Appendix C_Submittal No. 105.1 Coordination Study.pdf

PDF 1 MB Posted

Attached to
Arc Flash Study of All Off-Site Facilities
Solicitation number
UD-26-348
Issued by
Los Angeles County, California

About this file

This submittal transmittal and electrical system study report document concerns the S-8 Sewer Lift Station Rehabilitation Project for Long Beach, California Utilities Department. Lucas Builders, Inc. submitted a coordination study document on March 25, 2026, to project manager Hamed Soltani at Accenture, with the submittal numbered 105.1 and city project number UT-3899. The coordination study was submitted for review and comment via email attachment. Pioneer Power Group performed a comprehensive electrical system study including short circuit analysis, protective device coordination study, and arc flash analysis for new electrical equipment associated with the project. The study analyzed three primary buses: ECB MAIN, MCC (Motor Control Center), and MTS, all operating at 480 volts. The contractor certified that the material and equipment contained in the submittal meets all specified requirements with no exceptions. The arc flash study results are valid through March 25, 2031, pending no major system changes.

The electrical system study determined that all equipment passed device evaluation analysis with adequate coordination and circuit protection achieved across analyzed branches. All incident energy levels were found to be 34.5 calories/cm² or less, meeting NFPA 70E and NEC standards. The maximum fault currents calculated were 9.17 kA at ECB MAIN, 8.10 kA at MCC, and 9.60 kA at MTS, all within respective equipment withstand ratings of 65 kA, 65 kA, and 10 kA. The study included recommended protective device settings detailed in Appendix D for three low-voltage breakers and one motor control product. The report recommends implementing the specified protective device settings, affixing arc flash labels on new electrical equipment, providing arc flash training to qualified personnel, and procuring appropriate personal protective equipment. Per NFPA 70E standards, the arc flash study must be updated either every five years or upon any major system changes such as utility service modifications or equipment additions. Pioneer Power Group contact information for future renewal studies is provided as 301-569-7931 or sales@pioneerpwr.com.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lucas Builders, Inc SUBMITTAL TRANSMITTAL

510 E. Jamie Ave

La Habra CA 90631 Date:

310-853-0690 LBI Job No.:

Submittal No.:

City Project No.:

We are sending you x Attached via email only o Under separate cover via x Submittals for review and comment o Product data for information only

Submittal Description:

Remarks:

Copies

Specifications

Section No. Description -- Supplier

Review

Action a

1 26 24 19 a Note: NET = No exceptions taken; MCN = Make corrections noted; A&R = Amend and Resubmit; R = Rejected Attach additional sheets if necessary.

Contractor

Certify either A or B:

x A. We have verified that the material or equipment contained in this submittal meets all the requirements, including coordination with all related work, specified (no exceptions).

o B. We have verified that the material or equipment contained in this submittal meets all requirements specified except for the attached deviations.

Contractor's Authorized Signature

Accenture

UT-3899

Coordination Study

3/25/2026

HC-168

105.1

To:

Hamed Soltani

Project:

S-8 Sewer Lift Station

Rehabilitation Project Senior Project Manager

1 3/25/26 Coordination Study

Item Date Reviewer Initials Review Comments Attached

No. Deviation

8500 Brooktree Drive, Suite 110 Wexford PA 15090 • TELEPHONE: (724) 799-8385 x116

March 25, 2026

Subject: Electrical System Study Report for 200 Maryland Avenue NE, Washington, DC 20002.

Pioneer Power Group (PPG) is pleased to furnish an electronic copy of the subject report discussing the results of the short circuit, coordination, and arc flash analysis performed for the new electrical equipment for the Long BCH Util Dept S8 Sewer LS project.

Based on the electrical system studies performed, it was determined that:

1. All equipment has passed the device evaluation analysis.

2. Adequate coordination and circuit protection is achieved in the branches analyzed in the study.

3. All incident energy levels were found to be 34.5 calories/cm2 or less.

4. The engineer of record should review the overcurrent protection and implement any changes they see fit. See Section 4.02 for further details, and possible suggestions to improve coordination.

