About this file

This document contains a self-performance worksheet and details for a federal construction contract opportunity. The contract is for emergency bus and switchgear modifications at the San Diego VA Healthcare System, with a period of performance of 360 days from notice to proceed and an estimated start date of October 30, 2020. Work includes general construction, alterations, removal of existing equipment, and electrical work such as installing switchgear, switchboards, an automatic transfer switch, and related equipment. The self-performance worksheet requires offerors to calculate the percentage of work they will perform themselves versus subcontracting, with a minimum threshold of 50% for SDVOSB set-aside contracts. Relevant costs to track include total price, profit, materials, and self-performed labor. The contracting agency is the Department of Veterans Affairs Veterans Health Administration VISN 22.

View the file

Other files

File Type Posted
36C25820C0093 Award Notice.pdf PDF
RFI Responses Available 36C25820B0003 21 Sep 2020.docx DOCX document
36C25820B0003 0013.docx DOCX document
RFIs 1-146 36C25820B0003 17 Sep 2020.docx DOCX document
36C25820B0003 0012.docx DOCX document
asbestos survey.pdf PDF
36C25820B0003 0011.docx DOCX document
Asbestos Survey Requirements CFR2011 title40 vol31 sec763-85.pdf PDF
RFIs 1-141 36C25820B0003 10 Sep.docx DOCX document
36C25820B0003 0010.docx DOCX document
36C25820B0003 0009.docx DOCX document
Addendum 01 Plans Emerg Bus and Switch Gear Mod 20200908.pdf PDF
Atch 2 Wage Determination revised 4 Sep 2020.docx DOCX document
RFIs 1-124 36C25820B0003 26 Aug.docx DOCX document
36C25820B0003 0008.docx DOCX document
Atch 2 Wage Determination revised 21 Aug 2020.docx DOCX document
36C25820B0003 0007.docx DOCX document
RFIs 1-96 36C25820B0003 Amendment 0007 24 Aug 2020.docx DOCX document
RFIs 1-91 36C25820B0003 EMERGENCY BUS AND SWITCHGEAR MODIFICATIONS.docx DOCX document
36C25820B0003 0006.docx DOCX document
IFB Atch 2 Wage Determination CA20200001 rev 14 Aug 2020.docx DOCX document
RFIs 36C25820B0003 EMERGENCY BUS AND SWITCHGEAR MODIFICATIONS 5 Aug 2020.docx DOCX document
36C25820B0003 0005.docx DOCX document
36C25820B0003 0004.docx DOCX document
Wage Determination 31 Jul 2020.docx DOCX document
RFIs 36C25820B0003 EMERGENCY BUS AND SWITCHGEAR MODIFICATIONS 31 Jul 2020.docx DOCX document
Atch 2 Wage Determination Rev 24 Jul 2020.docx DOCX document
36C25820B0003 SIte Walk Sign-in Sheets.pdf PDF
SF24-16d.pdf PDF
36C25820B0003 0003.docx DOCX document
RFIs 36C25820B0003 EMERGENCY BUS AND SWITCHGEAR MODIFICATIONS.docx DOCX document
VA701-16-B-0085-A00005002 - Geotechnical Report.pdf PDF
VA map 1.pdf PDF
VA-SD Geotech Report-Parking Lot.pdf PDF
36C25820B0003 0002.docx DOCX document
20090985 A7955 Sept 28 2009.pdf PDF
VASD GEOTECH report 20160205-E1828.pdf PDF
36C25820B0003 0001.docx DOCX document
Atch 2 Wage Determination 3 Jul 2020.doc DOC document
Atch 5 664-16-301 Specifications CD Final.pdf PDF
Atch 7 ICRA.doc DOC document
Atch 4 664-16-301 Drawings CD Final.pdf PDF
36C25820B0003.docx DOCX document
Atch 6 Sample Preliminary Construction Schedule.pdf PDF
Atch 3 Statement of Work SOW Construction.docx DOCX document
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section J, Attachment 1

Attachment 1, Self Performance Worksheet

SELF-PERFORMED WORK AND LIMITATIONS ON SUBCONTRACTING

This procurement is a 100% SDVOSB set-aside. FAR 52.219-27 (OCT 2019) and VAAR 852.219-10 (JUL 2019)(DEVIATION) are incorporated into this solicitation and resulting contract. Offeror to complete and submit this worksheet with their bid documents. The period of time used to determine offeror’s compliance with the requirements for self-performance of work and the limitations on subcontracting will be the period the Agency uses to evaluate the bid of this pending Contract.

OFFEROR’S SELF PERFORMANCE WORKSHEET

Offeror’s are required to complete this Worksheet for this Contract.

a) Offeror’s total proposed price $___________

b) Subtract profit or fees $

c) Subtract cost of materials $

d) Offeror’s total estimated cost of contract performance for personnel (a-b-c=d) $____________

e) Offeror’s total estimated self-performed cost of contract performance incurred for personnel who are offeror’s employees or the employees of other SDVOSBC’s $___________

f) Offeror’s percentage of self-performed work (e/d X 100 = %) __________%

List of Proposed Subcontractors for this project /Value of those subcontracts:

Subcontractor $Value

Subcontractor $Value

Subcontractor $Value

Subcontractor $Value

Subcontractor $Value

Subcontractor $Value

List of “Self Performed” work activities to be performed by the SDVOSB:

Section J, Attachment 1

Attachment 1, Self Performance Worksheet

At completion of this Contract, the awardee shall complete and submit calculations to the Contracting

Department for the actual results achieved.

a) Offeror’s total proposed price $___________

b) Subtract profit or fees $

c) Subtract cost of materials $

d) Offeror’s total estimated cost of contract performance for personnel (a-b-c=d) $____________

e) Offeror’s total self-performed cost of contract performance incurred for personnel who are offeror’s employees or the employees of other SDVO SBC’s $___________

f) Offeror’s percentage of self-performed work (e/d X 100 = %) __________%

Definitions: (from 13 CFR 125.6)

Cost of the contract. All allowable direct and indirect costs allocable to the contract, excluding profit or fees.

Cost of contract performance incurred for personnel. Direct labor costs and any overhead which has only direct labor as its base, plus the concern's General and Administrative rate multiplied by the labor cost.

Cost of materials. Includes costs of the items purchased, handling and associated shipping costs for the purchased items

(which includes raw materials), off-the-shelf items (and similar proportionately high-cost common supply items requiring additional manufacturing or incorporation to become end items), special tooling, special testing equipment, and construction equipment purchased for and required to perform on the contract. In the case of a supply contract, the acquisition of services or products from outside sources following normal commercial practices within the industry are also included.

Personnel. Individuals who are “employees” under §121.106 of this chapter except for purposes of the HUBZone program, where the definition of “employee” is found in §126.103 of this chapter.

Subcontracting. That portion of the contract performed by a firm, other than the concern awarded the contract, under a second contract, purchase order, or agreement for any parts, supplies, components, or subassemblies which are not available off-the-shelf, and which are manufactured in accordance with drawings, specifications, or designs furnished by the contractor, or by the government as a portion of the solicitation. Raw castings, forgings, and moldings are considered as materials, not as subcontracting costs. Where the prime contractor has been directed by the Government to use any specific source for parts, supplies, components subassemblies or services, the costs associated with those purchases will be considered as part of the cost of materials, not subcontracting costs.