Security System Testing Specification
This is an appendix specification document for Section 16899 Security System Testing, prepared for the Massachusetts Bay Transportation Authority (MBTA) and MassDOT Security as part of RFP 118-26 for the MVSS Bus Maintenance Contract in Massachusetts. The specification establishes comprehensive requirements for testing and inspecting all security systems, subsystems, assemblies, and components installed or affected by contract work, including video management monitoring systems (VMMS), Electronic Access Control Systems (EACS), telecommunications systems, and network infrastructure. The testing scope encompasses initial tests, visual inspections, breakdown tests, wiring and fiber verification, continuity and signal loss tests, electrical isolation tests, voltage and current tests, equipment burn-in tests, timing tests, network tests, integration tests, and overall system functional tests conducted throughout project phases from installation through final system configuration and programming.
The contractor is responsible for developing and submitting a comprehensive Test Plan within 60 days of receiving notice to proceed, along with Quality Assurance/Quality Control procedures within 30 days, Installation Plans within 20 days, Inspection Procedures with data sheets within 45 days, and Test Procedures with data sheets within 60 days. The contractor must appoint a Quality Assurance Officer with minimum 10 years' experience in electrical and systems application, who cannot have other project responsibilities and must review and certify all test documentation. The contractor bears all costs for labor, materials, test equipment, and technical expertise, including maintaining properly calibrated test equipment re-certified every 90 days, providing backup test equipment to prevent schedule delays, and performing all retesting upon failure. Following successful completion of all inspections and testing with resolution of all discrepancies, the contractor must submit a Final Test Report and Letter of System Certification within one week, followed by a 60-day operational period without failure before final system certification. MassDOT Security reserves the right to witness all inspections and tests, and all costs are included in the contract lump sum price for Item 0130.130.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
XXXCNXX SECURITY SYSTEM TESTING
September 2025 16899 - 1
Appendix C - Section 16899 Security System Testing
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work to be done under this section, and in conjunction with the other sections of this Specification, consists of the tests and inspections that shall be performed to demonstrate and certify that all systems, subsystems, assemblies, sub assembles, interfaces and components provided, relocated or otherwise affected by the work performed for this Contract function properly, safely and are in compliance with these Specifications. Tests shall also be made to demonstrate that existing functioning systems affected by or adjacent to work performed as part of this Contract are not adversely impacted and function as originally intended.
B. Tests and inspections shall be performed during the various phases of this Project, from installation of the various system elements up to and including final system configuration and programing. Tests and inspections shall consist of, but not be limited to initial tests, visual inspections, breakdown tests, wiring and fiber verification tests, continuity and signal loss tests, electrical isolation tests, voltage and current tests, equipment burn-in tests, timing tests, network tests, video management monitoring system (VMMS) tests, Electronic Access Control System (EACS) security system component tests, telecommunications systems tests, integration tests, and overall system functional tests.
C. Test Plan – The Contractor shall develop a comprehensive Test Plan that will lead to the certification for service of the systems installed and the work performed under this Contract for approval by MBTA and/or MassDOT. The Test Plan shall detail and employ a logical process of component inspections through to overall system functional tests with each inspection and test building on the previous, resulting in a thoroughly tested and integrated system installation. The Test Plan shall itemize and provide overall organization of the Initial Tests and supporting data, Inspection Procedures and data forms, Test Procedures and data forms, and the final Test Report and System Certification. The Test Plan shall be representative of the Contractors application and design to be installed under this Contract.
The Test Plan shall also identify how to document and address discrepancies during inspections and testing. The Test Plan shall include a matrix based checklist verifying each test has been conducted with a pass /fail/expected results criteria.
D. Inspection Procedures – The Contractor shall develop a comprehensive schedule of inspections for all elements and components being installed, including but not limited to cable, fiber, conduit, cases, junction boxes, terminations, breakers, splice boxes, assemblies and equipment. The Contractor shall provide detailed inspection data forms for the inspection of all elements and components in the installation, including all applicable requirements.
E. Test Procedures – The Contractor shall develop comprehensive Test Procedures for all functional elements of the system as well as the system as a whole. At a minimum, each Test Procedure shall identify in detail, the purpose of the test, the equipment and system under test, the method and process of performing the test such that each system and subsystem is sequenced through its required operation including the imposition of simulated conditions, the expected results of the test including definition of pass/fail criteria, the test equipment needed to perform the test, the staffing requirements needed to perform the test, and the approximate duration of the test.
September 2025 16899 - 2
F. Test Report and System Certification – Immediately following the completion of all inspections and testing, and the system is considered by the MassDOT Security and the MBTA to be in-service, the Contractor shall provide a Test Report and Letter of System Certification. The Test Report shall contain the original versions of the Test Plan, Test documents, Inspection documents, Test Procedure and data documents, all discrepancies reports, their resolution and retest data, etc. The Letter of System Certification will be based on the successful completion of all tests and inspections as identified in the Test Report. With the Letter of System Certification, the Contractor will also be stating that the system installed meets all applicable requirements of the specification and plans, as well as all local, state and federal codes and regulations.