5. The NFPA 70E Standard requires arc-flash studies to be updated either (i) every five years or

(ii) at the time any major system changes take place [i.e., the utility service changes, a renovation is done, large motors are added to the distribution system, etc.] In the event that your study needs to be updated, Pioneer Power Group may be reached at 301-569-7931 or sales@pioneerpwr.com.

Recommendations by PPG are shown in Section 6.02. If you have any questions or require further information, please don't hesitate to contact us.

Sincerely, Dulcie Summers

Electrical Engineer

Enclosures: As stated mailto:sales@pioneerpwr.com

Electrical System Study Report

Long BCH Util Dept S8 Sewer LS

March 25, 2026

Arc Flash Results Valid Through March 25, 2031 Pending No Major System

Changes (see Appendix A)

Project S-9201

Rev.1

Revision Table

Revision # Date Description

0 February 27, 2026 Original Issue

1 March 25, 2026

Customer Comment:

1) Please revise the unknown short circuit rating on the

MTS based on a statement inside of the cover of the MTS per manufacturer.

PPG Response:

1) Revised short circuit current rating to 10kA based on statement.

Long BCH Util Dept S8 Sewer LS

March 25, 2026 TOC-1 Pioneer Power Group

TABLE OF CONTENTS

Page Nos.

EXECUTIVE SUMMARY ..................................................................................... ES-1

SECTION 1 - INTRODUCTION

1.01 Objectives and Scope ............................................................................ 1-1

SECTION 2 – SYSTEM MODELING

2.01 Overview of System Model ................................................................... 2-1

2.02 Study Scenarios .................................................................................... 2-3

SECTION 3 – SHORT CIRCUIT STUDY

3.01 Overview of Short Circuit Study ........................................................... 3-1

3.02 Results of Short Circuit Study ............................................................... 3-1

3.03 Equipment Evaluation ........................................................................... 3-1

SECTION 4- COORDINATION STUDY

4.01 Overview of Coordination Study ........................................................... 4-1

4.02 Results of Coordination Study ............................................................... 4-1

SECTION 5 – ARC FLASH ANALYSIS

5.01 Overview of Arc Flash Analysis ............................................................ 5-1

5.02 Arc Flash Analysis Results .................................................................... 5-1

5.03 Arc Flash Labels .................................................................................. 5-3

SECTION 6 – CONCLUSIONS AND RECOMMENDATIONS

6.01 Conclusions .......................................................................................... 6-1

6.02 Recommendations ................................................................................. 6-2

APPENDIX A – 5 Year Expiration and Renewal of your Study

APPENDIX B – One Line Diagram and Input Data Report

APPENDIX C – Utility Data Sheet

APPENDIX D – Protective Device Settings Table

March 25, 2026 ES-1 Pioneer Power Group

EXECUTIVE SUMMARY

Objectives and Scope

Pioneer Power Group (PPG) has performed an electrical system study for the new electrical equipment for the Long BCH Util Dept S8 Sewer LS project. This report presents the short circuit, coordination, and arc flash study results for the associated electrical facilities. The following tasks were undertaken to reach the conclusions and recommendations given in this report:

• System Modeling

• Short Circuit Study

• Coordination Study

• Arc Flash Analysis

The responsibility for making changes in the operations, procedures, or for implementing any recommendations in this report is the customer's responsibility.

System Modeling

The electrical distribution system was modeled to best simulate the electrical facilities associated with the Long BCH Util Dept S8 Sewer LS project. Multiple system operating scenarios were simulated to ascertain the worst-case condition with regard to the arc flash analysis. All studies were performed on the basis of the worst-case scenario.

Short Circuit Study

A short circuit study was performed to calculate the available fault current values of the new electrical equipment at the facilities. The results of the short circuit study are used to confirm the withstand ratings of electrical equipment and the interrupting rating of protective devices. The short circuit study results are also subsequently used to perform the coordination study and arc flash analysis. The short circuit study was performed in accordance with IEEE Standard 141-

1993.

March 25, 2026 ES-2 Pioneer Power Group

Protective Device Coordination Study

A protective device coordination study was performed to ascertain the settings of the protective devices for the new electrical equipment at the facilities. A coordination study yields increased equipment protection by ensuring proper device coordination by setting protective devices to trip in sequence, thus increasing continuity of service and limiting the effects of nuisance tripping and disturbances to smaller areas within the distribution system. The coordination study results are also subsequently required for the arc flash analysis. The protective device coordination studies were performed in accordance with IEEE Standard 242-2001.

