Atch 6 Sample Preliminary Construction Schedule.pdf
PDF 128 KB Posted
- Solicitation number
- 36C25820B0003
About this file
This document outlines a federal construction contract opportunity for emergency bus and switchgear modifications at the Veterans Affairs San Diego Healthcare System. The project involves general construction work including necessary removal of existing equipment and construction. Electrical work includes supplying and installing switchgear, switchboards, an automatic transfer switch, protective relays, metering equipment, conduits, wiring and related equipment. The period of performance is 360 days from the notice to proceed with an estimated start date between October 30, 2020 and October 25, 2021. The solicitation number is 36C25820B0003 and responses are due per the instructions in block 10 of the SF1442 form included with this opportunity. The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 22.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Start Finish Duration Predecessors
1 Emergency Bus & Switchgear ModificationsMon 10/5/20 Fri 7/2/21 257 days
2 NTP Mon 10/5/20 Mon 10/5/200 days
3 Submittal Preparation Mon 10/5/20 Tue 11/3/20 30 days 2
4 Mid Lead Items Wed 11/4/20 Sat 1/16/21 60 days 3
5 Long Lead Materials Wed 11/4/20 Wed 3/17/21120 days 3
6 Remove Power Connections at EPG1 Sun 1/17/21 Wed 3/17/2160 days 4
7 Install Temp Power for Life Safety & Critical Circuits connected to EDB1
Thu 3/18/21 Wed 3/31/21
14 days 6
8 Install Portable Gen Switchboard and concrete pad
Thu 4/1/21 Fri 4/30/21 30 days 7
9 Install conductors and conduits for temp power.
Sat 5/1/21 Fri 5/14/21 14 days 8
10 Install additional conduits in Bldg 1 Sat 5/15/21 Fri 6/4/21 21 days 9
11 Install temp Switchboard EPLC‐T Sat 6/5/21 Sat 6/19/21 15 days 10
12 Connect EPLC‐T Sun 6/20/21 Mon 6/21/21 2 days 11
13 Install Switchboard EPEE1 Sun 1/17/21 Sat 1/30/21 14 days 4
14 Install feeders and conduits Sun 1/31/21 Sat 2/13/21 14 days 13
15 Install ATS‐8 Sun 2/14/21 Sat 2/20/21 7 days 14
16 Remove circuits from EDB1 Sun 2/21/21 Sat 3/6/21 14 days 15
17 Remove Swbd EDB1 Sun 3/7/21 Sat 3/13/21 7 days 16
18 Install Swtichboard EPLC1, ATS‐16 Sun 3/14/21 Sat 3/27/21 14 days 17
19 Install EPG1 Thu 3/18/21 Wed 4/28/21 42 days 5
20 Install EPG1 feeders Thu 4/29/21 Wed 5/12/21 14 days 19
21 Make cutovers Thu 5/13/21 Wed 6/2/21 21 days 20
22 Final corrections and closeout Thu 6/3/21 Fri 7/2/21 30 days 21
10/5
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Manual Progress
Bldg. 2 ‐ Emergency Bus & Switchgear Modifications VA San Diego
Page 1 Project No:
664‐16‐301
Project: Emergency Bus & Switchg Date: Tue 7/7/20
File details come from the government source that posted it. Updated .