G. Contractor Responsibility – Unless otherwise stated, all support, labor and technical expertise for the work identified in this section and other test sections is the responsibility of the Contractor. All materials, equipment, and test gear necessary to support the requirements of these specifications are the responsibility of the Contractor.
H. MassDOT Security Witnessing –MassDOT Security reserves the right to witness all inspections and tests. The Contractor shall provide sufficient notice to MassDOT Security as to the schedule of inspections and tests to be performed. Tests will not be considered official unless MassDOT Security Project designee has witnessed the test or MassDOT Security has informed the Contractor that MassDOT Security will not be witnessing that specific test.
Under no circumstances shall the Contractor use MBTA Operations support staff as test witnesses. Whether or not MassDOT Security witnesses the test does not relieve the Contractor from any other requirements of the Contract Documents.
I. Test Failure – In the event the item under inspection or the system under test does not meet the applicable requirements, the Contractor shall make the necessary corrections to bring the item or system into compliance. The Contractor shall be responsible for all applicable testing or retesting. The Contractor shall fully document the process from discrepancy report, failure analysis, corrective action plan, through to data showing the successful completion of testing.
J. Impacts of Testing on Application and Design – The Contractor shall be responsible for applying and installing system components so that they can be effectively and efficiently tested separately and then together as a connected and cohesive functioning system.
1.2 REFERENCE STANDARDS
A. All standards referenced within the Contract documents, as well as all applicable local, state and federal codes shall be observed and adhered to for all inspections and testing.
B. The Contractor shall make reference to all applicable requirements in their test and inspection procedures.
C. If a conflict exists between standards and regulations as specified herein the most restrictive, in the opinion of the Engineer, shall govern. The Contractor shall immediately make MassDOT Security aware of any conflicts.
1.3 QUALITY ASSURANCE
A. The Contractor shall maintain and adhere to a quality control process with regard to tracking all test documentation, including the test plan, inspection procedures, test procedures, test data, discrepancies, etc. The Contractor shall submit their methods to MassDOT Security for review and approval.
September 2025 16899 - 3
B. The Contractor’s designated Quality Assurance Officer shall review for completeness and accuracy all test documents, including, but not limited to the Test Plan, Test Data, Inspection Procedures, Test Procedures, Inspection Data Sheets, Test Data Sheets, etc. The Quality Assurance Officer shall date and sign all documents that they review. The Contractor shall identify their Quality Assurance Officer in their bid. The Quality Assurance Officer can have no other responsibilities on this Project. The Quality Assurance Officer shall have a minimum of ten (10) years of experience in electrical and systems application and inspection as well as knowledge of trends and innovations with regard to the systems and products being applied on this Project.
C. Test equipment of the proper type, capacity, range and accuracy shall be supplied by the Contractor to perform the required tests and inspections. This equipment shall be in good working order and properly calibrated at the time the tests or inspections are conducted. The calibration of each instrument shall be certified by a recognized testing facility. Re-certification shall be conducted every 90 days or less. Out-of-date instruments will be considered non-certified. Tests conducted with non-certified instruments will be rejected.
Tests that require the use of test equipment shall have the make, model and calibration date noted on the test data forms.
1.4 SUBMITTALS
A. All Submittals shall be made in the format and manner that is required by these Specifications and subsequent MassDOT Security approved agreements. Unless otherwise stated all submittals from the Contractor shall be for MassDOT Security review and approval.
B. All Submittals shall have sufficient data and information so that they may be reviewed as “standalone” documents. All references must be provided or already be in possession of MassDOT Security.
C. Approval of any submittals does not relieve the Contractor from the requirements of these specifications. The Contractor shall make separate and specific requests for approval on waiving any requirements of the Contract.
D. Submittal Format – All Submittals for this section shall be made in compliance with all other requirements of these specifications. In addition, all Submittals for this Section shall also be made in electronic, .pdf format submitted on electronic media. Each Specification Section requiring a submittal shall have a single corresponding .pdf document.
E. Test Plan – Within thirty (30) days of receiving MassDOT Security notice to proceed, the Contractor shall submit their Test Plan Outline, and within sixty (60) days submit their final Test Plan.
F. Quality Assurance/Quality Control – Within thirty (30) days of receiving MassDOT Security notice to proceed, the Contractor submit their Quality Assurance/Quality Control procedures and processes, both general and specific to this Project.
G. Installation Plans – Within twenty (20) days of receiving MassDOT Security notice to proceed, the Contractor shall submit Installation Plans. The Installation Plans shall identify the locations where system elements and components shall be installed as well as all cable, fiber and conduit routing. Subsequent versions of the Installation Plans shall be submitted as they are revised during the installation process to reflect actual field conditions.
H. Inspection Procedures – Within forty-five (45) days of receiving MassDOT Security notice to proceed, the Contractor shall submit their Inspection Procedures, complete with corresponding data sheets.
September 2025 16899 - 4
I. Test Procedures – Within sixty (60) days of receiving MassDOT Security notice to proceed, the Contractor shall submit their Test Procedures, complete with corresponding data sheets.