Arc Flash Analysis

An arc flash analysis was performed to determine the incident energy, arc flash boundary, arc flash

PPE class, and appropriate Personal Protective Equipment (PPE) required for performing operation and maintenance of the new electrical equipment at the facilities. An arc flash analysis is required to comply with the arc flash labeling requirements of the applicable NFPA 70E and

NEC standards. The arc flash hazard analysis was performed in accordance with IEEE Standard

1584-2018.

The information produced herein, including equipment labels, is based upon an arc flash study supplied by customer personnel and/or the conditions and practices observed at the time of the site visit. Changes in equipment settings or electrical distribution system configuration made after the date set forth in this report will invalidate the calculated Arc Flash Incident Energy values and may require more personal protective equipment (PPE).

March 25, 2026 1-1 Pioneer Power Group

SECTION 1

INTRODUCTION

1.01 Objectives and Scope

Pioneer Power Group (PPG) was retained to analyze and perform an electrical system study for the new electrical equipment for the Long BCH Util Dept S8 Sewer LS project. Towards this end, PPG performed an electrical system study to ensure proper functionality with the consideration of system modeling, short circuit, protective device coordination, and arc flash analysis.

The following tasks were undertaken to reach the conclusions and recommendations provided in this report:

• System Modeling

• Short Circuit Study

• Coordination Study

• Arc Flash Analysis

Under system modeling, the electrical one-line diagram was developed to represent the new and existing electrical equipment associated with this project. The short circuit study was performed to determine the available fault currents throughout the distribution system and verify the adequacy of equipment withstand ratings. The coordination study was performed to ensure the settings of the protective devices provided satisfactory protection and coordination within the electrical distribution system. The arc flash analysis was performed to ascertain incident energy levels, arc flash PPE categories, and appropriate Personal Protective Equipment. Conclusions and recommendations are based on the results from the electrical system studies performed.

March 25, 2026 2-1 Pioneer Power Group

SECTION 2

SYSTEM MODELING

2.01 Overview of System Model

The electrical distribution system for the facilities was modeled and simulated using SKM Power

Tools software. The system model was prepared in accordance with the Contract Drawings, electrical equipment shop drawings, transformer ratings, cable sizes, cable lengths, protective device information, and other distribution equipment based on information obtained by the customer.

For the study purposes, the following assumptions were considered:

• All system voltages were modeled at nominal levels.

• The utility source was modeled as an infinite bus to yield maximum three-phase and single-line-to-ground fault currents at 480V.

• Transformer “XFMR UTILITY” size was assumed to be rated 112.5 KVA based on 200A downstream OCPD.

• Transformer impedance was modeled as 1.5% for most conservative results based on assumed rating.

• CBL-0001, CBL-0002 and CBL-0003 were modeled to be non-magnetic duct material and

THWN insulation.

• CBL-0001 was modeled to be 10 feet in length.

• To ensure conservative arc-flash results – VCBB was chosen as the default bus configuration for all equipment except for any MCC locations. HCB was chosen as the bus configuration for any MCC locations.

• VCB results were also calculated and compared against any VCBB equipment and the worst-case result was reported. Similarly, VCB and VCBB results were calculated and compared against any HCB equipment and the worst-case result was reported.

March 25, 2026 2-2 Pioneer Power Group

Appendix B contains the one-line diagram and input data report for the system model. Appendix

C contains the utility information correspondence.

March 25, 2026 2-3 Pioneer Power Group

2.02 Study Scenarios

For this project, one (1) short circuit scenario was simulated to analyze the electrical distribution system operation. The scenario considered the calculated Infinite Bus symmetrical fault current from the source.

Two (2) arc-flash scenarios were simulated to ensure worst-case results as follows:

Scenario 1: Infinite bus at Utility Transformer Primary

Scenario 2: 50% of Maximum Secondary Utility Let-Through Fault Current

The worst-case results have been reported, compiling all scenarios.

