Att 4 - Specifications - Grand Junction Data Center CD Set - UPDATED.pdf
PDF 7 MB Posted
- Attached to
- 575-221 - EHRM Infrastructure Upgrades Construction - Tier 2 Data Center - Grand Junction, CO Federal contract opportunity
- Solicitation number
- 36C77625B0038
About this file
This file is a comprehensive set of technical specifications for an electrical infrastructure upgrade project at the Grand Junction VA Medical Center. The project involves constructing a new Tier 2 Data Center, encompassing approximately 3,317 square feet of renovation and new construction, with a focus on electrical, mechanical, and technology infrastructure upgrades.
The specifications cover detailed requirements for electrical systems, including grounding and bonding, low-voltage conductors, power distribution, and communications infrastructure. Key technical components include installation of new electrical panels, cable trays, conduit systems, and specialized grounding equipment. The project follows strict VA and industry standards, with specific requirements for cable color coding, equipment identification, safety protocols, and commissioning procedures. The electrical work is part of a broader data center infrastructure upgrade, with emphasis on maintaining high reliability, safety, and performance standards for critical VA healthcare facility systems.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
06-01-23
EHRM DATA CENTER, GRAND JUNCTION VAMC (CD SET)
PROJECT # 575-221
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21
01 33 23 Shop Drawings, Product Data, and Samples 02-23
01 35 26 Safety Requirements 10-22
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 01-21
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 31 00 Steel Decking 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 Bituminous Dampproofing 01-21
07 22 00 Roof and Deck Insulation 01-21
00 01 10-2
07 24 00 Exterior Insulation and Finish Systems 01-21
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 72 00 Roof Accessories 01-21
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 51 13 Aluminum Windows 01-21
08 56 53 Blast Resistant Windows 01-21
08 71 00 Door Hardware 05-22
08 80 00 Glazing 01-21
08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes 01-21
09 29 00 Gypsum Board 04-20
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 01-21
09 65 19 Resilient Tile Flooring 05-18
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21
10 26 00 Wall and Door Protection 01-21
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16
21 13 13 Wet-Pipe Sprinkler Systems 06-15
21 22 00 Clean Agent Fire Suppression Systems 05-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 01-23
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 13 00 Facility Sanitary and Vent Piping 09-20
22 14 00 Facility Storm Drainage 09-15
00 01 10-3
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
03-23
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
03-23
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 03-23
23 09 23 Direct-Digital Control System for HVAC 03-23
23 23 00 Refrigerant Piping 03-23
23 31 00 HVAC Ducts and Casings 03-23
23 34 00 HVAC Fans 03-23
23 36 00 Air Terminal Units 03-23
23 37 00 Air Outlets and Inlets 03-23
23 72 00 Air-to-Air Energy Recovery Equipment 03-23
23 81 00 Decentralized Unitary HVAC Equipment 03-23
23 81 23 Computer-Room Air-Conditioners 03-23
23 81 43 Air-Source Unitary Heat Pumps 03-23
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 05 39 Underfloor Raceways for Electrical Systems 11-22
26 05 41 Underground Electrical Construction 11-22
26 05 73 Overcurrent Protective Device Coordination Study 11-22
26 08 00 Commissioning of Electrical Systems 11-22
26 09 23 Lighting Controls 11-22
26 22 00 Low-Voltage Transformers 11-22
26 24 13 Distribution Switchboards 11-22
26 24 16 Panelboards 11-22
26 26 00 Power Distribution Units for Static Uninterruptible
Power Systems
11-22
26 27 26 Wiring Devices 11-22
26 29 11 Motor Controllers 11-22
26 29 21 Enclosed Switches and Circuit Breakers 11-22
26 33 53 Static Uninterruptible Power Supply 11-22
26 41 00 Facility Lightning Protection 11-22
26 43 13 Surge Protective Devices 11-22
26 51 00 Interior Lighting 11-22
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
00 01 10-4
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 08 00 Commissioning of Communications Systems 11-16