J. Test Report and System Certification – At no more than one (1) week after the completion of testing and MassDOT Security assuming responsibility for the installed system(s), the Contractor shall submit the Test Report and System Certification letter signed by a principle of the prime Contractor, certifying that all necessary tests have been performed and that the system(s) successfully passed the tests.
PART 2 - PRODUCTS
2.1 TEST EQUIPMENT AND MATERIALS
A. Relative to the systems being installed as a part of this Project, the Contractor shall supply and use the latest commercially available test equipment. Use of indirect testing methods resulting from a lack of having proper test equipment shall not be approved. All test equipment shall be calibrated within 6 months of testing.
B. All test instruments and equipment necessary to conduct the tests specified herein shall be available, ready-for-use not less than one week in advance of test need. Ready-for-use shall mean properly matched for test parameters, properly calibrated, sufficiently supplied with leads, probes, adapters, stands etc. necessary to conduct the particular test in a completely professional manner.
C. All temporary or interim test related materials, special tools, connections, jumpers etc. shall be furnished and available not less than one week in advance of the test need.
D. The Contractor shall maintain a complete backup set of test instruments and equipment in compliance with all other aspects of these specifications so that if any part of the primary test equipment fails, the backup equipment can be immediately used so that there will be no loss to the test schedule.
PART 3 - EXECUTION
3.1 TEST PLAN
A. The Contractor shall develop and submit a comprehensive Test Plan that will provide a roadmap and structure for the process by which inspection and testing will be employed in certifying the installed system(s) for service. While the intent of this document is to provide an overview, it shall have sufficient detail so that the intent and completeness of the envisioned inspections and testing can be understood by MassDOT Security prior to the development of the detailed inspection and test procedures. The Test Plan must be approved by MassDOT Security and submitted to the MassDOT Security as part of the project documentation.
B. The Contractor shall take into account their application and integration of the selected products and subsystems when developing this Test Plan and subsequent support documents.
C. The Test Plan will show how all elements and components of the installed systems will be completely tested. The Test Plan shall include logically formatted descriptions that identify all components to be inspected up to and including full system integration functional testing.
September 2025 16899 - 5
D. The Contractor shall provide a comprehensive Quality Assurance/Quality Control policy and process for this Project. This policy and process shall be reflected in all aspects of inspection and testing.
E. Format – The Contractor shall develop and provide a Test Plan that at a minimum contains the items from the security project commissioning checklist. It is expected that the Contractor shall expand their Test Plan with any and all necessary detail for the application being installed on the Project:
1. Test Plan Summary – A summary describing how the Contractor’s plan for testing will demonstrate that the installation will perform as intended and be in compliance with all sections of the specifications, drawings and applicable standards.
2. Quality Assurance/Quality Control – The Contractor shall describe their method of providing and maintaining a high standard of quality with regard to inspection, testing and system certification on this Project. At a minimum, this section will summarize how tests and inspections will be performed in a consistent manner, as well as describing how all test documentation will be developed and maintained in a logical and documented format.
3. Initial Test Procedures and Documentation – Within this section and subsections, the Contractor shall itemize all components and systems to be used on this project and identify if and how they will be inspected and tested by the manufacturer. For items that are not inspected or tested by the manufacturer, the Contractor shall describe their plans methods for inspecting and testing those items on an item-by-item basis.
4. Inspection Procedures and Documentation – Within this section and subsections, the Contractor shall itemize all components and systems to be installed on this project and identify how they will be inspected onsite. This shall include inspection prior to installation as well as post installation inspection. Post installation inspection shall also include the Contractor’s method of installation verification against the latest revision of the approved Contractor’s Installation Plans.
5. Inspection and Testing Outline – The Test Plan shall contain an outline of all inspections and tests to be performed with brief descriptions. The Contractor shall also provide graphical flow charts that identifies the order of all inspections and tests based on dependencies as well as those actions that can be performed in parallel.
6. The Contractor shall inspect and test all components and systems installed under this Contract. Any additional inspections or tests that are not defined herein, but in the opinion of MassDOT Security may be required due to the Contractor’s application and installation, shall be added, fully documented and performed by the Contractor at no additional cost or schedule extension. The Contractor shall adhere to the same requirements as those already identified in these specifications
3.2 QUALITY ASSURANCE/QUALITY CONTROL
A. The Contractor shall provide and/or develop a comprehensive Quality Assurance/Quality Control Plan to be used in support of all inspections and testing as well as for installation and the selection of products.
B. The Contractor may use their corporate Quality Assurance/Quality Control documents where they are applicable to this Project. New processes and procedures shall be created as required by the particular application and systems being installed on the Project.
C. Format – The following represents the general format that the Quality Assurance/Quality Control documents should follow. It is expected that the Contractor shall expand their Quality
September 2025 16899 - 6
Assurance/Quality Control plans and procedures with any and all necessary detail for the application being installed by this Project:
1. Summary – The Contractor shall provide a brief summary outlining the goals and methods of maintaining Quality Assurance/Quality Control.
2. Role and Responsibilities of the Contractor’s Quality Assurance Officer – The Contractor shall define the role and responsibilities of the Project Quality Assurance Officer. At a minimum, this person shall have authority over all Contractor work forces and system elements being installed.
