DATE OMB NO 0704-0188PROVISIONING PERFORMANCE SCHEDULE
END ARTICLE CONTRACTOR
SOLICITATION OR CONTRACT NUMBER TYPE OF CONTRACTEND ARTICLE DELIVERY DATES
DATE OF FIRST DELIVERY
EMD PROD
REVISION
NUMBER DATEDATE OF LAST DELIVERY EMC W/PROD OPT
NO EVENT TIMING CALENDAR DATEACTION
AGENCY
CONTRACT AWARD GOVT CONTRACT MAILING DATE1
GOVT AND
CONTR
NLT 45 DAYS AFTER MAILING DATE OF
CONTRACT
GUIDANCE CONFERENCE2
SUBMIT TO DLSC NOT EARLIER THEN 30
DAYS PRIOR TO SUBMITTING PTD
DLSC SCREENING CONTR3
NLT 165 DAYS PRIOR TO CONTRACTOR'S
ORDER NEED DATE
SAIP CONTR4
a. CANDIDATE LIST
NLT 30 DAYS AFTER RECEIPT OF CANDIDATE
LIST
b. SELECTED ITEM NOTIFICATION GOVT
c. CONTRACTOR PROCUREMENT
SCHEDULE PTD, EDFP SCREENING
NLT 90 DAYS PRIOR TO CONTRACTOR'S
ORDER NEED DATE
CONTR
GOVT AND
CONTR
NLT 60 DAYS PRIOR TO CONTRACTOR'S
ORDER NEED DATE
d. PROVISIONING CONFERENCE START
FINISH
NLT 30 DAYS PRIOR TO CONTRACTOR'S
ORDER NEED DATE
e. PIOs RELEASED TO CONTRACTOR GOVT
LONG LEAD ITEMS LIST (LLIL) WITH
EDFP AND DLSC SCREENING RESULTS
NLT 30 DAYS AFTER RELEASE FOR
FABRICATION OR PROCUREMENT OF
CONTR5 START
FINISH
b. RECOMMENDED ITEMS CONTR 45 DAYS PRIOR TO RELEASE OF PPL
GOVT AND
CONTR
NLT 90 DAYS PRIOR TO CONTRACTOR'S
ORDER NEED DATE
c. PROVISIONING CONFERENCE
NLT 30 DAYS AFTER RECEIPT OF LLIL FROM
CONTRACTOR
d. PIOs RELEASED TO CONTRACTOR GOVT
NLT 60 DAYS PRIOR TO PROVISIONING
CONFERENCE
PTD/EDFP REQUIREMENTS CONTR6
GOVT AND
CONTR
STARTPROVISIONING CONFERENCE NLT 60 DAYS AFTER RECEIPT OF PTD/EDFP7
FINISH
PIOs w/DELIVERY SCHEDULE GOVT DUE 90 DAYS AFTER RECEIPT OF PTD/EDFP8
ACCEPTANCE/REVISION OF
DELIVERY SCHEDULE
CONTR NLT 60 DAYS AFTER RECEIPT OF PIO's9
IAW PROGRAMMING CHECKLIST BUT NLT 90
DAYS PRIOR TO OND
SPARES NEED DATE GOVT10
TRAINING START DATE GOVT11
OPERATIONAL NEED DATE GOVT12
REMARKS (Continue on reverse)
APPROVED BY
AF PROV CHAIRPERSON CONTRACTOR PROGRAM MANAGER
PREVIOUS EDITION IS OBSOLETE.AFMC FORM 718, 20181207
Prescribed by: AFMCMAN20-106
Public reporting burden for this collection of information is estimated to average 8 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Washington Headquarters Services, Directorate of Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project
REMARKS (Continued)
AFMC FORM 718, 20181207, Reverse
DATE
OMB NO 0704-0188
PROVISIONING PERFORMANCE SCHEDULE
END ARTICLE
CONTRACTOR
SOLICITATION OR CONTRACT NUMBER
TYPE OF CONTRACT
END ARTICLE DELIVERY DATES
DATE OF FIRST DELIVERY
EMD
PROD
REVISION
NUMBER
DATE
DATE OF LAST DELIVERY
