Appendix H_2026-05-01 - CCD Immersive Learning Lab - Bid Set - Specs.pdf
PDF 15 MB Posted
- Solicitation number
- IFB1 GMAA 2026000184 4
- Issued by
- Denver County, Denver City, Colorado
About this file
This is a Project Manual and Bid Set Specifications document for the Community College of Denver (CCD) Immersive Learning Lab, a tenant improvement project located at 1111 W Colfax Ave, Denver, CO 80204, under the Auraria Higher Education Center. The project consists of approximately 4,256 square feet of interior renovation within the Cherry Creek Building to create an immersive learning environment, including an immersive classroom, free-roam VR pod, front-of-house spaces, and associated support areas. The Work encompasses architectural, structural, mechanical, electrical, and low-voltage systems; raised access flooring; lighting and controls; new partitions, doors, and finishes; and infrastructure required to support vendor-furnished immersive technology systems. The facility is classified as Business (B) and IIA Construction. The project will be constructed under coordinated, concurrent multiple contracts, with the General Construction Contract covering all building systems, infrastructure, and finishes, while a separate Dreamscape Learn Contract will furnish and install immersive technology systems including VR equipment, tracking systems, render servers, and specialty equipment. The Architect is Clark & Enersen, with contact Tim Ripp, and the Owner's Representative is Heather Hardman (heather.hardman@ahec.edu). The specifications establish comprehensive administrative and procedural requirements for contract management, including submittal procedures, quality requirements, payment procedures, change order processes, and project coordination protocols. Contractors must submit a schedule of values, construction schedule, and various submittals including Shop Drawings, Product Data, and Samples within specified timeframes, with the Architect allowing 14 days for initial review and 14 days for resubmittal review. The project includes one identified alternate for replacing three existing fire dampers on existing 24-inch round supply air ductwork if deemed necessary based on damper capabilities. Progress meetings will be conducted at regular intervals, with preconstruction conferences required before construction begins and preinstallation conferences mandated for activities requiring coordination. The markup percentage for all changes in the work shall not exceed 10 percent, and the Contractor must coordinate closely with the separate Dreamscape Learn contractor to ensure a dust-free environment and operational facility infrastructure before immersive system installation commences prior to Substantial Completion.
The specifications require Contractor-initiated cost proposals for changes within 14 days, with detailed breakdowns of quantities, unit costs, applicable taxes, delivery charges, equipment rental, labor, and supervision costs. All submittals must be coordinated with the construction schedule and submitted electronically in PDF format along with transmittal forms containing project identification and submittal tracking information. The document does not specify contract pricing, payment terms, set-asides, or funding sources in the excerpted sections provided. Specific quality-assurance and quality-control requirements are delegated to individual specification sections, with Contractors required to submit a quality-control plan within 10 days of Notice to Proceed. Testing and inspection services must verify compliance with specifications, with reports prepared by qualified testing agencies documenting results and interpretations. The project operates under Colorado Office of the State Architect (OSA) standards and forms, including OSA form SC 6.31 for Change Orders and SC-6.311 for Construction Change Directives. Owner retains the right to occupy and install equipment in completed portions of the Work prior to Substantial Completion, provided such occupancy does not interfere with construction completion. The building operates as a nonsmoking facility with restrictions on tobacco and controlled substances within 25 feet of entrances, operable windows, or outdoor-air intakes, and construction activities must not interrupt utilities serving Owner-occupied areas without at least two days' advance notice.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
CCD Immersive Learning Lab
Denver, CO
05/01/2026
Clark & Enersen Project No.:
295-016-25
Architect Electrical Engineer Mechanical Engineer
(Coordinating Professional)
Clark & Enersen, Inc.
Architecture Contact: Tim Ripp
Engineering Contact: TJ Schirmer
1010 Lincoln Mall, Suite 200
Lincoln, NE 68508
COA No. CA0029AE
Note that this information is being provided as required by state statues for an organization.
The individual in responsible charge for design is designated by the professional stamps on individual drawings.
Please follow information in the Project Manual for submitting questions during bidding or construction.
