APPENDIX B4-Historic-Info-2016-Final-Dredge-Prism.pdf

PDF 6 MB Posted

Attached to
MAINTENANCE DREDGING AT USCG SECTOR COLUMBIA RIVER [FORMERLY MARINE SECURITY UNIT (MSU)] PORTLAND, OR
Solicitation number
70Z08825B0000088
Issued by

About this file

This file is a detailed dredging project documentation for the US Coast Guard's Marine Safety Unit (MSU) Swan Island location in Portland, Oregon. The project involved maintenance dredging of up to 1,000 cubic yards at the Swan Island Lagoon, with a final project depth of -11.65 feet Columbia River Datum (CRD), allowing one foot of over-depth to -12.65 feet. The work was completed between July 1 and October 31, 2016, using hydrographic surveying techniques, multi-beam sonar systems, and specialized dredging software (WinOPS) to precisely track and document the dredging process.

The documentation includes comprehensive technical details such as pre-dredging and post-dredging bathymetric surveys, precise coordinate mapping, debris removal, and sand cover placement. The project team from Marine Industrial Construction, LLC documented the entire process, including transect lines, bucket print locations, and slope characteristics. Key technical specifications included using an R2Sonic 2022 Multi-beam Sonar System, collecting data in accordance with US Army Corps of Engineers standards, and ensuring all dredged materials were loaded into a scow and disposed of at an upland site. The total dredging volume was estimated at 450 cubic yards, with a sand cap of 94 cubic yards.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scale: Noted on Maps

Drawn By: JAB

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Cover Sheet & Index

Sheet Number: 1 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Sheet Number 1: Cover Sheet & Index Sheet Number 2: Tide and Ground Control Sheet Number 3: Bid Engineering Sheet Number 4: Spud Configuration Sheet Number 5: Project Area and Dredging Prism Sheet Number 6: Revised Dredging Prism and Design Sheet Number 7: Pre Dredging Prism Transects & Volumes Sheet Number 8: Post Dredge Prism with Debris Sheet Number 9: Post Sand Cover Prism Transects and Volumes Sheet Number 10: Final Dredge Prism with Annotated Details Sheet Number 11: Final Transects Sheet Number 12: Dredging Software (WinOPS) Bucket Prints Over Time During Dredging

SHEET INDEX

Coordinates are Oregon State Plane North, International Feet, NAD 1983, Columbia River Data Vertical Control

PROJECT NOTES

This work includes maintenance dredging of up to 1,000 cubic yards (CY) at the U.S.

Coast Guard (USCG), Marine Safety Unit (MSU) Portland. The final project depth shall is -11.65 ft. Columbia River Datum (CRD).

One foot of over depth is authorized to -

12.65 ft. All dredged shall be loaded into a scow and disposed of at an upland site. All work was completed during the approved in-water work window of July 01, to October 31.

PROJECT DESCRIPTION Project LocationVICINITY MAP

MIC TEAM MEMBER

Michael Eakin, Lead Estimator Joe Bernert, Quality Control Reviewed by D. J. Bernert, PE

PROJECT TEAM

2016 USCG MSU SWAN ISLAND DREDGING

Engineering & Project Design/Deployment

Marine Industrial Construction, LLC Final Dredging Prism and Related Data/Information

USCG CONTACTS/LEADS

Keith Ruch, USCG Contracting Officer Representative (COR), Oakland Engineering Dave Stalters, Project Manager Chief, Environmental Management Branch Civil Engineering Unit Oakland, CA 94612

MKCS Jon Franco, MSU Point of Contact Marine Safety Unit Portland 6767 N. Basin Ave.

Portland, OR 97217-3992

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Tide Control and Ground Control

Sheet Number: 2 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

\ NGS Control Verified

NOAA - Survey Control Points 0 900 1,800450

Feet

RD3092NAD83(1991) 45 34 07.25164(N)122 43 25.65639(W)
NAVD88 ORTHO HEIGHT - 37 feet
STATE PLANES 701,265.86 7,632,677.31
RD3083NAD 83(1991) 45 34 05.28313(N) 122 43 13.91922(W)
NAVD88 ORTHO HEIGHT – 37 feet
STATE PLANES 701,043.60 7,633,506.45

RD3048 NAD 83(1991) 45 33 52.15428(N) 122 42 31.86137(W)

NAVD88 ORHO HEIGHT 37 feet
STATE PLANES 699,632.39 7,636,460.85

Tide Control Ground Control

Ground Control

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Bid Engineering

Sheet Number: 3 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Project permit conditions are outlined in detail in the following project specifications:

1. CERCLA Notification of Work, NWP-2013-172, U.S. Coast Guard, Swan Island Lagoon, Multnomah County, Oregon.

2. National Marine Fisheries Services (3/31/2016) Biological

Opinion, Reference Number WCr-2016-4197.

