This document is a Request for Information (RFI) related to a federal contract opportunity for the Sprinkler Systems Replacement for Collections at the John Adams Building (JAB) of the Library of Congress in Washington, DC. The solicitation number is AOCACB24R0025 and the project number is LC13017A.

The key details are:

  • This is a full and open competitive solicitation with an estimated magnitude of construction between $25,000,000 and $28,000,000.
  • The Government anticipates awarding the contract in December 2024 with a 1,002 calendar day period of performance.
  • The contractor is allowed to subcontract up to 15% of the work.
  • The Government will not provide the number of proposals received or identify incumbent contractors.
  • The contractor is responsible for securing the construction site per the project specifications. No security devices or cameras are required.
  • The contractor must comply with federal requirements for employing U.S. persons and verifying I-9 documentation.
  • The contractor is required to provide a dedicated Site Safety and Health Officer and coordinate the Quality Control Manager and Assistant Quality Control Manager.
  • The contractor must follow USCP protocols for deliveries and work hours at the site.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No.: AOCACB24R0025 Project No. & Title: JAB Sprinkler System Replacement (PN: LC13017A)

Contracting Officer (CO): John Lingamfelter; john.lingamfelter@aoc.gov Contract Specialist: Charvey Smith; charvey.smith@aoc.gov

Item No. Reference Request for Information (RFI) AOC Responses

1 NA

How many companies are expected to bid on this project? Are there any incumbent contractors? What is the government’s budget for this project and how flexible is it?

AOC Response: This is a full & open competitive solicitation. The Government will not disclose the number of proposals recevied or names of firms that have responded to this solicitation.

The estimated magnitude of construction is between $25,000,000.00 and $28,000,000.00 as stated in page 1 of the solcitiation.

2 NA

When do you expect to make a decision and what is the anticipated start date for the project?

AOC Response: The Government anticipates an award in December 2024. Construction start date is contingent upon issuance of Notice to Proceed (NTP) after award.

SF 1442 RFP, Pg 15

FAR 52.236-1

Please confirm the Contractor is allowed to subcontract the scope of work out. Page 15 of 61 of the solicitation under FAR 52.236-1 indicates 100 percent of the work is to be self performed, but also states to fill in the value.

AOC Response: The solicitation clause has been updated to reflect “fifteen (15) precent”.

4 SF 1442, RFP

Clarify the duration of the project - the 1442 calls for 1016 cd, The bid form calls for 852 cd, L2.5 Factor 5: Technical Approach Pgh B calls for 997 cd

AOC Response: The total construction period of performance is 1,002 calendar days.

Attachment 4

Bid Pricing Schedule

Clarify the unit of measure for unit price one. Confirm it is price per lf of abatement per 012200 3.01. The bid form references DY each -- if not 012200 3.01, clarify what does DY stand for. What pipe size is the pricing to be based on.

AOC Response: As noted in the Specifications, Unit of Measure per 012200 3.01 A.2 is "per linear foot of abatement"

In the Bid Form, DY is the daily rate and applies to General Conditions.

Unit price for 3 and 4 is being removed from the Bid Pricing Schedule.

Follow abatement pricing per the specifications. Asbestos containing pipe insulation unit of measurement is linear feet (LF).

The general size of the asbestos containing pips insulation on deck is 6" - 8" OD insulation.

Attachment 9 USCP Off-Site Vendor

Procedures

Clarify the hours for the delivery screening facility - Section 011000 -calls for 7 pm to 7 am - The document 9. USCP Off-Site Vendor Procedures calls for 4:30 to 3:00 pm ( AOC52.223-8)

AOC Response:

USCP documents and guidelines to prevail with hours of operations for delivery screen facilities etc. At the JAB, deliveries may utilize either roll-up doors on Ground level or Basement level. However Ground level is a shared space, so no storage of delivery material is permitted. All deliveries arriving via the Ground level rollup doors must be stored in the designated areas on the Basement level.

Additionally, see project specification for project delivery scheduling requirements.

7 Spec 012200-3.01

Specification section 012200-3.01 only provides details of Unit Price 1 - Provide detailed description of unit price 2 / 3 / 4 similar to 012200 3.01 (clarify size of fittings - elbows / size of black steel pipe / sprinkler head type etc.)

AOC Response:

Unit price for 3 and 4 will be removed.

Asbestos containing pipe insulation unit of measurement is linear feet (LF). The general size of the asbestos containing pipe insulation on deck 12 is 6"- 8" OD insulation.

8 Spec 014126

Provide specification section 014126 Permit Requirements (referenced in several locations of Division 1). Provide a list of all permits the Contractor is responsible for (public space / building / abatement / trade / occupancy permit etc.)

AOC Response:

Project specifications updated to include 014126 for permit requirements.