3. Standards Compliance – The Contractor shall identify, index and describe all standards relevant to the work being performed and the system elements being installed on this Project. The Contractor shall describe how compliance shall be maintained through inspections and tests.
4. Methodology of Conducting Inspections and Tests – The Contractor shall describe their approach for maintaining a high degree of quality and consistency across all inspections and tests. The Contractor shall describe how this methodology shall be reflected in the Contractor’s test and inspection procedures.
5. Inspection and Test Data – All Inspection and Test Data shall be recorded in formats submitted and approved by MassDOT Security All test data shall contain all applicable cross references necessary for efficient tracking. Where possible, automated means of generating the test shall be used. This includes the use of test equipment capable of recording and outputting reports as well as screen capture and database reports from processor based systems. All test data shall allow for the documenting of the responsible party conducting the Inspection/Test, MassDOT Security witness, date, test equipment used, etc.
6. Methodology of Developing, Maintaining and Tracking Test Documentation – The Contractor shall describe in detail their method for tracking and certifying all inspection and testing of system elements identified by the Test Plan and the Contract Documents. The process of maintaining all documentation shall be done using a logical approach and in order of dependency on previous tests. The Contractor’s Quality Assurance Officer shall be responsible for ensuring the completeness and accuracy of all test related documents.
7. Discrepancies and Discrepancy Resolution – The Contractor shall develop a comprehensive plan for identifying, tracking and resolving to MassDOT Security’s satisfaction all discrepancies. MassDOT Security shall have final approval over the level of retest required for the resolution of any Discrepancies, in part or complete retest. Any system modifications made after completion of the applicable test procedure shall require the creation of a Discrepancy, including the follow on resolution and retest process by the Contractor.
a. The Contractor shall develop a Discrepancy Report Tracking Form for the purposes of documenting any and all discrepancies identified during this Project.
Each Discrepancy shall have a unique identification for ease of tracking.
b. A Discrepancy shall be generated using the approved Discrepancy Report Tracking Form whenever an issue is detected during inspection/testing, whenever a system element does not meet the requirements of an inspection/test or if any party witnessing the inspection/test deems it appropriate to generate a Discrepancy Report for future resolution.
September 2025 16899 - 7
c. The Contractor shall note on all Test Data Forms and Installation Plans where a discrepancy was initiated with a unique identifier and date for cross referencing and future resolution.
d. Discrepancies resolved at the time of inspection/test shall be tracked as such. A discrepancy shall still be generated and will be given an initial status of resolved.
e. Discrepancies requiring future efforts for resolution will be tracked until they are resolved.
f. Closing of any/all discrepancies can only be done by the MassDOT Security as an acknowledgement that they were satisfactorily resolved.
g. The Contractor shall maintain for the duration of the Project a Discrepancy list.
The Contractor shall provide a copy of this list at the request of the MassDOT Security, during Project Progress Meetings, for field meetings specific to discrepancy resolution, and at any other time that they MassDOT Security requires. The Discrepancy list shall be maintained in a Microsoft Excel Spreadsheet designed by the Contractor and approved by the MassDOT Security.
At a minimum, the spreadsheet shall contain the Discrepancy Report Tracking Form Number, date the discrepancy was generated, description of the discrepancy, status of the discrepancy (open, resolved, closed), date resolved, MassDOT Security witness to the discrepancy resolution, date closed (by MassDOT Security only).
3.3 PRE-INSTALLATION BENCH TESTS AND DOCUMENTATION
A. The Contractor shall bench test at the Contractor’s facility all field assemblies and devices to be installed in order to assure proper operation of all equipment used on this Project, in advance of installation. Step-by-Step test procedures shall be developed by the Contractor for bench testing of all equipment and devices to be installed. These test procedures shall be submitted to MassDOT Security, in advance of testing, for approval.
B. Bench testing and inspections shall be done according to the manufacturer’s recommendations and shall be in compliance with the Quality Assurance/Quality Control process. Evidence of this inspection and testing, including acceptability shall be indicated on the item where practical.
C. The Contractor shall provide confirmation documentation that all system elements and equipment were initially tested by the Contractor and received a “passing” status in meeting all these specifications, before installation. This information shall include signed proof of compliance by the Contractor’s Quality Assurance Officer.
D. If any equipment is found to be defective after installation, it shall be replaced at no cost to MassDOT Security.
3.4 INSPECTION PROCEDURES AND DOCUMENTATION
A. The Contractor shall develop Inspection Procedures that will guide and support the inspection of all components and systems elements as installed, relocated or re-tasked in their final location and as shown on the latest revision of the Contractor’s Installation Plans.
B. Inspection Procedures – The procedures for inspections shall be inclusive of all components and elements that make up the systems as defined by these specifications and drawings. There shall be an Inspection Procedure for each type of component and/or type of installation (conduit, camera, SES cabinet, etc.) The Procedure shall describe in detail why the installed
September 2025 16899 - 8 system element is being inspected, how it will be inspected, and identify the features and characteristics of the component or its installation to be verified – check-off list.
