Att 01_Schedule of Items (250520).docx
DOCX document 47 KB Posted
- Attached to
- Hiawatha NF GAOA Grand Island Trails Improvement
- Solicitation number
- 12445525Q0061
- Issued by
-
Department of Agriculture Forest Service
About this file
The document is a Schedule of Items for the Munising Ranger District/Hiawatha National Forest's Grand Island Trail Rim Improvement project, scheduled to start on 6/30/2025. The comprehensive project involves extensive trail reconstruction and maintenance across 21 different sites, including approximately 2.5 miles of linear trail grading, culvert installations/replacements, and site rehabilitation. Specific work includes establishing new drainage ditchlines, trail surface retreading, clearing and grubbing vegetation, installing 14 culverts of various sizes (ranging from 18" to 38" diameter), and performing site restoration through seeding and topsoil placement.
Key technical details include trail improvements with 12' standard width, drainage management with 2' wide and 2' deep ditchlines, culvert installations at varying burial depths (2-15 feet), and environmental considerations such as riprap placement and silt fence installation for erosion control. The project will require mobilization, material stockpiling (including up to 200 cubic yards of MDOT 23A material, 10 cubic yards of Class III riprap, and 200 cubic yards of screened topsoil), and is part of the Great American Outdoors Act (GAOA) funded infrastructure improvements for the Hiawatha National Forest. The solicitation is issued by the Department of Agriculture Forest Service, with the specific solicitation number 12445525Q0061.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 30 (11_2016).pdf | ||
| 12445525Q0061.pdf | ||
| Att 04_GI Trail Maps.docx | DOCX document | |
| Att 02_SOW (250520).docx | DOCX document | |
| Att 03_GI Rim Trail Culvert Plan.pdf | ||
| Att 05_Trail Design Parameters.pdf | ||
| Att 06_Standard Trail Detail Sheets Combined.pdf | ||
| Att 07_EGLE Permit.pdf | ||
| Att 08_Wage Determination MI20250001 05.16.2025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF ITEMS
MUNISING RANGER DISTRICT/HIAWATHA NATIONAL FOREST PROJECT TITLE:
GAOA GRAND ISLAND TRAIL RIM IMPROVEMENT
WORKPLAN ACQUISITION PLAN/REQUISITION NO: 663149/1089299
Anticipated Start Date 6/30/2025
| ITEM NUMBER |
| DESCRIPTION |
| PAY UNIT |
| UNITS |
| COST/UNIT |
| EST QTY |
| 1 |
| Grand Island Rim Trail Improvements Site 1: Trail |
Drainage Improvement and Site Rehabilitation
A.
Linear Grade (approximately 0.02 miles) - Establish new ditchlines approximately 2' wide by 2' deep for runoff. Retread 12' wide trail surface with centerline crown or offslope toward ditchline. Install outlet ditches at low points and intermittently along steeper slopes. Clear and grub to 18' wide by 10' high from trail centerline. Haul and spread a TBD quantity of MDOT 23A (if any) as determined by the COR.
Lump Sum
| B. |
| Rehabilitation of Site/Seeding. (Approximately 0.02 miles) |
| Lump |
Sum
| Total |
| Dollars |
| 2 |
| Grand Island Rim Trail Improvements Site 2: Culvert |
Installation and Site Rehabilitation
| A. |
| Culvert: 18" (Dia.) by 25' (L) Round Galvanized CMP. |
| Lump |
| B. |
| Installation of culvert (approximately 2-3 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
C.
Linear Grade (approximately 0.02 miles) - Establish new ditchlines approximately 2' wide by 2' deep for runoff. Retread 12' wide trail surface with centerline crown or offslope toward ditchline. Install outlet ditches at low points and intermittently along steeper slopes. Clear and grub to 18' wide by 10' high from trail centerline. Haul and spread a TBD quantity of MDOT 23A (if any) as determined by the COR.
| D. |
| Rehabilitation of Site/Seeding (approximately 0.02 miles) |
| Lump |
| Total |
| Dollars |
| 3 |
| Grand Island Rim Trail Improvements Site 3: Trail Drainage Improvement/Timber Post and Rail Fence |
Installation/Site Rehabilitation
Linear Grade (approximately 0.28 miles) - Establish new ditchlines approximately 2' wide by 2' deep for runoff. Retread 12' wide trail surface with centerline crown or offslope toward ditchline. Install outlet ditches at low points and intermittently along steeper slopes. Clear and grub to 18' wide by 10' high from trail centerline. Haul and spread a TBD quantity of MDOT 23A (if any) as determined by the COR.