SF 1442 RFP

AOC 52.204-4

Please advise if US Persons are allowed on the project or is this a US Citizen project. AOC 52.204-4 indicates US Persons.

AOC Response:

Per paragraph a "By entering into this contract, the Contractor agrees to comply with all federal laws that apply to the Contractor’s activities, including immigration laws, employing only individuals who are eligible to work in the United States and maintaining a signed copy of I-9 Employment Eligibility Verification for each employee if required by law".

Spec section 015000-

3.01E

Specification section 015000-3.01E - states field office and screening faculties to be maintained / cleaned - advise if the screening facility is the off site location or is this located on site. Provide size of staff to support, number of offices, toilets, wash facilities, lunchrooms etc. so we know how to price the supplies. We are assuming those areas are existing as there is no reference to providing temporary space for the Owner.

Confirm the field office space is the contractors space and provide location of the screening facilities

AOC Response:

This project will not provide any screening facilities. Project specifications updated to remove this reference. Follow USCP guidelines for offsite screening.

Spec section 017300-

3.04

Specification section 017300-3.04 - confirm due to the nature of the replacement, is a land surveyor or professional engineer required for the project.

AOC Response:

No land surveyor is needed. This will be removed from the project specifications.

12 Spec 040325

Reference Spec 040325 - Historic Terra Cotta Unit Masonry Repair.

Please confirm that this spec section applies to the patching of some 270 holes in the glazed terra cotta masonry units where the old fire suppression system will be removed. Existing patches do not seem to apply to these standards.

AOC Response:

Correct, this spec (040325) section applies to patching of openings in the glazed terra cotta masonry units where the old fire suppression system would be removed.

13 Drawing G005

Drawing G005 - Deck 1 indicates we can have the entire bay behind the guard booth for laydown and only a portion of the second bay -- Advise if we can have both bays to the existing doors at the loading dock (both entire bays) in that area as stated in the walk thru.

AOC Response:

Laydown areas will be provided as shown on the contract documents. All bids shall be based on bid documents.

14 NA

Provide the size and height of the existing freight elevator

AOC Response: Freight elevator capacity is 4,000# with interior cab dimensions: 8'-6.5" (front to back) x 6'-5.33" (side to side, 74" inside rail to inside rail) x 7'-10.75" high

15 NA

Confirm we will be able to use the floor elevators (with protection) that stop on every other deck if the freight elevator is not operational (it was stated it would not be working until the spring 2025)

AOC Response: Service freight elevator is currently out of service and undergoing repair work with target completion of Spring 2025.

Our project start is dependent on freight elevator being operational as it services every deck on the north side.

Drawing G005 /

015500 3.01

Confirm the fence located at the Partial site plan at west entrance on G005 is unsecured (ref 015500 3.01) and does not require screening facility / low voltage for cameras.

AOC Response:

The fenced area is an unsecured facility in terms of USCP protocols. The contractor is required to secure the facility as outlined in the project specifications (015500 3.01). No cameras shall be included in this contract.

17 A501 detail 2

A501 detail 2 - where plates are to be installed at removed piping locations, confirm thickness of deck system. Is there concrete or just terrazzo above the steel deck. Confirm there is no concrete at locations above steel deck - only finish flooring (or provide location / conditions that there is concrete above steel deck)

AOC Response:

Detail 2 on Sheet A501 shows a condition where 3/16" metal plate can be used to cover each side of a hole in the existing steel plate deck floors when existing sprinkler piping is removed from the decks. The existing steel plate deck is between 1/4" to 3/8" thick and may have cork composition tile or vinyl composition tile on the top surface. Contractor shall verify steel plate deck thickness in the field before installing covers to the holes in the decks. Cork composition tile or vinyl composition tile is the typical condition at the deck floors.

18 A501 detail 2

A501 detail 2 - to install new metal plates, will it be required to chip back the terrazzo flooring for the minimum 1" overlap.

AOC Response:

There is no terrazzo on the steel deck floors where this detail applies. When the piping is removed requiring the hole to be covered, no cork composition tile or vinyl composition tile needs to be chipped back. Any existing fire stopping that remains will likely need to be removed before covering the hole.

19 NA

Does the terrazzo flooring at standpipes have a setback from the existing opening / riser in the deck or does the pour abut the pipe?

AOC Response:

The existing conditions have firestopping between the visible flooring and the pipes. Most of the stairs within the stacks do not have terrazzo flooring at the landings; they have cork composition tile and vinyl composition tile as the floor finish. For the stairs that have terrazzo flooring, it is presumed that the terrazzo goes up to the opening as it may have been cut after the terrazzo was installed.

20 NA

Provide thickness of current terrazzo flooring.

AOC Response:

The thickness of the terrazzo floors is not known and is not identified in the Building Preservation Guide. Historic terrazzo systems could be up to 1/2" thick. Terrazzo is typcally poured over thick mortar beds or concrete. Terrazzo would not be power over the steel deck. While we do not have existing info on the terrazzo, we believe the terrazzo and concrete that is in the corner stairwells could be between 3" to 6".