C. Inspection Data Forms and Test Copy of the plans – The Inspection Data Forms shall be developed by the Contractor and will be based on the Contractor’s Inspection Procedure and referenced to (based on) the most current revision of the Contractor’s Installation Plans. The Inspection Data Forms shall provide a way to reference the applicable Inspection Photos. The Contractor shall also provide and maintain a sets of Installation Plans to be used as Test Copies of the Plans. Where more practical than using custom Inspection Data Forms the Test Copies of the plans will be used to document the results of Inspection. A separate set of Test Copy plans shall be used for each Inspection. Only the relevant pages are required. When completed, all Inspection Data Forms, Test Copies of the plans and corresponding inspection photos shall be combined into a standalone PDF document for each component.
D. External Routing – For all conduit, cable and fiber runs, the routing shall be verified against the Contractor’s Installation Plans. Characteristics to be verified include, but are not limited to verification of products installed, means of installation and mounting, cable fill, bend radiuses, routing of wire ways, sealing of conduits, etc.
E. Mounting – For all equipment, junction boxes, cabinets, racks, cases, etc., the installation shall be verified against the Contractor’s Installation Plans, as well as all applicable standards and practices. Characteristics to be verified include, but are not limited to: mounting location, labeling (stenciling/nameplates), method of mounting, clearances, method of securing, etc.
F. Local/Internal Elements – For the installation of all system elements as it relates to equipment racks, equipment internal to cabinets, etc., the installation shall be verified against the Contractor’s Installation Plans, as well as all applicable standards and practices.
Characteristics to be verified include, but are not limited to component mounting, cable entrances, cable isolation, wiring, fiber, strain relief, bend radius, grounding, terminations, mounting, tagging and labeling, etc.
G. Impacts – All elements of the systems being installed under this Project shall be fully inspected to confirm that they are not, and will not be, impacted by existing infrastructure.
Conversely, the existing systems and structures adjacent to the systems installed as part of this Project shall be checked to confirm that their operation or integrity is not, and cannot be impacted by the newly installed systems. To comply with this requirement the Contractor shall make every effort to install the new system elements so that they do not coexist with existing infrastructure. Where proximities are tight, the Contractor, through the MassDOT Security Project Office, shall involve the necessary MassDOT Security departments or external utilities as needed to gain an understanding of the necessary criteria for isolation and/or possible approval for their design and application. The Contractor shall make no assumptions that their application and installation supersedes existing infrastructure functionality.
H. Discrepancies – Discrepancy reports shall be generated for all situations where the Contractor’s Installation Plans do not match the field conditions, where the Contractor’s Installation Plans are lacking for information, or if the field conditions are considered to be unacceptable. The Contractor shall be responsible for updating all plans to reflect all details of the actual field conditions. Where the physical route, location or method of installation is determined to be unacceptable, the Contractor shall determine a new, more acceptable route, location or method, followed by updating the installation and/or plans as needed.
September 2025 16899 - 9
I. Format – The following represents a sample of the Inspections to be performed and the general format that the Documentation should follow. It is expected that the Contractor will expand the required Inspection Procedures and Documentation with any and all necessary detail for complete and proper inspection of the application being installed on this Project:
1. Summary – This section shall describe the purpose and general methods to be used for the Inspection process, as well as the documentation to be used and provided for tracking.
2. Index/Table of Contents – The Contractor shall create an Index/Table of Contents that identifies the Inspection Procedure for each type of system element and installation type. For example a common Inspection Procedure could be used for all camera installations so long as the test data forms allow for the unique identification of each camera and camera location.
3. Dependencies – The Contractor shall identify and document any dependencies between Inspections that must be accounted for, or have been successfully concluded prior to a particular Inspection taking place. The Contractor shall represent this information in both a written description and with a block diagram indicating Inspections that must be performed in either a serial or parallel manner. The Contractor shall also identify any restrictions in the ability to conduct complete and detailed inspections for MassDOT Security consideration and approval.
4. Inspection Procedures – Using the following as examples the Contractor shall develop detailed Inspection Procedures according to their application and as required by these Contract Documents. The Inspection Procedures will be refined in the submittal review process with MassDOT Security. If while in the process of Inspection, it is determined by MassDOT Security that additional requirements and Inspection Procedures are needed, the Contractor shall generate those updates or additional procedures in compliance with the requirements of these Contract Documents.
a. Cable, Fiber, Conduit, etc, Routing and Installation Inspection – This procedure shall be designed and used to confirm that all cable, fiber, conduit, etc., runs are in accordance with all Contract requirements.
1) Confirm that all Cable, Fiber, Conduit, etc. are installed as shown in the
Contractor’s Installation Plans, including routing, support method, transitions, end-points (rooms, Junction Boxes, Equipment Cabinets), etc.
2) Confirm that the installation is properly and sufficiently supported. Where possible closely inspect and mechanically stress a sample of the support elements to ensure they are not lose or fail. All mounts that seem visually compromised shall be tested.
3) Confirm that the Contractor used the submitted products only for the installation. All products shall be listed on the test data sheet for verification.