March 25, 2026 3-1 Pioneer Power Group

SECTION 3

SHORT CIRCUIT STUDY

3.01 Overview of Short Circuit Study

A short circuit study was performed for the proposed distribution system to determine the available fault currents at pertinent locations throughout the distribution system. The short circuit study calculates and yields the results from the balanced and unbalanced fault currents at all buses. The results from the short circuit study are used to confirm the interrupting rating of the protective devices and withstand rating of the electrical equipment. The results obtained from the short circuit study are also used in the coordination study and arc flash analysis. The short circuit study was performed in accordance with IEEE standard 141-1993.

3.02 Results of Short Circuit Study

The short circuit study results are depicted in Table 3-1. The results from the short circuit study are depicted at each bus: the three-phase fault currents together with the 3-cycle, 5-cycle, and 8-cycle asymmetrical three-phase fault currents and the single-phase ground fault currents. The short circuit study results incorporate the X/R ratio factor adjustment of equipment.

3.03 Equipment Evaluation

The calculated results from the short circuit study were used to confirm the interrupting / withstand ratings of electrical equipment and protective devices. Table 3-2 depicts the results of the electrical equipment with respect to the calculated worst-case fault current. The equipment evaluation results incorporate the X/R ratio factor adjustment for the short circuit currents.

DAPPER Unbalanced Fault Report

Table 3-1: Comprehensive Short Circuit Study Settings (Scenario 1)

Three Phase Fault

Single Line to Ground

Line to Line Fault

Line to Line to Ground

All BusesFaulted Bus

Yes

Yes

Yes

No

No

Motor Contribution

Transformer Tap

Xformer Phase Shift

Yes

Yes

Bus Voltages

Branch Currents

Phase or Sequence

Fault Current Calculation

Asym Fault Current at Time 0.50

First Bus From Fault

First Branch From Fault

Report phase quantities

Asymmetrical RMS (with DC offset and Decay)

Cycles

Fault Location

Bus Name

Bus

Voltage

3-Phase

Amps

3P

X/R

SLG

Amps

SLG

MVA

SLG

X/R

Mom

Amps 3 Cycles 5 Cycles 8 Cycles

3-Phase

MVA

---------3P Asym Amps--------

ECB MAIN. 480 9,165 3.20 8,9827.62 10,374 9,165 9,165 9,1652.49 3.16

MCC 480 8,096 2.31 7,5686.73 8,614 8,096 8,096 8,0962.10 2.23

MTS 480 8,568 2.63 8,1757.12 9,323 8,568 8,568 8,5682.27 2.55

March 25, 2026 4-1 Pioneer Power Group

Table 3-2: Equipment evaluation of Long BCH Util Dept S8 Sewer LS

Bus Name

Max Fault

Current (kA)

Equipment

Withstand Rating (kA)

Result

ECB MAIN. 9.17 65.00 Pass

MCC 8.10 65.00 Pass

MTS *9.60 (*N1) 10.00 Pass

(*N1) System X/R higher than Test X/R, Calc INT kA modified based on low voltage factor.

March 25, 2026 4-2 Pioneer Power Group

SECTION 4

COORDINATION STUDY

4.01 Overview of Coordination Study

A protective device coordination study is used to ascertain the recommended settings of protective devices within a distribution system. Settings and ampacities are determined by plotting time-current curves (TCC) of the given protective devices. A coordination study will yield increased equipment protection by ensuring proper device coordination by setting protective devices to trip in sequence. This will increase facility reliability and limit the effects of nuisance tripping and disturbances to smaller areas within the distribution system. The coordination study was performed in accordance with the IEEE Standard 242-2001.

4.02 Results of Coordination Study

The settings of the protective devices were ascertained for a condition that allows the facilities to operate successfully. A coordination study was performed and TCCs were plotted to establish protective settings. Figure 4-01 depicts the time-current curves for the studied electrical distribution system. Based on the analysis performed, best possible protective device coordination is achieved. Based on the coordination study for the furnished electrical equipment, the settings for the protective devices can be found in Appendix D.