CCD Immersive Learning Lab 05/26
Clark & Enersen Project No.: 295-016-26
TABLE OF CONTENTS 00 00 03 - 1
SECTION 00 00 03 - TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
• 01 10 00 Summary
• 01 23 00 Alternates
• 01 25 00 Substitution Procedures
• 01 26 00 Contract Modification Procedures
• 01 29 00 Payment Procedures
• 01 31 00 Project Management and Coordination
• 01 33 00 Submittal Procedures
• 01 40 00 Quality Requirements
• 01 50 00 Temporary Facilities and Controls
• 01 60 00 Product Requirements
• 01 73 00 Execution
• 01 77 00 Closeout Procedures
• 01 78 23 Operation and Maintenance Data
• 01 78 39 Project Record Documents
• 01 79 00 Demonstration and Training
DIVISION 02 – EXISTING CONDITIONS
• 02 41 19 Selective Demolition
DIVISION 03 – CONCRETE
DIVISION 04 – MASONRY
DIVISION 05 – METALS
• 05 43 00 Slotted Channel Framing
• 05 52 13 Pipe and Tube Railings
DIVISION 06 – WOODS, PLASTICS AND COMPOSITES
• 06 10 00 Rough Carpentry
• 06 16 00 Sheathing
• 06 40 23 Interior Architectural Woodwork
TABLE OF CONTENTS 00 00 03 - 2
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
• 07 84 13 Penetration Firestopping
• 07 84 46 Fire-Resistive Joint Systems
• 07 92 00 Joint Sealants
• 07 92 19 Acoustical Joint Sealants
DIVISION 08 – DOORS AND WINDOWS
• 08 10 00 Interior Aluminum Door & Glazing Frames
• 08 11 13 Hollow Metal Doors and Frames
• 08 14 16 Flush Wood Doors
• 08 71 00 Door Hardware
• 08 80 00 Glass and Glazing
DIVISION 09 – FINISHES
• 09 22 16 Non-Structural Metal Framing
• 09 29 00 Gypsum Board
• 09 51 13 Acoustical Panel Ceilings
• 09 65 13 Resilient Base and Accessories
• 09 68 13 Tile Carpeting
• 09 91 23 Interior Painting
DIVISION 10 – SPECIALTIES
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 – SPECIAL CONSTRUCTION
DIVISIONS 14 – NOT USED
TABLE OF CONTENTS 00 00 03 - 3
DIVISION 21 – FIRE SUPPRESSION
DIVISION 22 – PLUMBING
• 22 05 00 Basic Plumbing Requirements
• 22 05 29 Plumbing Hangers and Supports
• 22 05 53 Plumbing Identification
• 22 07 19 Plumbing Piping Insulation
• 22 10 00 Plumbing Piping
DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING
• 23 00 00 Mechanical Demolition
• 23 05 00 Basic HVAC Requirements
• 23 05 00 Pressure Test Log
• 23 05 19 HVAC Meters and Gauges
• 23 05 29 HVAC Hangers and Supports
• 23 05 30 HVAC Firestopping
• 23 05 53 HVAC Identification
• 23 05 93 Testing, Adjusting, and Balancing
• 23 07 13 Ductwork Insulation
• 23 07 19 HVAC Piping Insulation
• 23 09 00 Digital Control Equipment
• 23 09 01 Instruments and Control Elements
• 23 21 13 Hydronic Piping
• 23 21 16 Hydronic Specialties
• 23 31 13 Ductwork
• 23 33 00 Ductwork Accessories
• 23 36 00 Air Terminal Units
• 23 37 00 Air Outlets and Inlets
• 23 81 23 Ductless Split System Air Conditioners
DIVISION 26 – ELECTRICAL
• 26 05 00 Electrical General Provisions
• 26 05 01 Basic Materials and Methods
• 26 05 19 Conductors
• 26 05 26 Grounding System
• 26 05 33 Raceways
• 26 22 00 Dry-Type Transformers
TABLE OF CONTENTS 00 00 03 - 4
• 26 24 16 Panelboards
• 26 27 26 Wiring Devices
• 26 51 00 Lighting
DIVISION 27 – COMMUNICATIONS
• 27 00 00 Communications
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
• 28 00 00 Electronic Safety and Security
DIVISION 31 – EARTHWORK
DIVISION 32 – EXTERIOR IMPROVEMENTS
DIVISION 33 – NOT USED
APPENDIX
END OF SECTION 00 00 03
SUMMARY 01 10 00 - 1
SECTION 01 10 00 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work by Owner.
