipment and that the quantity of the composite sample meets the requirements in Table II of this contract provision. See Table I, Minimum Sampling and Testing Requirements, and Table II, Sample Retention;

(iii) TESTING. Types of test series and individual test methods/procedures to be performed on samples taken from each location identified in (ii) above. See Table I, Minimum Sampling and Testing Requirements, and Table III, Definitions of Test Series;

(iv) CALIBRATION. Program for testing and measuring equipment in accordance with ISO 10012, Measurement Manage

05/05/2014

DATEREVIEWED BY

04/14/2014

1:1

A

ENERGY QAP E1

SHEET 2 OF 11PREVIOUS EDITION IS USABLE Add Continuation Page

Systems - Requirements for Measurement Processes and Measuring Equipment, or equivalent local regulation, as appropriate;

and, a program for meters used to determine quantity complying with the API MPMS, Chapters 4, 5, and 6, or equivalent foreign standard. For items not covered by API, ASTM, or IP publications, the applicable manufacturer's recommended calibration method(s), outlined in the applicable industry publication, shall be used if acceptable to the Government;

(v) STORAGE AND HANDLING. Procedures for quality/quantity determination. Includes a description of storage and handling equipment, such as tanks, lines, valves, and manifolds; identification of dedicated/common product systems, including description of line segregation and controls to assure capability for proper gauging, sampling, draining of water, filtration, circulation, and drying; and identification of any other process/system used in maintaining product integrity during storage and handling;

(vi) LOADING AND SHIPPING - GENERAL. Procedures for product movement and related quality/quantity checks from shipping tank(s) to custody transfer point (CTP). Description of transfer system from shipping tank to CTP. A dedicated system, including lines, pumps, loading arms, and hoses, is preferred, but an isolated common system incorporating blind flanges, spectacle plates, or double valves between systems is acceptable. An isolated common system using single valves designed to ensure positive isolation, such as twin seal single valves, are also acceptable. Systems with single valve (other than twin seal) isolation require specific procedures be included in the QCP to ensure product integrity prior to the CTP. When single valves (other than twin seal) are present in the system, the Contractor shall provide their quality control procedures, from the first single valve to the CTP, at time of bid to the Contracting Officer for a determination of acceptability. Procedures for conditioning and testing of isolated systems that last carried a product other than that intended for movement under this contract. For in-line blending of non-aviation products, where approved in this contract, requirements must comply with the IN-LINE BLENDING OF NONAVIATION PETROLEUM PRODUCTS contract provision.

(vii) LOADING AND SHIPPING - TANK CARS, TANK TRUCKS, AND INTERMODAL CONTAINERS. For direct deliveries using Contractor-supplied tank cars and tank trucks in dedicated same grade aviation fuel service, refer to the section of API 1595 entitled “Loading of Road/Rail Cars” for loading and shipping procedures. All other tank car, tank truck, and intermodal container loadings shall be in accordance with the following procedures: Confirm all compartments have been prepared in accordance with Table IV, Conversion Chart for Tank Cars, Tank Trucks, and Intermodal Containers, below. Whenever possible, ensure the same preparation procedures used for compartments are applied to hoses, manifolds, etc. Ensure that conveyances carrying lubricating oil are dry and free from loose rust, scale, and dirt. Provide for investigation of discrepancies in either recorded quality or quantity. When required by the contract, seal conveyance and record seal numbers on the shipping document. Strainers and filters shall be located as near the loading or filling point as practicable and shall be used as outlined below for all deliveries except deliveries into tanker, barge, or pipeline.

(A) All aviation fuel shall be passed through strainers of 60 mesh or finer screen;

(B) All lubricating oil products, including preservatives, having a kinematic viscosity of 20.0 centistokes or less at 100 degrees Fahrenheit shall be passed through a 100 mesh or finer screen;

(C) All lubricating oil products, including preservatives, having a kinematic viscosity greater than 20.0 centistokes at

100 degrees Fahrenheit, but less than 22.0 centistokes at 210 degrees Fahrenheit, shall be passed through a 60 mesh or finer screen; and

(D) The Contractor shall furnish and periodically inspect strainers and filters pursuant to this paragraph to determine condition and perform maintenance as necessary, keeping a written record thereof.

(viii) LOADING AND SHIPPING - TANKERS AND BARGES.

(A) For f.o.b. destination Contractor-supplied tankers/barges. Procedures for the preparation of vessel cargo systems, in accordance with Energy Institute (EI) HM 50, Guidelines for the Cleaning of Tanks and Lines for Marine Tank Vessels Carrying Petroleum and Refined Products, that ensure the vessel is suitable to load the intended product(s).Particular attention should be given to vessels that previously carried a Fatty Acid Methyl Ester (FAME) cargo. As a minimum, f.o.b. destination Contractors must ensure that all cargo systems on the vessel intended for loading product under this contract, to include tanks, lines, manifolds, and pumps, are washed, gas freed, and inspected. In the event a solvent de-greaser is utilized in the tank preparation process, a minimum of two rinses must be performed by the vessel prior to loading Aviation Turbine Fuel. Vessels that will be carrying JP8 will be allowed to load without cleaning based upon the following criteria: the last cargo prior to loading JP-8 is Jet A/A1, and the second and third to last cargoes were clean middle distillate or lighter petroleum products (no black oils, lubricating oils, vegetable oils, palm oils, biodiesel with FAME content greater than or equal to 15 % or other similar products). The vessel will drop all lines and strip dry all cargo tanks of the previously carried Jet A/Jet A1 prior to loading JP-8. These procedures, and others deemed necessary by the Contractor, shall be included to ensure that the product meets the specification requirements at the CTP.