March 25, 2026 4-3 Pioneer Power Group

The results of the protective device coordination study analysis are as follows:

• Figure 4-01 UTILITY to MCC o Satisfactory protective device coordination and equipment protection is achieved.

TX Inrush

0.5 1 10 1

K

K

K

M

0.01

0.10

CURRENT IN AMPERES

T I M E

I N

S E C O N D S

ECB MAIN

EATON

PD-2, PDG2_M

PDG2_M

Trip 200.0 A

Plug 200.0 A Settings Phase 480V

MCC_M

ALLEN-BRADLEY

140G, K-Frame 140G-K

Trip 400.0 A Plug 400.0 A Settings Phase

LTPU (I1) 0.5 (200A)

LTD ( t1) 6 (I^s T On)

STPU (I2) 2.4 (960A)

STD ( t2) 0.05 (I^s T On)

INST (I3) 8 (3200A)

INST OR Fixed (5000A)

MCC_PUMP

ALLEN-BRADLEY

140MG, G-Frame

140MG-G

Trip 30.0 A Plug 30.0 A Settings Phase

INST (90-330A) A (90A)

MCC_LGST

ALLEN-BRADLEY

140G, G-Frame 140G-G6 Trip 60.0 A

Plug 60.0 A Settings Phase Thermal Curve (H+C) INST Fixed (600A)

CBL-0001

Size: 3/0 AWG

Qty/Ph: 3

CBL-0002

Size: 3/0 AWG Qty/Ph: 3

CBL-0003

Size: 3/0 AWG Qty/Ph: 3

ECB MAIN

EATON

PD-2, PDG2_M

PDG2_M

Trip 200.0 A

Plug 200.0 A Settings Phase 480V

MCC_M

ALLEN-BRADLEY

140G, K-Frame 140G-K

Trip 400.0 A Plug 400.0 A Settings Phase

LTPU (I1) 0.5 (200A)

LTD ( t1) 6 (I^s T On)

STPU (I2) 2.4 (960A)

STD ( t2) 0.05 (I^s T On)

INST (I3) 8 (3200A)

INST OR Fixed (5000A)

MCC_PUMP

ALLEN-BRADLEY

140MG, G-Frame

140MG-G

Trip 30.0 A Plug 30.0 A Settings Phase

INST (90-330A) A (90A)

MCC_LGST

ALLEN-BRADLEY

140G, G-Frame 140G-G6 Trip 60.0 A

Plug 60.0 A Settings Phase Thermal Curve (H+C) INST Fixed (600A)

CBL-0001

Size: 3/0 AWG

Qty/Ph: 3

CBL-0002

Size: 3/0 AWG Qty/Ph: 3

CBL-0003

Size: 3/0 AWG Qty/Ph: 3

UTILITY

S

P

XFMR UTILITY

ECB MAIN.

ECB MAIN

EN

MTS.

CBL-0001

MTS

CBL-0002

MCC_M

CBL-0003

MCC

MCC_PUMP

MTR SUM

MCC_LGST

4-01_UTILITY to MCC Reference Voltage: 480V, Current x 1

March 25, 2026 5-1 Pioneer Power Group

SECTION 5

ARC FLASH ANALYSIS

5.01 Overview of Arc Flash Analysis

An arc flash analysis was performed to determine the incident energy, arc flash boundary, arc flash

PPE class, and appropriate Personal Protective Equipment (PPE) required for performing operation and maintenance of the electrical equipment associated with the new facilities. The arc flash analysis is performed on the basis of the results obtained from the short circuit and coordination studies. The arc flash analysis includes the determination of the incident energies at assigned working distances throughout the electrical system and the determination of the arc flash protection boundaries. An arc flash analysis is required for the labeling requirements of NFPA

70E and NEC. The arc flash hazard analysis was performed in accordance with IEEE Standard

1584-2018.

The information produced herein, including equipment labels, is based upon an arc flash study supplied by customer personnel and/or the conditions and practices observed at the time of the site visit. Changes in equipment settings or electrical distribution system configuration made after the date set forth in this report will invalidate the calculated Arc Flash Incident Energy values and may require more personal protective equipment (PPE).