4. Work under separate contracts.
5. Access to site.
6. Coordination with occupants.
7. Work restrictions.
8. Specification and drawing conventions.
B. Related Requirements:
1. Section 01 50 00 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.3 PROJECT INFORMATION
A. Project Identification: Auraria Higher Education Center, Community College of Denver Immersive Learning Lab.
1. Project Location: 1111 W Colfax Ave, Denver, CO 80204.
B. Owner: Auraria Higher Education Center- Building / Community College of Denver - Tenant.
1. Owner's Representative: Heather Hardman.
a. Contact: heather.hardman@ahec.edu
C. Architect: Clark & Enersen.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. The Project consists of tenant improvements within the Community College of Denver
Cherry Creek Building to accommodate a new immersive learning environment. The
SUMMARY 01 10 00 - 2
Work includes construction of approximately 4,256 SF of interior renovation, including an immersive classroom, free-roam VR pod, front-of-house spaces, and associated support areas.
Work includes architectural, structural, mechanical, electrical, and low-voltage systems;
raised access flooring; lighting and controls; new partitions, doors, and finishes; and infrastructure required to support vendor-furnished immersive technology systems.
The facility is classified as Business (B) and IIA Construction.
B. Type of Contract:
1. Project will be constructed under coordinated, concurrent multiple contracts. Contracts for this Project include the following:
a. General Construction Contract: Construction of all building systems, infrastructure, and finishes required to support the immersive learning environment.
b. Dreamscape Learn Contract: Furnishing and installation of immersive technology systems, including VR equipment, tracking systems, render servers, and specialty equipment.
1.5 WORK BY OWNER
A. General: Cooperate fully with Owner so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner.
B. Concurrent Work: Owner retains the right to perform construction operations at Project site.
Those operations will be conducted simultaneously with work under this Contract.
1.6 WORK UNDER SEPARATE CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts.
Coordinate the Work of this Contract with work performed under separate contracts.
B. Concurrent Work: Owner has awarded separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.
1. Dreamscape Learn Immersive Technology Contract:
2. To Dreamscape Learn (DSL): Furnishing and installation of immersive learning systems including VR headsets, tracking systems, render server racks, lighting trusses, special effects systems, immersive classroom equipment, and free-roam pod equipment. Work includes coordination with Contractor for installation sequencing and integration with building systems. DSL’s work is dependent on completion of supporting infrastructure by the Contractor, including power, data, HVAC, structural support, and architectural construction required for installation.
SUMMARY 01 10 00 - 3
3. The Contractor shall provide a complete and operational facility ready to receive vendor-installed immersive systems. This includes all architectural, structural, mechanical, electrical, and data infrastructure required to support the Dreamscape Learn systems.
Installation of immersive systems by Dreamscape Learn shall occur after completion of supporting construction and achievement of a “dust-free” environment, but prior to Substantial Completion. Contractor shall coordinate closely with Dreamscape Learn to support installation activities and integration with building systems.
1.7 ACCESS TO SITE
A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to areas indicated on drawings.
2. Driveways, Walkways and Entrances: Keep driveways, loading areas and entrances serving premises clear and available to Owner, Owner’s employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.
1.8 COORDINATION WITH OCCUPANTS
A. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations.
B. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.
SUMMARY 01 10 00 - 4
1. Architect will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work.
2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited Owner occupancy.
3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work.
4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.
1.9 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Construction Manager and Owner not less than two days in advance of proposed utility interruptions.
C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify Construction Manager and Owner not less than two days in advance of proposed utility interruptions.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet (8 m) of entrances, operable windows, or outdoor-air intakes.
E. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.
1.10 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
SUMMARY 01 10 00 - 5
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 10 00
ALTERNATES 01 23 00 - 1
SECTION 01 23 00 - ALTERNATES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for alternates.
1.3 DEFINITIONS
A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.
1. Alternates described in this Section are part of the Work only if enumerated in the Agreement.
2. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum.
1.4 PROCEDURES
A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.
1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate.
B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each alternate. Indicate if alternates have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated revisions to alternates.
C. Execute accepted alternates under the same conditions as other work of the Contract.
D. Schedule: A schedule of alternates is included at the end of this Section. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.
ALTERNATES 01 23 00 - 2
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF ALTERNATES
A. Alternate No. 1: Replace existing fire dampers
1. Base Bid: Do not replace existing fire dampers installed within existing 24” round supply air ductwork. There are three existing dampers. One damper is located at the point where the ductwork exits the mechanical room, and the other two are shown on the plans.
2. Alternate: Provide a price to replace all three existing fire dampers on the existing 24” round supply air ductwork if necessary based on the capabilities of the existing units.