3. Oregon Department of Environmental Quality 401 Water Quality

Certification (2013-00172).

4. US Army Corp of Engineers, Portland District, Compliance

Certification, NWP-2013-172.

Disposal to upland disposal site (as defined in the specification and submittals.

Work Window for the Project is July 1, 2016 to October 31, 2016.

Data presented in Oregon State Plane Coordinates, North, International Feet, NAD 1983, Columbia River Data Vertical Control

PROJECT NOTES

A’

A

A’ A

USCG MSU Portland: Bid Engineering

Rip Rap

Begin

End

Dredging Zone

Dredging Prism / Boomed Area

Docks

Rip Rap Boundary

Bathymetric Depth

Recent Aerial Imagery superimposed

0 10 25 50 100

FEET

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Spud Configuration for Dredging

Sheet Number: 4 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Project permit conditions are outlined in detail in the following project specifications:

1. CERCLA Notification of Work, NWP-2013-172, U.S. Coast Guard, Swan Island Lagoon, Multnomah County, Oregon.

2. National Marine Fisheries Services (3/31/2016) Biological

Opinion, Reference Number WCr-2016-4197.

3. Oregon Department of Environmental Quality 401 Water Quality

Certification (2013-00172).

4. US Army Corp of Engineers, Portland District, Compliance

Certification, NWP-2013-172.

Disposal to upland disposal site (as defined in the specification and submittals.

Work Window for the Project is July 1, 2016 to October 31, 2016.

Data presented in Oregon State Plane Coordinates, North, International Feet, NAD 1983, Columbia River Data Vertical Control

PROJECT NOTES

USCG MSU Portland

Spud

Sp u d

Swing on Spud

Swing on Spud

Dredge Swath

Spud Configuration for Dredging

100 foot length

36 foot width

Dock

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Project Area and Dredging Prism

Sheet Number: 5 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Project Area Dredging Prism

Approved By: JAB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Dredging Prism and Design

Sheet Number: 6 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Pre Dredging Prism Maps Design & Volumes

Detailed dredging prism engineering and maps were compiled from the contracted pre-dredging survey.

Specifications include:

• Minimum Dredging Depth -11.65 Columbia River Data (CRD)

• Maximum Dredging Depth -12.65 Columbia River Data (CRD)

Ground control to be determined on site. Marking on dock for additional site Quality Control during project implementation. Data is incorporated into the WinOPS dredging software for real-time evaluation.

Hydrographic Surveying completed by a third party contractor: James Glaeser (NW Hydro). James is an American Congress on Surveying and Mapping (ACSM) Certified Hydrographer (#222).

Survey completed on 10/4/2016.

Soundings were collected using a R2Sonic 2022 Multi-beam Sonar System operation at 400 kH. Data processing was completed using HyPack HyWeep Software. All bathymetric data was collected in accordance with the US Army Corp of Engineers Hydrographic Survey Manual EM-112-1003 (January 2002).

Base survey data (from Northwest Hydro Inc) is also provided to the USCG for Quality Control purposes.

PROJECT NOTES

Transect Lines presented on next Sheet See Sheet 8 for Transects

Approved By: JAB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Dredging Prism Transects

Sheet Number: 7 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Pre Dredging Prism Transects & Volumes

Dredging volumes were based on the pre-dredging surveying and the dredging prism. The dredging prism was refined to be larger since the slope of the shoreline (where rip rap is expected) is slightly north (shoreward) of the original proposed prism line (on average 7 feet). Correspondingly the northwest edge of the rip rap is expected to extend into the berth slightly more than the original prism (or rip rap may have falling off the armoring into the prism). Several other features were identified with shape angles indicating an anthropogenic feature, or rip rap in the prism (identified on the map).

Dredging is to the rip rap with a right to refusal (not to impact structural engineering).

The dredging volume of the primary prism to -12.65 feet CRD is 318 cubic yards with an average dredging depth of 3.3 feet. The prism edge on the shore-side is 71 feet in length and the average depth is 8 feet. Using a conservative factor of a 1:1 slope this is an additional 28 CY for a 348 cubic yards. The sloughing, given site conditions, is expected to more significant (1:3 or greater) and sediment on the riprap is expected to slough (rip rap area is 943 square feet). The total dredging volume is estimated at 450 cubic yards.

The surface area (planar) of the dredged area is 2545 square feet and the sand cap is expected to be 94 cubic yards of sand, or 132 tons.