27 11 00 Telecommunications Room Fittings 06-15
27 11 26 Communications Rack Mounted Power Protection and Power
Strips
06-23
27 13 23 Communications Optical Fiber Backbone Cabling 08-23
27 15 00 Communications Structured Cabling 01-16
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 13 00 Physical Access Control System 10-11
28 16 00 Intrusion Detection System 10-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16
31 63 33 Drilled Micropiles 01-21
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
32 31 40 High Security Fences and Gates 08-16
DIVISION 33 – UTILITIES
33 08 00 Commissioning of Site Utility Systems 11-16
33 10 00 Water Utilities 03-17
33 30 00 Sanitary Sewer Utilities 06-13
DIVISION 34 – TRANSPORTATION
34 71 13 Passive Vehicle Barriers 04-18
05-01-20
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
CIVIL
ARCHITECTURAL
STRUCTURAL
PLUMBING
MECHANICAL
FIRE
ELECTRICAL
- - - END - - -
00 01 15 - 2
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
CS001 Cover Sheet
CS002 Risk Assessment
CS003 IT Security Checklist
CS004 General Notes, Symbols, Abbreviations
CS005 Architectural Location Plan
LP101 First Floor Life Safety Plan and Bldg Analysis
HA101 General Information Site Plan
HA102 1st Floor Asbestos Abatement Plans
HA103 Conceptual Sequencing Major Construction Plan
CIVIL
C100 Civil Notes
C101 Utility/Demolition Site Plan
C102 Civil Gate Design
STRUCTURAL
S-001 General Structural Notes
S-002 General Structural Notes
S-003 Special Inspections
S-010 Legends and Abbreviations
S-101 Footing and Foundation Plan
S-111 Roof Framing Plan
S-501 Details
S-502 Details
S-511 Details
S-601 Schedules
S-602 Schedules
ARCHITECTURAL
AD101 First Floor Demolition Plan
00 01 15 - 3
AD102 First Floor Reflected Ceiling Demolition Plan
AE101 First Floor Plan
AE102 First Floor Reflected Ceiling Plan
AE103 Roof Plan
AE104 Equipment Plan
AE201 Exterior Elevations
AE301 Building Sections
AE303 Wall Sections
AE501 Architectural Details
AE601 Door and Window Schedules
AI101 First Floor Room Finish Plan and Schedule
FIRE
FA101 1st Floor Fire Alarm Plan
FA601 Fire Alarm Riser
FX101 Level 1 Fire Protection Plan
PLUMBING
PE001 Plumbing Cover Sheet
PE501 Plumbing Details and Schedules
PD101 Level 1 Plumbing Demo Plan
PL101 Level 1 Plumbing Plan – DWV
PL102 Level 1 Plumbing Plan – Water
MECHANICAL
ME001 Mechanical Cover Sheet
ME501 Mechanical Details
ME601 Mechanical Schedules
ME602 Mechanical Schedules
ME603 VRF Schematic
MD101 Level 1 Mechanical Demo Plan
MH101 Level 1 Mechanical Plan
MH102 Roof Mechanical Plan
MP101 Level 1 Mechanical Piping Plan
ELECTRICAL
EE001 Electrical Cover Sheet
00 01 15 - 4
EE002 Symbols Legend
EE003 Telecom Schedules and Notes
EE004 Auxiliary Schedules and Notes
EE501 Electrical Details
EE601 Grounding Riser Diagram
EE701 Typical Mounting Details
EE702 Typical Labeling Details
EE703 Typical Labeling Details
ES101 Electrical Site Plan
ES501 Electrical Site Details
ED101 1st Floor Electrical Demolition Plan
ED102 1st Floor Electrical Feeder Demolition Plan
EP101 1st Floor Power Plan
EP102 1st Floor New Electrical Feeder Plan
EP103 Roof Power Plan
EP201 Power Elevations
EP600 One-Line Diagram Schedules
EP601 Demolition One-Line Diagram
EP602 New One-Line Diagram
EP603 Electrical Schedules
EP604 Panel Schedules
EP605 Panel Schedules
EL101 1st Floor Lighting Plan
EL102 1st Floor Emergency Egress Photometric Plan
EL601 Interior Lighting Fixture Schedule
EL604 Lighting Control Schedules
ET101 1st Floor Telecom Plan
ET102 1st Floor Lower Cable Raceway Plan
ET103 1st Floor Upper Cable Raceway Plan
ET401 Telecom Enlarged Plans
ET501 Telecom Equipment Cabinet Elevations
ET502 Telecom Equipment Cabinet Elevations
ET503 Telecom Details
ET504 Telecom Cable Tray Details
ET505 Equipment Rack Grounding Detail
ET506 Telecom Cable Tray Details
ET507 Telecom Equipment Rack Grounding Detail
00 01 15 - 5
ET601 Telecom Cable Riser Diagram (Server Room 107)
ET602 Telecom Riser Diagrams
EY101 Level 1 Auxiliary Plan
EY501 Auxiliary Details
EY601 Auxiliary Riser Diagrams
EK101 Lightning Protection Plan
EK501 Lightning Protection Details
EK502 Grounding Details
- - - E N D - - -
11-01-21
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Grand Junction
EHRM Data Center as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the Contracting Officer Representative (COR).