END OF SECTION 01 23 00
SUBSTITUTION PROCEDURES 01 25 00 - 1
SECTION 01 25 00 - SUBSTITUTION PROCEDURES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.
3. The following are not considered to be requests for substitutions:
a. Substitutions requested during the bidding period, and accepted by Addendum prior to award of the Contract, are included in the Contract Documents and are not subject to requirements specified in this Section for substitutions.
b. Revisions to the Contract Documents requested by the Owner or Architect.
c. Specified options of products and construction methods included in the Contract
Documents.
d. The Contractor’s determination of and compliance with governing regulations and orders issued by governing authorities.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
SUBSTITUTION PROCEDURES 01 25 00 - 2
a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.
b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section.
Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
h. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
i. Cost information, including a proposal of change, if any, in the Contract Sum.
j. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.
k. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
2. Architect’s Action: If necessary, Architect will request additional information or documentation for evaluation within seven (7) days of receipt of a request for substitution.
Architect will notify Contractor of acceptance or rejection of proposed substitution within fourteen (14) days of receipt of request, or seven (7) days of receipt of additional information or documentation, whichever is later.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
SUBSTITUTION PROCEDURES 01 25 00 - 3
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
i. The request is directly related to an “or-equal” clause or similar language in the Contract Documents.
j. The specified product of method of construction cannot be provided in a manner that is compatible with other materials and where the Contractor certifies that the substitution will overcome the incompatibility.
B. Substitutions for Convenience: Architect will consider requests for substitution if received within sixty (60) days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.
b. Requested substitution does not require extensive revisions to the Contract Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated results.
d. Substitution request is fully documented and properly submitted.
e. Requested substitution will not adversely affect Contractor's construction schedule.
SUBSTITUTION PROCEDURES 01 25 00 - 4
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work.
h. Requested substitution has been coordinated with other portions of the Work.
i. Requested substitution provides specified warranty.
j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
k. The request is directly related to an “or-equal” clause or similar language in the Contract Documents.
END OF SECTION 01 25 00
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 1
SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
B. Related Requirements:
1. Section 01 25 00 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
1.3 CHANGE-ORDER BULLETIN (COB)
A. Architect/Owner-Initiated Change-Order Bulletin: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum and/or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Change-order bulletin is issued by Architect are not instructions either to stop work in progress or to execute the proposed change.
2. Within fourteen (14) days after receipt of Change-order bulletin, submit a quotation estimating cost adjustments to the Contract Sum and The Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Mark-up percentage for all changes in the work shall not exceed 10%.
e. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
f. Quotation Form: Use form acceptable to Architect.
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 2
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Mark-up percentage for all changes in the work shall not exceed 10%.
6. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
7. Comply with requirements in Section 01 25 00 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
8. Proposal Request Form: Use form acceptable to Architect.
1.4 CHANGE ORDER PROCEDURES
A. On Owner’s approval of a Work Changes Change-order bulletin, Architect will issue a Change Order for signatures of Owner and Contractor on Colorado Office of the State Architect (OSA) form SC 6.31 – Change Order
1.5 CONSTRUCTION CHANGE DIRECTIVE:
A. Architect may issue a Change Order Bulletin (Colorado Office of the State Architect (OSA) form SC-6.311. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01 26 00
PAYMENT PROCEDURES 01 29 00 - 1
SECTION 01 29 00 - PAYMENT PROCEDURES
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
1.3 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.
1.4 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor’s construction schedule.
1. Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following:
a. Application for Payment forms with continuation sheets.
b. Submittal schedule.
c. Items required to be indicated as separate activities in Contractor's construction schedule.
2. Submit the schedule of values to Architect at earliest possible date, but no later than seven (7) days before the date scheduled for submittal of initial Applications for Payment.
3. Subschedules for Phased Work: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values coordinated with each phase of payment.
4. Subschedules for Separate Elements of Work: Where the Contractor's construction schedule defines separate elements of the Work, provide subschedules showing values coordinated with each element.
5. Subschedules for Separate Design Contracts: Where the Owner has retained design professionals under separate contracts who will each provide certification of payment requests, provide subschedules showing values coordinated with the scope of each design services contract as described in Section 01 10 00 "Summary."
PAYMENT PROCEDURES 01 29 00 - 2
B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.
1. Identification: Include the following Project identification on the schedule of values:
a. Project name and location.
b. Name of Architect.
c. Architect's project number.
d. Contractor's name and address.
e. Date of submittal.
