Atch 3 AF 66 Submittal Register.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
AMENDMENT 01 (12 Sep 2025) Maintain and Inspect Radio Towers at 5 Missile Alert Fields and Bldg 3650
Solicitation number
FA461325Q0027
Issued by

About this file

The submitted file is an Attachment 3 Submittal Register (AF Form 66) for a radio tower maintenance project at five Missile Alert Facilities (MAFs) and Building 3650. The document outlines 17 specific submittal requirements that the contractor must provide, including Material Safety Data Sheets, work schedules, annual tower inspection reports, post-project reports, and various manufacturer data documentation for components like replacement bulbs, electrical conduits, acrylic paint, tower bolts, and grounding receptacles.

Submission timelines vary but are primarily within 10 days after Notice to Proceed (NTP) or upon specific project milestones, such as final inspection. Key documentation requirements include a Quality Control Plan, site interruption plan, contract progress schedules and reports, and compliance documentation. The project is associated with the Department of the Air Force Global Strike Command, with the solicitation (FA461325Q0027) seeking maintenance of radio towers, aircraft warning lights, tower structures, and foundations at secure sites under F.E. Warren Air Force Base in Wyoming.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet 1

PROJECT NUMBERPROJECT TITLESOLICITATION/CONTRACT NUMBER
SCHEDULE OF MATERIAL SUBMITTALS25-4115MAINTAIN RADIO TOWERS

at 5 MAFs & BUILDING 3650

TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURE'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSTESTSREPORTSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATEFOLLOW-UPDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDISAPPROVED
1Material Safety and Data SheetX10 Days After NTP
2EAL DocumentationX10 Days After NTP
3Work ScheduleXUpon Notice To Proceed and Monthly
4Annual Tower Inspection ReportXUpon Final Inspection
5Post Project ReportXWithin 10 Days of Final Inspection
6Non-Shrink Crack SealantX10 Days After NTP
7Replacement Bulb Manufacture DataX10 Days After NTP
8Replacement Bulb Socket Manufacture DataX10 Days After NTP
9Electrical Conduit Manufacture DataX10 Days After NTP
10Tower, Acrylic Paint Manufacture DataX10 Days After NTP
11Tower, Bolt Manufacture DataX10 Days After NTP
12Grounding Receptacle Manufacture DataX10 Days After NTP
13Liens or Landowner AgreementsXBefore Using Adjacent Land
14Site Interruption PlanX30 Days Before Interrputing the Site
15Contract Progress ScheduleXOne Day After Completing a Tower
16Contract Progress ReportXOne Day After Completing a Tower
17Quality Control Plan10 Days After NTP
AF Form 66, OCT 89PREVIOUS EDITION WILL BE USEDSee Specifications for Frequency