4) Confirm that the installation does not interfere with any clearance envelopes.
This includes but is not limited to train dynamic envelopes, public passage clearance, clearance for maintenance and other activities for the newly installed systems as well as existing infrastructure.
5) Confirm that the installation does not interfere with architectural elements of any and all public spaces except where previously approved by MassDOT Security. The Contractor shall make submittals specifically identifying conflicts or issues with architectural elements.
6) Confirm that the Cable/Fiber fill is appropriate and does not exceed standards.
September 2025 16899 - 10
7) Confirm mechanical isolation between low voltage and high voltage systems.
No colocation within the same support or containment system.
8) Confirm that where entrance and exits exist that there is proper application of anti-chaffing and mechanical strain relief for a high vibration environment.
9) Verify that all components are as submitted and that there are no substitutions.
10) The test data forms for this procedure shall be a combination of a check-off lists and a Test Copy of the Installation Plans for verification of the cable/fiber routing and transitions. Where the routing is confirmed, the Contractor shall trace the line over with a green pencil. Where the routing cannot be confirmed or deviates from the Installation Plans, the Contractor shall mark the plans in Red Pencil and generate the necessary Discrepancy Reports. Any failures to pass inspections documented on the check-off lists shall also result in the Contractor generating a Discrepancy.
b. Power Feed and Source Inspection – This procedure shall be designed and used to confirm that all power feeds and sources are as required for the application defined by the Contract Documents, manufacturer’s recommendations and as shown in the MassDOT Security approved Contractor developed Installation Plans.
1) Confirm that the installation of all newly installed breaker panels are located as shown in the Installation Plans and in accordance with all code requirements.
2) Confirm that the installation of all new breakers are installed in the location shown on the Installation Plans and that the capacity is appropriate for the expected load.
3) Confirm that all wiring is properly sized, terminated, dressed, strain relieved, etc. Where possible very the mechanical connection of all conductors by straining the wire.
4) Verify that all components are as submitted and that there are no substitutions.
5) Confirm that all panels, breakers, cables, wires, etc. are properly tagged and labeled with the appropriate nomenclature and description.
6) The test data forms for this procedure shall be check-off lists with all components to be verified identified within the lists. Any failures to pass inspections documented on the check-off lists shall also result in the Contractor generating a Discrepancy.
c. Cabinet, Junction Box Mounting Inspection – This procedure shall be designed and used to confirm that all cabinets, junction boxes and other devices are properly mounted at the locations as shown in the MassDOT Security approved Contractor developed Installation Plans and as required by the Contract Documents.
1) Confirm that the installation of the newly installed Junction Box is located as shown on the Installation Plans.
2) Confirm that the installation is sufficient for the weight and size of the Junction
Box.
3) Confirm that the components used in mounting the junction Box are of the proper material for the location (galvanized, stainless, etc.) and are the same as was submitted for use in this application.
4) Confirm that the Junction Box door is secured properly and that the hinges, handle and locking system function as intended.
5) Confirm that all cabling and conduit entrances are properly secured, sealed, de-burred, etc.
September 2025 16899 - 11
6) The test data forms for this procedure shall be check-off lists with all components to be verified identified within the lists. Any failures to pass inspections documented on the check-off lists shall also result in the Contractor generating a Discrepancy.
d. Junction Box Local/Internal Installation and Wiring Inspection – This procedure shall be designed and used to confirm that all components and materials that make up a Junction Box are properly installed, terminated, tagged, labeled, secured, sealed, etc., in compliance with the Contract Documents, manufacturer’s recommendations and MassDOT Security approved Contractor developed Installation Plans.
1) Confirm that all cabling and conduit entrances are properly secured, sealed, de-burred, etc.
2) Confirm that the cabinet door, handle and locking mechanism are functioning properly and can be secured.
3) Verify that all components are as submitted and that there are no substitutions.
4) Confirm that all wire terminations are properly made. Verify the mechanical integrity of the connections by straining the conductors and connectors. Check for loose or improperly tightened terminals.
5) Verify the slack of all cables and fiber are properly dressed and that none of the bends exceeds the manufacturer’s recommendations for bend radius.
6) Confirm that all wires, terminals, fibers, etc. are properly tagged and labeled with the appropriate nomenclature. Verify that the Junction Box is labeled (stenciled) according to the Installation Plans.
7) The test data forms for this procedure shall be a combination of a check-off lists and a Test Copy of the Installation Plans for verification of the cable/fiber routing and transitions. Where the conductors and terminals cannot be confirmed or deviates from the Installation Plans, the Contractor shall mark the plans in Red Pencil and generate the necessary Discrepancy Reports. Any failures to pass inspections documented on the check-off lists shall also result in the Contractor generating a Discrepancy.
e. SES Cabinet Local/Internal Installation and Wiring Inspection – This procedure shall be designed and used to confirm that all system components, wiring, fiber, terminations, etc., are in compliance with the Contract Documents, manufacturer’s recommendations and MassDOT Security approved Contractor developed Installation Plans.
1) Confirm that all cabling and conduit entrances are properly secured, sealed, de-burred, etc.