2. Arrange schedule of values consistent with format of AIA Document G703.
3. Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed:
a. Related Specification Section or Division.
b. Description of the Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
e. Name of supplier.
f. Change Orders (numbers) that affect value.
g. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.
1) Labor.
2) Materials.
3) Equipment.
4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with Project Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five (5) percent of the Contract Sum.
a. Include separate line items under Contractor and principal subcontracts for Project closeout requirements in an amount totaling five (5) percent of the Contract Sum and subcontract amount.
5. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
6. Provide a separate line item in the schedule of values for each part of the Work where
Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
a. Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance.
7. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
8. Allowances: Provide a separate line item in the schedule of values for each allowance.
Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.
PAYMENT PROCEDURES 01 29 00 - 3
9. Purchase Contracts: Provide a separate line item in the schedule of values for each purchase contract. Show line-item value of purchase contract. Indicate owner payments or deposits, if any, and balance to be paid by Contractor.
10. Each item in the schedule of values and Applications for Payment shall be complete.
Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.
11. Schedule Updating: Update and resubmit the schedule of values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.
1.5 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.
B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.
C. Application for Payment Forms: Use forms provided by Colorado Office of the State Architect
(OSA)
D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.
1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.
E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.
1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment, for stored materials.
2. Provide supporting documentation that verifies amount requested, such as paid invoices.
Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.
3. Provide summary documentation for stored materials indicating the following:
PAYMENT PROCEDURES 01 29 00 - 4
a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.
b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.
c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.
F. Transmittal: Submit three (3) signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt. One copy shall include waivers of lien and similar attachments if required.
G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of values.
3. Contractor's construction schedule (preliminary if not final).
4. Copies of building permits.
5. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
6. Certificates of insurance and insurance policies.
7. Performance and payment bonds.
H. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
3. Occupancy permits and similar approvals.
4. Application for reduction of retainage, and consent of surety.
5. Advice on shifting insurance coverage.
6. List of incomplete Work of Substantial Completion.
I. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."
5. AIA Document G706A, "Contractor's Affidavit of Release of Liens."
6. AIA Document G707, "Consent of Surety to Final Payment."
7. Evidence that claims have been settled.
8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.
PAYMENT PROCEDURES 01 29 00 - 5
9. Final liquidated damages settlement statement.
10. Completion of items specified for completion after Substantial Completion.
11. Proof that taxes, fees and similar obligations have been paid.
12. Removal of temporary facilities and services.
13. Removal of surplus materials, rubbish and similar elements.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01 29 00
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 1
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. Requests for Information (RFIs).
4. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.
1.3 DEFINITIONS
A. RFI: Request from Owner, Construction Manager, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.
B. INFORMATIONAL SUBMITTALS
C. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
D. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses.
Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 2
1. Post copies of list in project meeting room, in temporary field office, by each temporary telephone. Keep list current at all times.
1.4 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Inspection of Conditions: Require the Installer of each major component to inspect both the substrate and conditions under which Work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
C. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.
D. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
E. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
F. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 3
1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.
1.5 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Use applicable Drawings as a basis for preparation of coordination drawings.
Prepare sections, elevations, and details as needed to describe relationship of various systems and components.
b. Coordinate the addition of trade-specific information to the coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
d. Indicate clear space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
f. Indicate required installation sequences.
g. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 4
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
7. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches (32 mm) in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
8. Fire-Protection System: Show the following:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
9. Review: Architect will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If Architect determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Architect will so inform Contractor, who shall make changes as directed and resubmit.
10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 00 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files using format same as file preparation format and Portable Data File (PDF) format.
3. BIM File Incorporation: Develop and incorporate coordination drawing files into Building Information Model established for Project.
a. Perform three-dimensional component conflict analysis as part of preparation of coordination drawings. Resolve component conflicts prior to submittal. Indicate where conflict resolution requires modification of design requirements by Architect.
4. Architect will furnish Contractor one set of digital data files of Drawings for use in preparing coordination digital data files.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 5
a. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.
b. Contractor shall execute a data licensing agreement in the form of an agreement form acceptable to Architect.
c. Refer to Section 00 73 00 “Supplementary Conditions” for additional information on digital data files.
1.6 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in a form acceptable to the Architect.
1. Architect will return RFIs submitted to Architect by other entities controlled by Contractor with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of Architect.
6. RFI…
This is the start of the file's text. The full file is on GovTribe.