C. Offices of RDC+EA, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the
Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection.
Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
F. Communication: All communications relating to the process of construction, including Requests for Information, shall be directed to and from the Contracting Officer’s Representative.
01 00 00 -2
Requests for Information shall be submitted in the Contractor’s standard format. All contractual direction shall come from the
Contracting Officer.
G. Laying out construction progress meeting frequency and duration.
Note that day of the week or month and starting time shall be determined at the pre-construction (kick-off) meeting. Note that the agenda shall be established by the COR.
H. Weekly construction progress meetings, lasting approximately 1 hour will be held. Contractor shall establish agenda, hold the meeting, and publish meeting minutes.
I. Normal working hours for this contract will be from 7:00AM to
4:30PM MST Monday through Friday except for weekends and established Federal Holidays.
J. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR. Requests shall be submitted via email at least 14 days prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID / Work includes general construction, alterations, roads, walks, grading, drainage, necessary removal of existing structures and construction and certain other items.
B. • General Description: Location; Composed of but not limited to the following elements:
C. • Civil Work (Stormwater collection, geotextile, piles, steam lines, high voltage electrical, foundations.)
D. • Landscape to include TESC, plant materials installation, hardscape material, irrigation
E. • Architectural work, structural work, electrical work, mechanical work.
01 00 00 -3
F. • In the summary of work, highlight work restrictions (hours, days of week, noise, security requirements, and other elements that would affect the price of work for the contractor.
1.4
Scope of Work
The scope of this project consists of design and construction management services for the renovation of approximately 2,000 Sq. Ft.
for OIT administration offices and adding a new addition of approximately 1,317 Sq. Ft. for a new Data Center for the EHRM
Infrastructure Upgrades - Data Center project 575-221. The design phase of this project includes site visits, field investigation, studies and user interviews to prepare drawings, specifications and cost estimates to upgrade the facility’s EHRM infrastructure. If elected, the solicitation and construction phase of this project includes responding to RFIs, reviewing submittals and shop drawings, maintain logs and due dates, attending meetings, take minutes, perform inspection site visits, commission new equipment, and provide as-builts at project completion.
1.5 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at
Contractor's expense.
1.6 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Procedures to conform with Station Policy 132-5
Security Management Program. Recertification date: 12/31/2024 and Station Policy 138-0011 Failure of Essential Medical Center
Equipment or Utility. Recertification Date: 08/31/2026.:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
3. Notify VA Police at extension 970-242-0731 ext 2178 of:
01 00 00 -4
a. All assaults.
b. Any disturbance: a loud and/or angry patient, visitor or co-worker.
c. Threatened or actual suicides.
d. Homicides.
e. All thefts of government or personal property.
f. Vandalism of government or personal property.
g. All threats.
h. All motor vehicle accidents.
i. Intoxicated individuals
4. Assist in safeguarding government and personal property at this medical center.
a. Confirm any individuals not authorized or of concern in specific work areas. Approach individual and ask, "May I help you?" Provide guidance as necessary to direct visitor to authorized location. If visitor is uncooperative in any way, notify VA Police immediately.
b. Secure all work areas prior to departure at the end of the workday, or when area will not be occupied.
5. Not ever prop open a door that is otherwise locked from the outside.
6. Notify Engineering Service as soon as possible, in the event of a failure of essential Medical Center equipment or significant utility service (A/C, Boilers, Electrical, Elevators, Fire Alarm Systems, Fire Sprinkler System, Medical
Air/Vacuum, Waste, and Water)
a. Site Superintendent shall notify COR OR
b. OR Notify Engineering at 970-242-0731 ext 2002, during normal working hours.
c. OR Notify Engineering Central Utility Plant at ext. 1311 or 1322 after regular working hours, holidays, and weekends.
01 00 00 -5
d. OR Notify AOD after regular working hours, holidays, and weekends at ext 2121.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the COR so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the COR. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the
Contracting Officer.