5.02 Arc Flash Analysis Results

The arc flash analysis was performed using IEEE 1584 Standard as described above. Table 5-1 depicts the arc faults, incident energies, arc flash boundaries, and the associated arc flash PPE categories for the electrical equipment.

March 25, 2026 5-2 Pioneer Power Group

Table 5-1: Arc Flash Analysis Results Summary (Worst Case)

Bus Name Protective

Device Name

Bus kV

Bus Bolted Fault (kA)

Prot Dev Bolted Fault (kA)

Prot Dev Arcing Fault (kA)

Trip/ Delay Time (sec.)

Breaker Opening Time/Tol

(sec.)

Equip Type

Electrode Config Box Height

(in.)

Box Width

(in.)

Box Depth

(in.)

Gap

(mm)

Arc Flash

Boundary (in)

Working Distance

(in)

Incident Energy

(cal/cm2)

ECB MAIN MaxTripTime @2.0s 0.48 9.17 8.84 7.07 2 0.0000 PNL VCBB 30 22 6.1 25 126 18 34.5

MCC (MCC_M LineSide) ECB MAIN 0.48 4.51 4.19 2.99 2 0.0000 MCC HCB 90 20 20 25 81 18 25.3

MTS ECB MAIN 0.48 4.63 4.31 2.96 2 0.0000 PNL VCBB 60.5 18.6 8.6 25 66 18 12.2

March 25, 2026 5-3 Pioneer Power Group

5.03 Arc Flash Labels

Figure 5-1 below depicts the excerpt of a sample arc flash label template, which is in accordance with the requirements NFPA 70E, ANSI Z535.4, and OSHA. Actual Arc Flash labels will be similar but specific to the facility. The arc flash label will be a high-endurance weather-proof 4" x

6" label printed on a Brady thermal transfer printer. Arc flash labels are prepared on the basis of the composite worst-case scenario, as described above. Arc flash labels for the studied equipment will be provided as part of this project, upon approval of this report.

Figure 5-1: Sample Arc Flash Label Excerpt

March 25, 2026 6-1 Pioneer Power Group

SECTION 6

CONCLUSIONS AND RECOMMENDATIONS

6.01 Conclusions

Based on the electrical system studies performed, it was determined that:

1. All equipment has passed the device evaluation analysis.

2. Adequate coordination and circuit protection is achieved in the branches analyzed in the study.

3. All incident energy levels were found to be 34.5 calories/cm2 or less.

4. The engineer of record should review the overcurrent protection and implement any changes they see fit. See Section 4.02 for further details, and possible suggestions to improve coordination.

5. The NFPA 70E Standard requires arc-flash studies to be updated either (i) every five years or (ii) at the time any major system changes take place [i.e., the utility service changes, a renovation is done, large motors are added to the distribution system, etc.] In the event that mailto:sales@pioneerpwr.com

March 25, 2026 6-2 Pioneer Power Group

6.02 Recommendations

Based on the electrical system studies performed, PPG recommends:

1. Affix arc flash labels on new electrical equipment to meet the requirements of NEC 110.16 and NFPA 70E. Arc flash labels for the studied equipment will be provided as part of this project.

2. Provide arc flash training to qualified personnel responsible for performing operation, maintenance, and work on electrical equipment. Procure appropriate personal protective equipment (PPE) for qualified personnel.

3. Implement protective device settings for new equipment as shown in Appendix D.

Appendix D depicts the recommended protective device settings table for the studies performed in accordance with the furnished electrical equipment and the specified electrical distribution system. A revised protective device settings table and revised study results will need to be ascertained as part of a separate study in the event that the electrical distribution system or furnished electrical equipment is changed.

4. The NFPA 70E Standard requires arc-flash studies to be updated either (i) every five years or (ii) at the time any major system changes take place [i.e., the utility service changes, a renovation is done, large motors are added to the distribution system, etc.] In the event that

March 25, 2026 Pioneer Power Group

Appendix A

5 Year Expiration and

Renewal of your Study

NOTICE: 5 Year Expiration and Renewal of your Study

To ensure safety and accuracy for personnel working on electrical systems, NFPA 70E electrical standards recommended to renew an arc flash study every 5 years due to changes in equipment, electrical systems, updates in industry standards and regulations. Keeping the study up-to-date helps maintain compliance and reduces the risk of injury or damage.