SHEET 3 OF 11PREVIOUS EDITION IS USABLE Add Continuation Page

(B) For f.o.b. origin Government-supplied tankers/barges. Procedures for maintaining a time log of all significant events/delays including vessel notice of readiness, vessel arrival, mooring, vessel deballasting, inerting and conditioning of cargo tanks, inspections, hose connections and disconnections, starts, stops, vessel release, or any other event that affects laytime of the vessel. Procedures for assuring condition of loading line (full of tested product, all air bled, and pressure packed) and gauging shore tanks, both before and after loading.

In the event an automated metering system is to be used as the means of shore quantity determination, manual gauges of all storage tanks designated for shipment shall be taken prior to commencement of loading. Procedures for preload discussion between Contractor, vessel, and QAR to include, but not be limited to, prior two cargoes, cleaning procedures, loading plan, loading rates, sampling requirements, and after loading sampling and gauging. [Prior to loading - gauge, sample, and test intransit cargoes designated for load on top. Gauge and sample (1 gallon) any other product on board, except for JPTS, and retain those samples.] All cargo quantities shall be calculated and volume corrected both before and after loading. Procedures for commencement of loading into one tank (up to 3 feet), then switching to at most two other vessel tanks while first-in sampling and testing is being accomplished (Table I). Procedures for the transportation of samples from the vessel to the testing facility.

Monitoring the loading (including line blending and additive injection) from source to vessel, investigating irregularities immediately and stopping loading, if necessary. Procedures for investigating discrepancies in quality (mandated if off-specification or out of testing tolerance) and quantity (mandated if shore to ship variance is in excess of the following: 0.2% (0.002) for cargos not requiring cleaning, gas freeing, or drop/strip; 0.3% (0.003) for cargos requiring drop/strip; or 0.5% (0.005) for cargos requiring cleaning and gas freeing, or figures are suspect) on loaded conveyance.

(C) For both f.o.b. origin and destination tankers/barges. Procedures for immediately notifying the QAR when irregularities occur or are suspected, and on all occasions when loading is interrupted. Authority to release a Government-furnished vessel rests with the Government QAR after compliance and completion by the Contractor of all required operations, including the preparation of the DD Form 250-1.

(ix) RECORDS AND REPORTS. Procedures for completing and distributing required documentation both prior to and after the release of the vessel. Documentation shall include, as a minimum, test reports for all products and additives, additive blending and/or injection records, vessel notice of readiness, customs documents, bills of lading, vessel ullage reports, and the DD Form 250/DD Form 250-1 and continuation sheet(s) (or the Paperless Ordering and Receipt Transaction System [PORTS] or equivalent). Other documentation may be required on an as needed basis, such as vessel port logs, calibration records, and results of quality or quantity discrepancy investigations. These records and reports will include by whom, where, and how they were prepared, as well as retention information. The DD Form 250-1 and DD Form 250-1 continuation sheet(s) will be signed by the Contractor and the vessel representative in the appropriate blocks before presenting them to the QAR for signature. The DD Form 250 and DD Form 250-1 shall identify the type, brand name, and amount of all additive(s).

(x) CORRECTIVE ACTION. Actions to be followed to effect correction of any deficiency affecting product quality or quantity, such as handling of off-specification product (waivers, conveyance rejections, etc.). The corrective action procedures shall include notification of the QAR.

(4) The QCP shall identify one individual to serve as a point of contact for quality/quantity matters relating to the inspection system description in the plan.

(5) The Contractor is responsible for all inspection systems, QCPs, and product quality and quantity.

(c) The Contractor shall perform all inspections and acceptance tests required by the specifications of the supplies to be furnished under this contract or, shall have such tests performed, in a laboratory acceptable to the Government. For f.o.b. destination Contractor-supplied tankers/barges, the Contractor shall provide the QAR, prior to the first shipment, with the name and location of the laboratory to be used for testing at each discharge point. The Contractor shall also notify the QAR of any subsequent laboratory changes prior to the affected shipments. If any laboratory is determined to be unacceptable to the Government, the Contractor must designate another laboratory that is acceptable, before acceptance testing can take place. Acceptance tests will normally be performed at the acceptance point. However, when such tests are performed at origin on supplies to be accepted at destination, documentation that will enable verification of the original test results shall be provided to the Government prior to acceptance at destination. Regardless of the method of delivery, products furnished under this contract must meet all specification requirements at the CTP.

SHEET 4 OF 11PREVIOUS EDITION IS USABLE Add Continuation Page

(d) Prior to loading, the Contractor shall inspect all shipping conveyances for suitability to load the supplies furnished under this contract, except for Government-furnished tankers and barges Authorization for the Contractor to participate in the inspection of Government-supplied tankers and barges rests with QAR. The QAR has the right to inspect any Government-supplied conveyance prior to loading and, in the event the Contractor and the QAR disagree on the suitability to load such a conveyance, the determination of the QAR shall govern.

This is the start of the file's text. The full file is on GovTribe.