The document is an Abstract of Offers - Construction form for a maintenance dredging project at the U.S. Coast Guard Station Cape Disappointment. The solicitation (No. 70Z08825B0000069) was issued on 3/19/2025, with bids opened on 4/21/25 at 1:00 PM PST by the Civil Engineering Unit Oakland. Two offerors (Bergerson and HME) submitted bids for the project, with total estimated amounts of $833,149.00 and $770,000.00 respectively.
The project scope includes mobilization and demobilization, dredging to a depth of -10.00 ft mean lower low water (with two feet of over-depth authorized), hydrographic surveys (pre and post-dredging), and pre and post-dredge reporting. Key line items include 1 job for mobilization/demobilization, 600 cubic yards of dredging and disposal, 2 hydrographic survey events, and 2 dredge reports. The document notes that the apparent low ranking is subject to the Contracting Officer's determination of responsibility.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
7A.
ITEM
NO.
7B. DESCRIPTION OF OFFERED ITEM 7C. EST.
QUANTITY
D.
UNIT
E. UNIT PRICE F. ESTIMATED
AMOUNT
D. UNIT PRICE D. UNIT PRICE
MOBILIZATION AND DEMOBILIZATION FOR
MAINTENANCE DREDGING AT THE U.S. COAST
GUARD (USCG), STATION CAPE
DISAPPOINTMENT
1 JB $596,147.00 $596,147.00 $312,000.00 $500,000.00
DREDGING AND DISPOSAL: Required Dredging depth is -10.00 ft mean lower low water (MLLW). Two foot of Over-depth is authorized to -12.00 ft
600 CY $291.67 $175,002.00 $395.00 $350.00
3 HYDROGRAPHIC SURVEYS (Pre & Post) 2 EA $24,000.00 $48,000.00 $7,340.00 $20,000.00
4 PRE AND POST DREDGE REPORTS 2 EA $7,000.00 $14,000.00 $3,000.00 $10,000.00
5 $0.00
6 $0.00
7 $0.00
8 $0.00
9 $0.00
10 $0.00
11 $0.00
12 $0.00
TOTAL $833,149.00
NOTE: APPARENT LOW RANKING SHOWN PRIOR TO
CONTRACTING OFFICER MAKING A DETERMINATION
OF RESPONSIBILITY.
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) updated 10/27/16
ABSTRACT OF OFFERS - CONSTRUCTION PAGE1. SOLICITATION NUMBER
70Z08825B0000069
2. DATE ISSUED
3/19/2025
3. DATE OPENED
4/21/25 @ 1:00 PM PST
5. PROJECT TITLE
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
SIGNATURE DATE SIGNED
4. ISSUING OFFICE
Civil Engineering Unit Oakland (CN) 1301 Clay Street 7th Floor, Suite
700N Oakland, CA 94612-5203
Travis Cohen
6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT
(Including Profit) 4 4
MAINTENANCE DREDGING AT THE U.S. COAST GUARD
MOORINGS TONGUE POINT-ASTORIA, OR.-PSN 6049804
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY : Included B. BID SECURITY : Included
A. OFFEROR
BERGERSON
A. OFFEROR
HME
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F)
9. OFFERS
NO. 2
A. HIRED LABOR
NO. 1
C. AMENDMENTS ACKNOWLEDGED: C. AMENDMENTS ACKNOWLEDGED:
E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
$312,000.00 $500,000.00
$237,000.00 $210,000.00
$14,680.00 $40,000.00
$6,000.00 $20,000.00
$0.00 $0.00
$0.00 $0.00
$0.00
$569,680.00 $770,000.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00
$0.00 $0.00
$0.00 $0.00