Pioneer Power Group believes an Arc Flash Study should be periodically updated for the following reasons:

1. Protect workers: An up-to-date arc flash study provides information to help protect workers from hazardous electrical arc flash incidents.

2. Updating safety standards: Electrical safety standards and codes change over time, and a current arc flash study can ensure that your facility is in compliance with the latest requirements.

3. Changes in equipment or systems: Over time, changes to electrical equipment or systems can greatly affect the results of an arc flash study.

4. Improved accuracy: Technology and calculation methods improve over time, leading to more accurate and up-to-date results from an arc flash study.

If you are interested in learning more about your renewal study for this facility, contact Pioneer

Power Group at 301-569-7931 or email: renewal@pioneerpwr.com. Please include the report number/facility name located on the report cover page of the report (look for an “S-XXX” number).

The report number can also be found on the corresponding arc flash label. We make the renewal of your study simple and easy for our clients.

Pioneer Power Group

301-569-7931 mailto:renewal@pioneerpwr.com

Appendix B

One Line Diagram and

Input Data Report

UTILITY

12000.0 V

SC 3P 1000000 MVA

SC SLG 333333.3 MVA

S

P

XFMR UTILITY

112.5 kVA

12000 / 480V

1.50% Z

ECB MAIN.

Eaton

480V

ECB MAIN

EATON

PD-2, PDG2_M

200 A , 200 A

EN

MTS.

CBL-0001

1 - #3/0 AWG, 10 ft

MTS

480V

CBL-0002

1 - #3/0 AWG, 35 ft

MCC_M

ALLEN-BRADLEY

140G, K-Frame

400 A , 400 A

LPTU 0.5 (200A)

CBL-0003

1 - #3/0 AWG, 30 ft

MCC

Rockwell Automation

480V

MCC_PUMP

ALLEN-BRADLEY

140MG, G-Frame

30 A , 30 A

MTR SUM

41.5 hp

MCC_LGST

ALLEN-BRADLEY

140G, G-Frame

60 A , 60 A

Short Circuit Input Report

Feb 27, 2026 22:00:05 Page 1

ALL INFORMATION PRESENTED IS FOR REVIEW, APPROVAL

INTERPRETATION AND APPLICATION BY A REGISTERED ENGINEER ONLY

SKM DISCLAIMS ANY RESPONSIBILITY AND LIABILITY RESULTING

FROM THE USE AND INTERPRETATION OF THIS SOFTWARE.

SKM POWER*TOOLS FOR WINDOWS

INPUT DATA REPORT

COPYRIGHT SKM SYSTEMS ANALYSIS, INC. 1995-2023

ALL PU VALUES ARE EXPRESSED ON A 100 MVA BASE.