Note: Trail shall be widened near eroded area to accomodate 12' standard width.
| B. |
| Install 40' of timber post and rail fence at designated location. |
| Lump |
| C. |
| Rehabilitation of Site/Seeding (approximately 0.28 miles) |
| Lump |
| Total |
| Dollars |
| 4 |
| Grand Island Rim Trail Improvements Site 4: Culvert |
Replacement
| A. |
| Culvert: 36" (Dia.) by 45' (L) Round Galvanized CMP |
| Lump |
| B. |
| 36" Galvanized End Section (Installed at inlet end) with Hugger |
Bands Lump
| C. |
| Installation of culvert (approximately 5-10 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
| D. |
| Rehabilitation of Site/Seeding (approximately 0.02 miles) |
| Lump |
| Total |
| Dollars |
| 5 |
| Grand Island Rim Trail Improvements Site 5: Trail |
A Linear Grade (approximately 0.05 miles) - Establish new ditchlines approximately 2' wide by 2' deep for runoff. Retread 12' wide trail surface with centerline crown or offslope toward ditchline. Install outlet ditches at low points and intermittently along steeper slopes. Clear and grub to 18' wide by 10' high from trail centerline. Haul and spread a TBD quantity of MDOT 23A (if any) as determined by the COR.
| B. |
| Rehabilitation of Site/Seeding (approximately 0.05 miles) |
| Lump |
| Total |
| Dollars |
| 6 |
| Grand Island Rim Trail Improvements Site 6: Trail |
Linear Grade (approximately 0.09 miles) - Establish new ditchlines approximately 2' wide by 2' deep for runoff. Retread 12' wide trail surface with centerline crown or offslope toward ditchline. Install outlet ditches at low points and intermittently along steeper slopes. Clear and grub to 18' wide by 10' high from trail centerline. Haul and spread a TBD quantity of MDOT 23A (if any) as determined by the COR.
| B. |
| Rehabilitation of Site/Seeding - (approximately 0.09 miles) |
| Lump |
| Total |
| Dollars |
| 7 |
| Grand Island Rim Trail Improvements Site 7 (Site #47 on Plan Set): Culvert Replacement, Permitted EGLE Crossing |
| A |
| Culvert: 29" (H) by 45" (W) by 24' (L) Galvanized Elliptical |
CMP
Lump
B.
Installation of culvert (approximately 2-3 foot burial depth). Surface with 4 cubic yards of MDOT 23A. Place 2 cubic yards of Class III riprap above Class II nonwoven geotextile at pipe outlet (See Plan Set).
Rehabilitation of Site/Seeding (approximately 0.02 miles). Spread 4 cubic yards of topsoil along offsloped areas before seeding. Install 100 linear feet of silt fence as erosion control (See Plan Set).
| Total |
| Dollars |
| 8 |
| Grand Island Rim Trail Improvements Site 8: Culvert |
| A |
| Culvert: 18" (Dia.) by 25' (L) Round Galvanized CMP |
| Lump |
| B. |
| Installation of culvert (approximately 3-6 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
| C. |
| Rehabilitation of Site/Seeding (approximately 0.02 miles) |
| Lump |
Total
| 9 |
| Grand Island Rim Trail Improvements Site 9 (Site #48 on Plan Set): Culvert Replacement, Permitted EGLE Crossing |
| A |
| Culvert: 38" (H) by 60" (W) by 32' (L) Galvanized Elliptical |
CMP
Lump
| B. |
| Installation of culvert (approximately 5-7 foot burial depth). |
Surface with 4 cubic yards of MDOT 23A.
Lump
Rehabilitation of Site/Seeding (approximately 0.02 miles). Spread 4 cubic yards of topsoil along offsloped areas before seeding. Install 125 linear feet of silt fence as erosion control (See Plan Set).
| Total |
| Dollars |
| 10 |
| Grand Island Rim Trail Improvements Site 10: Trail |
Linear Grade (approximately 0.19 miles) - Establish new ditchlines approximately 2' wide by 2' deep for runoff. Retread 12' wide trail surface with centerline crown or offslope toward ditchline. Install outlet ditches at low points and intermittently along steeper slopes. Clear and grub to 18' wide by 10' high from trail centerline. Haul and spread a TBD quantity of MDOT 23A (if any) as determined by the COR.
| B. |
| Rehabilitation of Site/Seeding (approximately 0.19 miles) |
| Lump |
| Total |
| Dollars |
| 11 |
| Grand Island Rim Trail Improvements Site 11 (Site #50 on Plan Set): Culvert Replacement, Permitted EGLE Crossing |
| A |
| Culvert: 36" (Dia.) by 36' (L) Round Galvanized CMP |
| Lump |
B.
Installation of culvert (approximately 5-10 foot burial depth). Surface with 5 cubic yards of MDOT 23A. Place 6 cubic yards of Class III riprap above Class II nonwoven geotextile at pipe inlet (See Plan Set).