PROJECT NOTESPrism

Prism

Prism

Rip Rap

Rip Rap

Rip Rap

1:1

1:1

1:1 Rip Rap

Expected Slough

Transect Lines locations presented on Previous Sheet See Sheet 7 for Locations

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Post Dredge Prism with Debris

Sheet Number: 8 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

A B

C D

Concrete Anchor

E F Empty Barrel

Post Dredge Prism with Debris Features which were not able to be removed with Environmental Bucket (Cable Arm) where identified using WinOPS dredging software, Trimble Geo 7 GPS and field maps.

Features were annotated (map to side) and used to navigate to and remove with standard ESCO digging clamshell bucket (See images below and locations on the map).

PROJECT NOTES

A pre-dredging surveys was completed on 10/4/16, a post dredging survey on 10/12/16, and a sand cover survey on 10/13/2016.

All bathymetric data was collected in accordance with the U.S Army Corp of Engineers Hydrographic Survey Manual EM-112-02-1003 (November 2013), Survey Classification: Navigation and Dredging Support Surveys, Bottom Classification of Soft.

HYDROGRAPHIC SURVEYS

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Post Sand Cover Prism & Transects

Sheet Number: 9 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Post Sand Cover Prism Transects and Volumes Measurements

Sand cover volumes were based on the dredging area covered and a 1 foot cover. The area was 1975 square feet was 73 cubic yards. Dredging software had 33 bucket prints marking area for sand cover placement with an average of

2.5 c.y per bucket for 82.5 cy of sand (visually conformed that 20 cy were remaining in barge after placement [and confirmed with displacement records]).

PROJECT NOTES

Pre Dredge

Post Dredge

Sand Cover

Pre Dredge

Post Dredge

Sand CoverRip Rap

Debris

Debris 1 Foot Sand Cover

1 Foot Sand Cover

A pre-dredging surveys was completed on 10/4/16, a post dredging survey on 10/12/16, and a sand cover survey on 10/13/2016.

All bathymetric data was collected in accordance with the U.S Army Corp of Engineers Hydrographic Survey Manual EM-112-02-1003 (November 2013), Survey Classification: Navigation and Dredging Support Surveys, Bottom Classification of Soft.

HYDROGRAPHIC SURVEYS

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Final Dredge Prism Annotated

Sheet Number: 10 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Final Dredge Prism with Annotated Details Prism Outline

Flat (<15)

Moderate Slopes (15-25)

Steep Slopes (25-40)

Extremely Steep (>40)

Main Dock

Slopes after Dredging with Slough Areas

CY Removed

0.25

0.5

Bucket Density / CY

Low

Moderate

High

Prism Outline

Main Dock

Bucket / CY Densities

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

Final Transects

Sheet Number: 11 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Final Dredge Prism with Transects

Outside Prism Sloughing Area

Final dredging prism transects compiled from surfaces generated from post sand cover placement. It is expected that minor sloughing will occur at the edges of the prism where large angles of repose are present.

PROJECT NOTES

Approved By: MMB

Date: 10/27/16

Marine Industrial Construction, LLC 10500 SW Wilsonville Rd

Wilsonville, OR, 97070

(503) 682-2525

Sheet Contents:

WinOPS Time Series

Sheet Number: 12 of 12 Project Number: 2016-109

HSCG88-16-C-PQQ197

US Coast Guard

MSU Swan Island

Dredging Project 2016

Dredging Software (WinOPS) Bucket Prints Over Time During Dredging 10/10/2016 16:32 to 19:32 - Cycle time: 2.02 Min10/10/2016 12:19 to 14:09 - Cycle time: 2.20 Min 10/10/2016 14:09 to 16:01 - Cycle time: 2.24 Min 10/10/2016 16:01 to 18:32 - Cycle time: 3.02 Min

10/11/2016 7:00 to 8:35 - Cycle time: 1.90 Min 10/11/2016 8:35 to 10:40 - Cycle time: 2.50 Min 10/11/2016 12:05 to 13:50 - Cycle time: 2.10 Min10/11/2016 10:40 to 12:05 - Cycle time: 1.70 Min

10/11/2016 13:50 to 15:17 - Cycle time: 1.74 Min 10/11/2016 15:17 to 16:55 - Cycle time: 1.96 Min 10/11/2016 16:55 to 19:33 - Cycle time: 3.16 Min 10/11/2016 19:33 to 20:19-Cycle time: 0.92 Probe

The dredge operator sees on the computer screen the locations of the bucket with the all edges of the bucket visible.

Bucket Marks are only logged when the operator finds depths below the target depth noted in the software (i.e. Design depth – current tide).

Operator GIS data include:

- Prism Outline

- Pre-Dredge

Hydrographic Survey

- Docks & Shoreline features

- Dredge outline and orientation (with crane and bucket / boom location)

- Annotated features including expected rip rap areas

WinOPS NOTES