Feb 27, 2026 22:00:05 Page 2

FEEDER INPUT DATA

CABLE FEEDER FROM FEEDER TO QTY VOLTS LENGTH FEEDER

NAME NAME NAME /PH L-L SIZE TYPE

CBL-0001 XFMR UTILITY S ECB MAIN. 1 480 10.0 FEET 3/0 Copper

Duct Material: Non-Magnetic Insulation Type: PVC Insulation Class: THWN

+/- Impedance: 0.0766 + J 0.0415 Ohms/1000 ft 0.3325 + J 0.1801 PU

Z0 Impedance: 0.1217 + J 0.1055 Ohms/1000 ft 0.5282 + J 0.4579 PU

CBL-0002 ECB MAIN. UTILITY (N) 1 480 35.0 FEET 3/0 Copper

Duct Material: Non-Magnetic Insulation Type: PVC Insulation Class: THWN

+/- Impedance: 0.0766 + J 0.0415 Ohms/1000 ft 1.16 + J 0.6304 PU

Z0 Impedance: 0.1217 + J 0.1055 Ohms/1000 ft 1.85 + J 1.60 PU

CBL-0003 MTS MCC 1 480 30.0 FEET 3/0 Copper

Duct Material: Non-Magnetic Insulation Type: PVC Insulation Class: THWN

+/- Impedance: 0.0766 + J 0.0415 Ohms/1000 ft 0.9974 + J 0.5404 PU

Z0 Impedance: 0.1217 + J 0.1055 Ohms/1000 ft 1.58 + J 1.37 PU

Feb 27, 2026 22:00:05 Page 3

TRANSFORMER INPUT DATA

TRANSFORMER PRIMARY RECORD VOLTS * SECONDARY RECORD VOLTS FULL-LOAD NOMINAL

NAME NO NAME L-L NO NAME L-L KVA KVA

XFMR UTILITY XFMR UTILITY P YG 12000.0 XFMR UTILITY S YG 480.00 112.50 112.50

Pos. Seq. Z%: 0.423 + J 1.44 (Zpu 3.77 + j 12.79 ) Shell Type

Zero Seq. Z%: 0.423 + J 1.44 ( Pri - Sec: 3.77 + j 12.79 )

Taps Pri. 0.000 % Sec. 0.000 % Phase Shift (Pri. Leading Sec.): 0.000 Deg.

Feb 27, 2026 22:00:05 Page 4

GENERATION CONTRIBUTION DATA

BUS CONTRIBUTION VOLTAGE

NAME NAME L-L MVA X"d X/R

XFMR UTILITY P UTILITY 12000.0 999999.

Three Phase Contribution: 999999. MVA 9999.00

Single Line to Ground Contribution: 333333. MVA 9999.00

Pos Sequence Impedance (100 MVA Base) 0.00000 + J 0.00010 PU

Zero Sequence Impedance (100 MVA Base) 0.00000 + J 0.00010 PU

Feb 27, 2026 22:00:05 Page 5

MOTOR CONTRIBUTION DATA

BUS CONTRIBUTION VOLTAGE BASE Motor

NAME NAME L-L kVA X"d X/R Number

MCC MTR SUM 480 41.61 0.1507 4.90 1.00

Pos Sequence Impedance (100 MVA Base) 73.94 + j 362.25 PU

Appendix C

Utility Data Sheet

Fault information provided for the study is shown below:

• An infinite bus is assumed at the primary windings of XFMR UTILITY.

Please Note: Study will be revised and updated once actual utility fault current data is available.

Appendix D

Protective Device

Settings Tables

LV Breakers

Name/Type Description Frame/Sensor/Plug Settings:

ECB MAIN EATON 200A 480V

Thermal Magnetic PD-2, PDG2_M 200A

200A

MCC_LGST ALLEN-BRADLEY 100A Thermal Curve (H+C)

Thermal Magnetic 140G, G-Frame 60A INST Fixed (600A)

60A

MCC_M ALLEN-BRADLEY 400A LTPU (I1) 0.5 (200A)

Static Trip 140G, K-Frame 400A LTD ( t1) 6 (I^s T On)

400A STPU (I2) 2.4 (960A)

STD ( t2) 0.05 (I^s T On)

INST (I3) 8 (3200A)

INST OR Fixed (5000A)

MCP

Name/Type Description Frame/Trip Settings:

MCC_PUMP ALLEN-BRADLEY 30A INST (90-330A) A (90A)

140MG, G-Frame 30A

EXECUTIVE SUMMARY
SECTION 1 INTRODUCTION
1.01 Objectives and Scope
SECTION 2 SYSTEM MODELING
2.01 Overview of System Model
2.02 Study Scenarios
SECTION 3 SHORT CIRCUIT STUDY
3.01 Overview of Short Circuit Study
3.02 Results of Short Circuit Study
3.03 Equipment Evaluation
SECTION 4 COORDINATION STUDY
4.01 Overview of Coordination Study
4.02 Results of Coordination Study
SECTION 5 ARC FLASH ANALYSIS
5.01 Overview of Arc Flash Analysis
5.02 Arc Flash Analysis Results
5.03 Arc Flash Labels
SECTION 6 CONCLUSIONS AND RECOMMENDATIONS
6.01 Conclusions
6.02 Recommendations
Appendix A 5 Year Expiration and Renewal of your Study
Appendix B One Line Diagram and Input Data Report
Appendix C Utility Data Sheet
Appendix D Protective Device Settings Tables

File details come from the government source that posted it. Updated .