Rehabilitation of Site/Seeding (approximately 0.02 miles). Spread 10 cubic yards of topsoil before seeding at offsloped areas. Install 150 linear feet of silt fence as erosion control (See Plan Set).
| Total |
| Dollars |
| 12 |
| Grand Island Rim Trail Improvements Site 12: Trail |
Linear Grade (approximately 0.66 miles) - Establish new ditchlines approximately 2' wide by 2' deep for runoff. Retread 12' wide trail surface with centerline crown or offslope toward ditchline. Install outlet ditches at low points and intermittently along steeper slopes. Clear and grub to 18' wide by 10' high from trail centerline. Haul and spread a TBD quantity of MDOT 23A (if any) as determined by the COR.
| B. |
| Rehabilitation of Site/Seeding (approximately 0.66 miles) |
| Lump |
| Total |
| Dollars |
Grand Island Rim Trail Improvements Site 13: (Originally Site #57): Walking Bridge Cleanout
| A. |
| Excavate sediment deposits to increase drainage below bridge. |
| Lump |
| Total |
| Dollars |
Grand Island Rim Trail Improvements Site 14: (Originally Site #58): Culvert Replacement *Option Item*
| A. |
| Culvert: 36" (Dia.) by 53' (L) Round Galvanized CMP |
| Lump |
| B. |
| Installation of culvert (Approximately 10 -15 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
| C. |
| Rehabilitation of Site/Seeding (approximately 0.02 miles) |
| Lump |
Total
| 15 |
| Grand Island Rim Trail Improvements Site 15: (Originally Sites 40, 41, 42, 43 and 44): Trail Drainage Improvement |
and Site Rehabilitation
Linear Grade (approximately 0.66 miles) - Establish new ditchlines approximately 2' wide by 2' deep for runoff. Retread 12' wide trail surface with centerline crown or offslope toward ditchline. Install outlet ditches at low points and intermittently along steeper slopes. Clear and grub to 18' wide by 10' high from trail centerline. Haul and spread a TBD quantity of MDOT 23A (if any) as determined by the COR.
| B. |
| Rehabilitation of Site/Seeding (approximately 0.66 miles) |
| Lump |
Total
| 16 |
| Grand Island Rim Trail Improvements Site 16: Culvert |
| A. |
| Culvert: 18" (Dia.) by 28' (L) Round Galvanized CMP. |
| Lump |
| B. |
| Installation of culvert (approximately 3-4 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
| C. |
| Rehabilitation of Site/Seeding (approximately 0.02 miles) |
| Lump |
Total
| 17 |
| Grand Island Rim Trail Improvements Site 17: Culvert |
| A. |
| Culvert: 36" (Dia.) by 43' (L) Round Galvanized CMP. |
| Lump |
| B. |
| 36" Galvanized End Section (Installed at inlet end) with Hugger |
Bands Lump
| C. |
| Installation of culvert (approximately 8-12 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
| D. |
| Rehabilitation of Site/Seeding (approximately 0.02 miles) |
| Lump |
Total
| 18 |
| Grand Island Rim Trail Improvements Site 18: Culvert |
| A. |
| Culvert: 24" (Dia.) by 28' (L) Round Galvanized CMP. |
| Lump |
| B. |
| Installation of culvert (approximately 5-10 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
| C. |
| Rehabilitation of Site/Seeding (approximately 0.02 miles) |
| Lump |
Total
| 19 |
| Grand Island Rim Trail Improvements Site 19: Culvert |
| A. |
| Culvert: 24" (Dia.) by 30' (L) Round Galvanized CMP. |
| Lump |
| B. |
| 24" Galvanized End Section (Installed at inlet end) with Hugger |
Bands Lump
| C. |
| Installation of culvert (approximately 3-6 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
| D. |
| Rehabilitation of Site/Seeding (approximately 0.02 miles) |
| Lump |
Total
| 20 |
| Grand Island Rim Trail Improvements Site 20: Culvert |
| A. |
| Culvert: 24" (Dia.) by 38' (L) Round Galvanized CMP. |
| Lump |
| B. |
| 24" Galvanized End Section (Installed at inlet end) with Hugger |
Bands Lump
| C. |
| Installation of culvert (approximately 3-6 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
| D. |
| Rehabilitation of Site/Seeding |
| Lump |
Total
| 21 |
| Grand Island Rim Trail Improvements Site 21 (Originally |
Site #65): Culvert Replacement
| A. |
| Culvert: 24" (Dia.) by 36' (L) Round Galvanized CMP. |
| Lump |
| B. |
| Installation of culvert (approximately 5 foot burial depth). |
Surface with 5 cubic yards of MDOT 23A.
Lump
| C. |
| Rehabilitation of Site/Seeding (approximately 0.02 miles) |
| Lump |
Total
| 22 |
| MDOT 23A Stockpile at TBD Location on Grand Island. |
| A. |
| Up to 200 cubic yards MDOT 23A - See Culvert Plan Set for |
gradation requirements.
Cubic Yard
Total
| 23 |
| Class III Riprap Stockpile at TBD Location on Grand |
Island.
| A. |
| Up to 10 cubic yards of Class III riprap - See Culvert Plan Set |
for gradation requirements.
Cubic
Total
| 24 |
| Topsoil Stockpile at TBD Location on Grand Island. |
| A. |
| Up to 200 cubic yards of screened topsoil. |
| Cubic |
Total
| 25 |
| Mobilization |
| A. |
| Mobilization includes barge runs and the staging of equipment |
and materials at specified locations.
Lump
Total
Dollars $______________________________
Contractor Name:________________________________________________________________________
Contractor UEI:__________________________________________________________________________
Contractor Email:________________________________________________________________________