2) Confirm that the cabinet door, handle and locking mechanism are functioning properly and can be secured.
3) Confirm the installation of a ground faulted utility outlet. Verify that it is properly mounted and secured.
4) Verify that all components are as submitted and that there are no substitutions.
5) Confirm the installation of the Ethernet Network Switch. Check for proper make and model, as well as the method of installation against the Installation Plans. Verify that the Ethernet Switch is mechanically secured.
6) Confirm the installation of the Fiber Splice Panel. Check for proper make and model, as well as the method of installation against the Installation Plans.
September 2025 16899 - 12
Check that it is securely mounted and properly protecting the fiber splices and terminations.
7) Confirm the Installation of the DIN Rail mounting system. Check for proper installation against the Installation Plans. Make sure the DIN Rail is tight to the mounting surface.
8) Confirm the installation of the DIN Rail mounted terminals. Check for proper mounting and securing to the DIN Rail. Strain the terminals to verify the mechanical integrity.
9) Confirm the Installation of the DC Power Supply. Check for proper make and model, as well as method of installation against the Installation Plans.
10) Confirm that all wire terminations are properly made. Verify the mechanical integrity of the connections by straining the conductors and connectors. Verify that all terminals are not lose or over tightened.
11) Confirm that all equipment, wires, terminals, etc., are labeled and tagged with the appropriate nomenclature according to the Installation Plans. Verify that the SES cabinet is properly labeled (stenciled) according to the Installation Plans.
12) Verify the slack of all cables and fiber are properly dressed and that none of the bends exceeds the manufacturer’s recommendations for bend radius.
13) Confirm that at CAT 6 network cables have been routed neatly and secured with Velcro-type straps of the proper length.
14) The test data forms for this procedure shall be a combination of a check-off lists and a Test Copy of the Installation Plans for verification of the cable/fiber routing and transitions. Where the routing is confirmed, the Contractor shall trace the line over with a green pencil. Where the routing cannot be confirmed or deviates from the Installation Plans, the Contractor shall mark the plans in Red Pencil and generate the necessary Discrepancy Reports. Any failures to pass inspections documented on the check-off lists shall also result in the Contractor generating a Discrepancy.
f. Batteries and Battery Chargers – This procedure shall be designed and used to confirm that all batteries and battery chargers are properly installed and cabled in compliance with the Contract Documents, manufacturer’s recommendations and the Contractor’s application.
1) Confirm that the battery charger and batteries are as submitted and that there are no substitutions.
2) Confirm that the battery charger is properly mounted and secured
3) Confirm that the battery charger chassis is grounded
4) Inspect the Inside of the battery charger and confirm that all wires, terminations, components, etc., are properly assembled and appear to be unused. Check terminations of external wires for proper tagging, termination, etc.
5) Verify that the manufacturer’s characteristics plate is secure to the face of the battery charger and that the stated values match the expected values for the application.
6) Confirm that all cabling and conduit is installed as shown in the Installation Plans and as required by the application.
7) Confirm that all cabling is of the proper size and as shown on the Installation Plans.
September 2025 16899 - 13
8) Confirm that the batteries are as submitted and that there are no substitutions.
9) Confirm that the batteries are mechanically secured as shown in the Installation
Plans and that they are housed in a properly sized battery tray.
10) Confirm that the battery terminals and terminations are properly torqued and lubricated with conductive grease.
11) Confirm that all equipment, wires, terminals, etc., are labeled and tagged with the appropriate nomenclature according to the Installation Plans. Confirm that the battery charger and battery bank are properly labeled.
12) Demonstrate that the UPS and batteries have been sized properly to power the connected load for the time duration required per the Specifications. This demonstration shall require that the AC power to the UPS be disconnected and the protected equipment observed to operate for the time period required.
13) The test data forms for this procedure shall be a combination of a check-off lists and a Test Copy of the Installation Plans for verification of the cable routing and transitions. Where the routing cannot be confirmed or deviates from the Installation Plans, the Contractor shall mark the plans in Red Pencil and generate the necessary Discrepancy Reports. Any failures to pass inspections documented on the check-off lists shall also result in the Contractor generating a Discrepancy.
g. Uninterruptable Power Supply (UPS) – This procedure shall be designed and used to confirm that all Uninterruptable Power Supplies and associated batteries are properly installed and cabled in compliance with the Contract Documents, manufacturer’s recommendations and the Contractor’s application.
1) Confirm that the UPS and batteries are as submitted and that there are no substitutions.
2) Confirm that the UPS is properly mounted and secured
3) Confirm that the UPS chassis is grounded
4) Check terminations of external wires for proper tagging, termination, etc.
5) Confirm that all cabling and conduit is installed as shown in the Installation
Plans and as required by the application.
6) Confirm that all cabling is of the proper size and as shown on the Installation
Plans.
7) Confirm that the batteries are as submitted and that there are no substitutions.
8) Confirm that the batteries are mechanically secured as shown in the Installation
Plans and that they are housed in a properly sized battery tray.
9) Confirm that all equipment, wires, terminals, etc., are labeled and tagged with the appropriate nomenclature according to the Installation Plans. Confirm that the battery charger and battery bank are properly labeled.
