Appendix-7-OCIO-OCIDANP.docx

DOCX document 221 KB Posted

Attached to
INTERCITY BUS SERVICE FROM PASCO TO MOSES LAKE TO SPOKANE
Solicitation number
RFP 2025-1029
Issued by
Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington

About this file

This document is an Organizational Conflicts of Interest (OCOI) Certification and Disclosure form for a Request for Proposals (RFP-2025-1029) issued by the Washington State Department of Transportation (WSDOT) for an intercity bus service project connecting Pasco, Moses Lake, and Spokane. The project aims to establish a self-sustaining fixed route bus service known as the Wheat Line, which will be integrated into the statewide Travel Washington intercity bus network. The document requires potential vendors to conduct an internal review of team members to identify any potential organizational conflicts of interest and provide a detailed disclosure and mitigation plan if such conflicts exist.

The OCOI form mandates that vendors disclose any situations where they may be unable to render impartial assistance, potentially impaired in objectivity, or have an unfair competitive advantage. Vendors must list potentially conflicted persons or firms, describe the nature of the potential conflict, and provide a comprehensive plan for avoiding, mitigating, or neutralizing these conflicts. The Washington State Department of Transportation retains the sole discretion to review, require revisions to the OCOI plan, and potentially limit or prohibit a vendor's involvement in the project based on the disclosed conflicts of interest.

View the file

Other files

File Type Posted
Appendix-2-Signage-Specs-Graphic-Examples.docx DOCX document
Appendix-1-Service-Schedule.docx DOCX document
Exhibit-A-3-ClientReference.docx DOCX document
Exhibit-C-Bid Price.docx DOCX document
Appendix-4-Vendor-Experience-Form.docx DOCX document
Appendix-6-Cert-Restrictions-on-Lobbying.docx DOCX document
Exhibit-B-PerformanceRequirements.docx DOCX document
Appendix-5-State-Certs-and-Assurances.docx DOCX document
Exhibit-D-Contract.docx DOCX document
2025-1029- Amendment1.docx DOCX document
Exhibit-A-1-BiddersCertification.docx DOCX document
Appendix-3-Key-Staff-Resume-Form.docx DOCX document
RFP-2025-1029.pdf PDF
Appendix-2(a)-Travel-Washington-Logos.docx DOCX document
Exhibit-D-1-ContractIssuesList.docx DOCX document
Exhibit-A-2-BiddersProfile.docx DOCX document
Exhibit-E-DiverseBusinessInclusionPlan.docx DOCX document
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSALS RFP-2025-1029

Pasco to Moses Lake to Spokane Appendix 7 Organizational Conflicts of Interest Certification, Disclosure, and Avoidance/Neutralization Plans Appendix 7: Organizational Conflicts of Interest Certification, Disclosure, and Avoidance/Neutralization Plans ____________________________________

Request for Proposals

RFP-2025-1029

Pasco to Moses Lake to Spokane Washington State Intercity Bus Service Pasco to Moses Lake to Spokane

Offered by

Washington State Department of Transportation

WASHINGTON STATE DEPARTMENT OF TRANSPORTATION

ADMINISTRATIVE SERVICES CONTRACTS OFFICES

ORGANIZATION CONFLICTS OF INTEREST CERTIFICATION, DISCLOSURE AND AVOIDANCE/NEUTRALIZATION PLAN

Name of Vendor:

Organizational Conflicts of Interest Certification My signature below certifies that, prior to submitting the Proposal, the Vendor has conducted an internal review of the Vendor team members to identify any potential, real, or perceived Organizational Conflicts of Interest (“OCOI”) relative to the anticipated procurement as generally described in WSDOT’s Organizational Conflicts of Interest Manual M 3043.01.

I further certify that “Organizational Conflicts of Interest Disclosure and Avoidance/Neutralization Plan” forms are attached for any real or potential organizational conflict of interest, as listed below, for all Vendor team members. Vendor team members include Vendor’s chief executives, directors, personnel filling key Project positions and Vendor’s proposed Subcontractors/Consultants at any tier.

List name of person(s) or firm(s) potentially conflicted (if any).

Signed Date Printed Name and Title Organizational Conflicts of Interest Disclosure and Avoidance/Neutralization Plan This disclosure statement outlines potential organizational conflicts of interest, either real or apparent, which as a result of activities or relationships with other persons or entities, such person or entity:

1.is unable or potentially unable to render impartial assistance or advice to WSDOT; or
2.is or might be otherwise impaired in its objectivity in performing the contract work; or
3.has or appears to have an unfair competitive advantage.

SECTION I of this disclosure statement describes the potential Organizational Conflicts of Interest. SECTION II of this disclosure statement describes the management plan for avoiding or neutralizing the potential Organizational Conflicts of Interest as described in SECTION I of this disclosure statement.

I acknowledge that the Washington State Department of Transportation (WSDOT) may require revisions to the OCOI Plan described in SECTION II of this disclosure statement prior to concurrence, and that WSDOT has the right, in its sole discretion, to limit or prohibit my involvement in the Project as a result of the potential conflicts of interest described in SECTION I of this disclosure statement.

SECTION Ia - Name of Person(s) or Firm(s) Potentially Conflicted

SECTION Ib - Description of Potential Organizational Conflict of Interest

SECTION II - Plan for Avoiding, Mitigating or Neutralizing OCOI

Signed Date Printed Name and Title

WSDOT Concurrence (for WSDOT use only) Signed Date Printed Name and Title image2.jpeg image1.jpg

File details come from the government source that posted it. Updated .