About this file

This document outlines a federal construction contract opportunity for emergency bus and switchgear modifications at the Veterans Affairs San Diego Healthcare System. The project involves general construction work including necessary removal of existing equipment and construction. Electrical work includes supplying and installing switchgear, switchboards, an automatic transfer switch, protective relays, metering equipment, conduits, wiring and related equipment. The period of performance is 360 days from the notice to proceed with an estimated start date between October 30, 2020 and October 25, 2021. The solicitation number is 36C25820B0003 and responses are due per the instructions in block 10 of the SF1442 form included with this opportunity. The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 22.

View the file

Other files

File Type Posted
36C25820C0093 Award Notice.pdf PDF
RFI Responses Available 36C25820B0003 21 Sep 2020.docx DOCX document
36C25820B0003 0013.docx DOCX document
RFIs 1-146 36C25820B0003 17 Sep 2020.docx DOCX document
36C25820B0003 0012.docx DOCX document
asbestos survey.pdf PDF
36C25820B0003 0011.docx DOCX document
Asbestos Survey Requirements CFR2011 title40 vol31 sec763-85.pdf PDF
RFIs 1-141 36C25820B0003 10 Sep.docx DOCX document
36C25820B0003 0010.docx DOCX document
36C25820B0003 0009.docx DOCX document
Addendum 01 Plans Emerg Bus and Switch Gear Mod 20200908.pdf PDF
Atch 2 Wage Determination revised 4 Sep 2020.docx DOCX document
RFIs 1-124 36C25820B0003 26 Aug.docx DOCX document
36C25820B0003 0008.docx DOCX document
Atch 2 Wage Determination revised 21 Aug 2020.docx DOCX document
36C25820B0003 0007.docx DOCX document
RFIs 1-96 36C25820B0003 Amendment 0007 24 Aug 2020.docx DOCX document
RFIs 1-91 36C25820B0003 EMERGENCY BUS AND SWITCHGEAR MODIFICATIONS.docx DOCX document
36C25820B0003 0006.docx DOCX document
IFB Atch 2 Wage Determination CA20200001 rev 14 Aug 2020.docx DOCX document
RFIs 36C25820B0003 EMERGENCY BUS AND SWITCHGEAR MODIFICATIONS 5 Aug 2020.docx DOCX document
36C25820B0003 0005.docx DOCX document
36C25820B0003 0004.docx DOCX document
Wage Determination 31 Jul 2020.docx DOCX document
RFIs 36C25820B0003 EMERGENCY BUS AND SWITCHGEAR MODIFICATIONS 31 Jul 2020.docx DOCX document
Atch 2 Wage Determination Rev 24 Jul 2020.docx DOCX document
36C25820B0003 SIte Walk Sign-in Sheets.pdf PDF
SF24-16d.pdf PDF
36C25820B0003 0003.docx DOCX document
RFIs 36C25820B0003 EMERGENCY BUS AND SWITCHGEAR MODIFICATIONS.docx DOCX document
VA701-16-B-0085-A00005002 - Geotechnical Report.pdf PDF
VA map 1.pdf PDF
VA-SD Geotech Report-Parking Lot.pdf PDF
36C25820B0003 0002.docx DOCX document
20090985 A7955 Sept 28 2009.pdf PDF
VASD GEOTECH report 20160205-E1828.pdf PDF
36C25820B0003 0001.docx DOCX document
Atch 2 Wage Determination 3 Jul 2020.doc DOC document
Atch 1 Self Performance Calculations.pdf PDF
Atch 5 664-16-301 Specifications CD Final.pdf PDF
Atch 7 ICRA.doc DOC document
Atch 4 664-16-301 Drawings CD Final.pdf PDF
36C25820B0003.docx DOCX document
Atch 3 Statement of Work SOW Construction.docx DOCX document
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Start Finish Duration Predecessors

1 Emergency Bus & Switchgear ModificationsMon 10/5/20 Fri 7/2/21 257 days

2 NTP Mon 10/5/20 Mon 10/5/200 days

3 Submittal Preparation Mon 10/5/20 Tue 11/3/20 30 days 2

4 Mid Lead Items Wed 11/4/20 Sat 1/16/21 60 days 3

5 Long Lead Materials Wed 11/4/20 Wed 3/17/21120 days 3

6 Remove Power Connections at EPG1 Sun 1/17/21 Wed 3/17/2160 days 4

7 Install Temp Power for Life Safety & Critical Circuits connected to EDB1

Thu 3/18/21 Wed 3/31/21

14 days 6

8 Install Portable Gen Switchboard and concrete pad

Thu 4/1/21 Fri 4/30/21 30 days 7

9 Install conductors and conduits for temp power.

Sat 5/1/21 Fri 5/14/21 14 days 8

10 Install additional conduits in Bldg 1 Sat 5/15/21 Fri 6/4/21 21 days 9

11 Install temp Switchboard EPLC‐T Sat 6/5/21 Sat 6/19/21 15 days 10

12 Connect EPLC‐T Sun 6/20/21 Mon 6/21/21 2 days 11

13 Install Switchboard EPEE1 Sun 1/17/21 Sat 1/30/21 14 days 4

14 Install feeders and conduits Sun 1/31/21 Sat 2/13/21 14 days 13

15 Install ATS‐8 Sun 2/14/21 Sat 2/20/21 7 days 14

16 Remove circuits from EDB1 Sun 2/21/21 Sat 3/6/21 14 days 15

17 Remove Swbd EDB1 Sun 3/7/21 Sat 3/13/21 7 days 16

18 Install Swtichboard EPLC1, ATS‐16 Sun 3/14/21 Sat 3/27/21 14 days 17

19 Install EPG1 Thu 3/18/21 Wed 4/28/21 42 days 5

20 Install EPG1 feeders Thu 4/29/21 Wed 5/12/21 14 days 19

21 Make cutovers Thu 5/13/21 Wed 6/2/21 21 days 20

22 Final corrections and closeout Thu 6/3/21 Fri 7/2/21 30 days 21

10/5

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration‐only

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Manual Progress

Bldg. 2 ‐ Emergency Bus & Switchgear Modifications VA San Diego

Page 1 Project No:

664‐16‐301

Project: Emergency Bus & Switchg Date: Tue 7/7/20

File details come from the government source that posted it. Updated .