10) The test data forms for this procedure shall be a combination of a check-off lists and a Test Copy of the Installation Plans for verification of the cable routing and transitions. Where the routing cannot be confirmed or deviates from the Installation Plans, the Contractor shall mark the plans in Red Pencil and generate the necessary Discrepancy Reports. Any failures to pass inspections documented on the check-off lists shall also result in the Contractor generating a Discrepancy
h. CCTV Camera Installation Inspection – This procedure shall be designed and used to confirm that all CCTV Cameras and associated components are properly
September 2025 16899 - 14 installed in compliance with the Contract Documents, manufacturer’s recommendations and MassDOT Security approved Contractor developed Installation Plans
1) Confirm that the CCTV Camera and the mounting system is as submitted and that no substitution has been made.
2) Confirm that the CCTV Camera located as shown on the Installation Plans.
3) Confirm that the Camera is properly mounted and secured as shown on the
Installation Plans and as required by the Contract Documents. Generally verify that the camera is aimed in the proper direction and that it has an unobstructed view.
4) Confirm that all equipment, wires, terminals, etc., are labeled and tagged with the Appropriate nomenclature according to the Installation Plans.
5) The test data forms for this procedure shall be a combination of a check-off lists and a Test Copy of the Installation Plans for verification of the cable routing and transitions. Where the routing cannot be confirmed or deviates from the Installation Plans, the Contractor shall mark the plans in Red Pencil and generate the necessary Discrepancy Reports. Any failures to pass inspections documented on the check-off lists shall also result in the Contractor generating a Discrepancy.
i. Access Control Door Locking Hardware (Locks and Strikes)
1) Demonstrate all Access Control Door Locks and Strikes are fully operational.
2) Ensure that all Door Cords and wiring are secure.
j. Access Control Door Contacts
1) Demonstrate all Access Control Door Contacts are fully operational.
2) Ensure that all contacts and wiring are secure.
k. Access Control Card Readers
1) Demonstrate all Access Control Door Card Readers are fully operational.
l. Telephone System
1) Demonstrate that all telephones are assigned numbers.
2) Demonstrate that all telephones can make local and long distance calls.
3) Demonstrate that all telephones can receive calls.
4) Demonstrate that all telephone numbers assigned voice mail receive voice mail when the line is unanswered.
5) Demonstrate that all telephone numbers assigned voice mail receive voice mail when the line is busy.
6) Demonstrate intercom calling between all telephones.
3.5 TEST PROCEDURES AND DOCUMENTATION
A. The Contractor shall develop Test Procedures that will guide and support the testing of all system elements and their functions as well as testing the system as a whole.
B. Test Procedures – The Contractor shall develop Acceptance Test Procedures and methods that when performed will completely exercise each component and shall cause each installed system and subsystem to be sequenced through its required operations, including the imposition of simulated conditions to demonstrate that the installation in its final
September 2025 16899 - 15 configuration complies with all specified design requirements and operational functions. All application software, firmware, settings databases, user interfaces, network settings, alignment, etc., shall be verified for compliance and will be the latest stable revision. Testing Procedures shall be developed for the newly installed systems as well as any existing systems that are impacted or are close enough in proximity to the newly installed systems as to warrant testing of the existing systems.
C. The simultaneous recording of data for Test Procedures being performed simultaneously for efficiency shall be considered only if the Contractor demonstrates to MassDOT Security that the simultaneous performance of tests will not in any way degrade the test process or data in any way. The Contractor shall submit all necessary backup documentation within their Test Plan.
D. Test Procedure Data Forms – The Test Procedure Data Forms shall be developed by the Contractor and will be based on the Contractor’s Test Procedures and referenced to (based
on) the Contractor’s application and the Contractor Documents. The Test Procedure Data Forms shall make allowances for referencing electronic means of recording data and eventual combining of all test and configuration data into a standalone PDF file for each system element.
E. Electronic Documentation – The Contractor shall make use of electronic documentation whenever possible. This includes but is not limited to screen dumps/prints, video, photos, data dumps, etc. This data shall serve as proof of configuration verification and testing. All electronic data shall become the property of MassDOT Security. All electronic data developed while testing shall become part of the test data and record documents.
F. Impacts – All elements of the systems being installed under this Project shall be fully exercised and monitored to confirm that they are not and will not be impacted by existing systems. Conversely, the existing systems impacted by and adjacent to the systems installed as part of this Project shall be checked to confirm that their operation or integrity is not, and cannot be impacted by the newly installed systems. To comply with this requirement the Contractor shall make every effort to install the new system elements so that they do not coexist with existing infrastructure. Where proximities are tight, the Contractor, through the MassDOT Security Project Office, shall involve the necessary MassDOT Security departments or external utilities as needed to gain an understanding of the necessary criteria for isolation and/or possible approval for their design and application. The Contractor shall make no assumptions that their application and installation supersedes existing infrastructure functionality.
G. Discrepancies – Discrepancy reports shall be generated for all situations where the system functionality of the Contractor’s Installation does do…