EMC W/PROD OPT
NO
EVENT
TIMING
CALENDAR DATE
ACTION
AGENCY
CONTRACT AWARD
GOVT
CONTRACT MAILING DATE
GOVT AND
CONTR
NLT 45 DAYS AFTER MAILING DATE OF
CONTRACT
GUIDANCE CONFERENCE
SUBMIT TO DLSC NOT EARLIER THEN 30
DAYS PRIOR TO SUBMITTING PTD
DLSC SCREENING
CONTR
NLT 165 DAYS PRIOR TO CONTRACTOR'S
ORDER NEED DATE
SAIP
CONTR
a. CANDIDATE LIST
NLT 30 DAYS AFTER RECEIPT OF CANDIDATE LIST
b. SELECTED ITEM NOTIFICATION
GOVT
c. CONTRACTOR PROCUREMENT SCHEDULE PTD, EDFP SCREENING
NLT 90 DAYS PRIOR TO CONTRACTOR'S ORDER NEED DATE
CONTR
GOVT AND
CONTR
NLT 60 DAYS PRIOR TO CONTRACTOR'S ORDER NEED DATE
d. PROVISIONING CONFERENCE
START
FINISH
NLT 30 DAYS PRIOR TO CONTRACTOR'S ORDER NEED DATE
e. PIOs RELEASED TO CONTRACTOR
GOVT
LONG LEAD ITEMS LIST (LLIL) WITH EDFP AND DLSC SCREENING RESULTS
NLT 30 DAYS AFTER RELEASE FOR FABRICATION OR PROCUREMENT OF
CONTR
START
FINISH
b. RECOMMENDED ITEMS
CONTR
45 DAYS PRIOR TO RELEASE OF PPL
GOVT AND
CONTR
NLT 90 DAYS PRIOR TO CONTRACTOR'S
ORDER NEED DATE
c. PROVISIONING CONFERENCE
NLT 30 DAYS AFTER RECEIPT OF LLIL FROM
CONTRACTOR
d. PIOs RELEASED TO CONTRACTOR
GOVT
NLT 60 DAYS PRIOR TO PROVISIONING
CONFERENCE
PTD/EDFP REQUIREMENTS
CONTR
GOVT AND
CONTR
START
PROVISIONING CONFERENCE
NLT 60 DAYS AFTER RECEIPT OF PTD/EDFP
FINISH
PIOs w/DELIVERY SCHEDULE
GOVT
DUE 90 DAYS AFTER RECEIPT OF PTD/EDFP
ACCEPTANCE/REVISION OF
DELIVERY SCHEDULE
CONTR
NLT 60 DAYS AFTER RECEIPT OF PIO's
IAW PROGRAMMING CHECKLIST BUT NLT 90
DAYS PRIOR TO OND
SPARES NEED DATE
GOVT
TRAINING START DATE
GOVT
OPERATIONAL NEED DATE
GOVT
REMARKS (Continue on reverse)
APPROVED BY
AF PROV CHAIRPERSON
CONTRACTOR
PROGRAM MANAGER
PREVIOUS EDITION IS OBSOLETE.
AFMC FORM 718, 20181207
Prescribed by: AFMCMAN20-106 Public reporting burden for this collection of information is estimated to average 8 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Washington Headquarters Services, Directorate of Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project REMARKS (Continued) AFMC FORM 718, 20181207, Reverse 8.2.1.3158.1.475346.466429
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| end: |
| cntrctr: |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| solctn: |
| revnum: |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| emd: 0 |
| prod: 0 |
| emcprod: 0 |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| SHOW DATE AS YYYYMMDD (E.G., 20000101): |
| timing: |
| timing_2: |
| remarks: |
| chair: |
| contract: |
| manager: |
| remark: |