Appendix Rough Order Magnitude Cost Estimate.pdf
PDF 187 KB Posted
- Attached to
- RFP for Connect Shelters for Purchase And Use
- Solicitation number
- CE-26-705
- Issued by
- California
About this file
Summary of Description of Work for Tiny Homes Project - City of Long Beach
This document is a budgetary estimate and description of work prepared by Kardent Architecture Design for the City of Long Beach dated November 15, 2022. The project encompasses the development of a tiny homes community with three primary components: site work, modular units, and associated infrastructure. Site work includes surveying, monument signage, stormwater pollution prevention planning (SWPPP), pavement removal (146 cubic yards), tree removal (6 trees up to 24 inches), utility installations for water, sewer, fire water and hydrants, and storm drain systems. The modular units component specifies 12 modular housing units on 150 pier footings, with fire alarm systems, switchgear and distribution infrastructure, and a security checkpoint. Additional site improvements include 11,000 square feet of asphalt paving, wrought iron fencing (170 linear feet at 10 feet high), solar lights (6 units), bollards, and ADA signage.
The total project budget is estimated at $4,566,563.00, divided between the site work phase ($2,372,363.00) and modular units phase ($2,194,200.00). Direct costs total $3,260,680.00, with contingencies and markups applied across construction contingency (10%), general conditions (8%), insurance (2%), profit and overhead (10%), bonding (1%), testing and inspection (2%), permit and plan check (5%), and utility fees (4%). The estimate is based on preliminary design documents and known conditions but may not account for unforeseen conditions or economic fluctuations. The document includes a disclaimer that actual costs may vary by plus or minus 25 percent or more from the estimated amount.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11/15/2022
City of Long Beach
DESCRIPTION OF WORK
OTY UOM Unit Cost Total Cost
Site Work
Surveying 1 LS 25,000.00$ 25,000.00$
Monument Sign 1 LS 15,000.00$ 15,000.00$
SWPPP 1 LS 36,000.00$ 36,000.00$
Pavement Removal 146 CY 160.00$ 23,680.00$
Tree Removal up to 24" 6 EA 2,000.00$ 12,000.00$
Mobilization on Non Budget Items 1 LS 25,000.00$ 25,000.00$
Water 1 LS 95,000.00$ 95,000.00$
Sewer 1 LS 180,000.00$ 180,000.00$
Fire Water and Fire Hydrants 1 LS 200,000.00$ 200,000.00$
Storm Drain 1 LS 131,000.00$ 131,000.00$
Modular Wetland System 2 EA 45,000.00$ 90,000.00$
Asphalt Paving 11,000 SF 20.00$ 220,000.00$
Asphalt Trench Patching 1200 SF 20.00$ 24,000.00$
Edison Transformer and Fee 1 EA 100,000.00$ 100,000.00$
Switchgear and Distribution 1 LS 150,000.00$ 150,000.00$
Grading 1 LS 50,000.00$ 50,000.00$
Traffic Cotroll 20 Days 50,000.00$
Wrought Iron Fence 10 ' High 170 LF 700.00$ 119,000.00$
16' Gate 12,000.00$
Solar Lights 6 EA 16,000.00$ 96,000.00$
Bollards at Fire Hydrant's 6 EA 2,000.00$ 12,000.00$
ADA Signage 5,000.00$
Direct Cost 1,670,680.00$
Construction Contingency 10% 167,068.00$
General Conditions 8% 133,654.00$
Insurance 2% 33,413.00$
Profit and Overhead 10% 167,068.00$
Bond 1% 16,706.00$
Testing and Inspection 2% 33,413.00$
Permit and Plan Check 5% 83,534.00$
Utility Fees 4% 66,827.00$
2,372,363.00$
Modular Units
Pier Footings 150 EA 1,000.00$ 150,000.00$
Modular Units 12 EA 100,000.00$ 1,200,000.00$
Fire Alarm System 1 LS 70,000.00$ 70,000.00$
Switchgear and Distribution 1 LS 150,000.00$ 150,000.00$
Security Check Point 1 EA 20,000.00$ 20,000.00$
1,590,000.00$
Construction Contingency 10% 159,000.00$
General Conditions 8% 127,200.00$
Insurance 2% 31,800.00$
Profit and Overhead 10% 159,000.00$
Bond 1% 15,900.00$
Testing/Inspection/Staking 2% 31,800.00$
Permit/Plan Check 5% 79,500.00$ 2,194,200.00$
Tiny Homes
ITEM
NO
Site Work Total
Labor and Material
Direct Cost
Modular Total
Disclaimer: It is the requestor's obligation to carefully review and confirm the information provided is valid and reflects the scope of work requested by the project customer. The attached budgetary estimate is an initial projection of cost based on preliminary, quantities, general construction methods, and the scope of work as provided in the preliminary design documents. The construction budget estimate is based on known conditions as described in the general scope of work but may does not include "Unforeseen Conditions" and fluctuating cost impacts of the economy. The estimate was developed by drawing on historical construction methods and current published construction cost standards.
The actual cost may vary (+/- 25% or more) of the estimated amount.