C. Key Control Procedures to conform with Station Policy 138-1002
Control of Keys and Security Locks. Recertification Date:
12/31/2026:
1. The General Contractor shall provide duplicate keys and lock combinations to the VAPD and / or Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall install all permanent cores at completion of the work See Section 08 71 00, DOOR HARDWARE and coordinate.
3. If the Contractor is issued a facility key, the designated key holder shall:
01 00 00 -6
1) Read, verify, complete, and sign the "Key Receipt Memo.”
2) Maintain the security of keys issued to them.
3) Return keys in to Engineering when no longer needed.
4) Report lost, stolen, or misplaced keys to Engineering via lost key memo. The Contractor may be charged for lost keys and necessary lock changes.
D. Document Control:
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting
Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of
Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the
VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
01 00 00 -7
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted
24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. Motor Vehicle Restrictions: Contractor staff shall park off site. Exterior space is very limited. Contractor may deliver materials to site on an as-needed basis. Contractor shall not bring materials onsite until they can be immediately off-loaded the vehicle taken off site. Contractor may store materials within work area under contractor’s control.
Location of dumpsters shall be coordinated with COR at pre-construction meeting.
3. Other than pick up and drop activities previously identified, all contractors must park off campus.
F. Workers are subject to rules of Medical Center applicable to their conduct.
a. In conformance with Station Policy 05-41: Dress code.
1) Clothing and accessories may not reflect political statements, offensive materials, or present a safety hazard.
2) Tattoos that are considered inappropriate or offensive by the Reasonable Person Standard must be covered at all times while on Station. These include but are not limited to gang related images, racially inappropriate, sexually
01 00 00 -8 suggestive, refers to intolerance or discrimination against any race, color, creed, religion, gender, origin, sexual orientation, or groups that advocate such intolerance or behavior.
3) Clothing must cover person from neck to ankle and from mid-upper arm to shoulder and be opaque.
1.7 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the COR, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the COR.
When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
01 00 00 -9
D. Working space and space available for storing materials shall be as shown on the drawings.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR .
All such actions shall be coordinated with the COR or Utility
Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, 01 00 00 -10 electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the
Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, and Contractor, as follows:
Phase I:
Build a new data center. Build a new entry room. Refinish OIT reception room. Upgrade electrical system to support new data center.
Provide new CRAC units and HVAC to support the new data center. Old data center is to remain operational during phase 1. Also, open office space is to remain functional during construction of phase 1.
Contractor to provide protection for access to and from said spaces during construction. General contractor is connecting all campus data to new data center and is to commission data center before phase 2 is to begin.
01 00 00 -11
Phase II:
Demolish old data center and remaining office space. Build new office space as shown in the drawings. Reception room and new data center are to remain operational during the construction of this phase.
3. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical
Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
4. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m
(seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum
375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
K. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
01 00 00 -12
1. Contractor shall maintain a minimum temperature of 4 degrees C
(40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company
(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. Any outage will require
Station Facilities Management to coordinate with multiple other services, develop mitigation plans, and get approvals for the final concept.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR .
Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11
REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, 01 00 00 -13
COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. The Station needs at least 30 business-days-notice of a potential outage of any size. Formal submission must be made
15 days in advance, after coordination with the COR. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical
Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major outages (more than 4 hours) require 60 days-notice, to allow rescheduling patient appointments if required. Major outages must be shown on the initial construction schedule, or be added to the schedule as soon as the requirement is known.
In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
5. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, 01 00 00 -14 or within walls or partitions; so that they are completely behind the finished surfaces.
N. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
1.8 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply
Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
01 00 00 -15
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled
"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
01 00 00 -16
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.9 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
01 00 00 -17
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant
Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the
01 00 00 -18 permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the Engineering and Safety Offices. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials;
and
5. Providing adequately maintained sanitary facilities.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
01 00 00 -19
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems
(including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS"
(FAR 52.236-2).
1.11 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the
Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.12 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own
01 00 00 -20 expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work.
The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the
Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through
Contractor's negligence before their removal is authorized, the
Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the
Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark
(through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, 01 00 00 -21 floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
4. Lines of elevations of all swales and interment areas.
5. Lines and elevations of roads, streets.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
01 00 00 -22
G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".
1.13 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.14 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of
Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan.
Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved.
Warranty information made available during the construction phase
01 00 00 -23 must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended
01 00 00 -24 warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and
Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.