21 NA

Is the terrazzo poured directly on the steel deck or is there a concrete sub straight

AOC Response:

Historic terrazzo systems could be up to 1/2" thick. Terrazzo is typically poured over thick mortar beds or concrete. Terrazzo would not be power over the steel deck. While we do not have existing info on the terrazzo, we believe the terrazzo and contrete that is in the corner stairwells could be between 3" to 6".

Attachment 4

Bid Pricing Schedule

What size pipe fittings are we to base our price for the Unit Price No. 2?

AOC Response:

Asbestos containing pipe insulation unit of measurement is linear feet (LF). The general size of the asbestos containing pipe insulation on deck 12 is 6"- 8" OD insulation.

23 017419-3.03A

Advise location that a dumpster noted in 017419-3.03A or confirm it will be allowed on site or are we to use the existing facilities

AOC Response:

The project specification does not specifically indicate the use of a dumpster or the location. The contractor has been provided with staging areas. The contractor shall be responsible to develop appropriate means and methods to accomplish the work.

24 NA

Confirm we will be allowed to use the freight elevator to access all the decks. - The construction access plan only show the cellar and Deck 1 for material access / distribution. Also, please confirm we will be allowed to use the roll up door at Deck 2 to direct access the freight elevator as well.

AOC Response:

Yes, freight elevator is accessible to all deck levels. Rollup doors at Basement level (can be utilized provided that sufficient planning/coordination is provided to minimize garage access interruptions) and Ground level (permited with appropriate scheduling as this is a shared space) are available to the project team for loading/ unloading of materials. No storage is available for deliveries at the Ground level rollup doors. Deliveries will need to be staged and stored in the designated basement areas per plan.

25 NA

The technical proposal states an option to propose a better schedule.

Please clarify if the awarded Contract will be based on the offerors proposed schedule for performance or the schedule of performance in the Contract Documents / RFI responses.

AOC Response: No, the AOC will not allow early performance.

The awarded contract will be based on 1,002 calendar days.

SF 1442 RFP

AOC 52.211-12

Please clarify AOC 52.211-12 Damages - Construction - in addition to the liquidated damages stated, should the actual damages (stated in last bullet point) start at final completion not substantial especially due to the unique nature of the project and the access that will be available during the day to the stacks

AOC Response: The clause will remain in the RFP unedited.

Actual Damages are assessed when the AOC incurs damages due to a contractor delay that occurs after substantial completion.

27 NA

Confirm per the site walk, the protection at the book cases may remain in place during the day as long as the books are accessible.

AOC Response:

Yes, protection of the books shall comply with requirements under Specification 013591 (updated to provide additional information).

Temporary protection plastic sheeting could remain in place during the day as long as staff could lift the plastic sheeting to gain access to the books for retrieval.

28 013000- 1.07D5

Confirm a dedicated SSHO officer is required per 013000- 1.07D5 - the text is ghosted / light font. AOC Response:

Per updated Specs 013000.1.07.D, Site Specific Saftey Officer is required to meet the listed criterias.

Spec section 014300 -

1.02 C

Specification section 014300 - 1.02 C - confirm the AQCM does not need to be on site if the QCM is on site and that the AQCM can be working on another project unless needed (by the absence of the QCM) or is the intent to have two individuals (QCM and AQCM) onsite at all times.

AOC Response:

The QCM shall not work on another contract simultaneously with any other project. The AQCM shall not work on another contract when stepping in to fulfill the duties in QCM's absence.

30 NA

Clarify if there is any loading restrictions on the decks for material.

AOC Response:

Per the original building design load letter for JAB, the stack floors are rated at a uniform design live load of 120 pounds per square foot (psf).

Any concentrated loading would need to be looked at on a case by case basis by a Structural Engineer. To avoid a detailed structural analysis, the contractor could detail concentrated loads to be spread out over an area (with a base plate, cribbing, etc) so that the load applied to the floor would equate to the rated 120 psf allowable uniform load.

31 Factor 3

Factor 3: Prime Offeror Past Performance references an enclosed "AOC Past Performance Questionnaire for Prime Offeror," but we were unable to locate this document in the proposal attachments. This applies to both the prime offeror and the subcontractor. Could you kindly provide the PPQ form so we can distribute it for signatures.

AOC Response: The PPQ was incorporated and uploaded to SAM.gov as Attachment 10 via Amendment 03.

32 NA

Please consider granting an extension to the bid to allow sufficient time for the Past Performance Questionnaire (PPQ) form to be sent out, signed, and submitted to the contracting team (this form has not been issued yet).

AOC Response: The PPQ was incorporated and uploaded to SAM.gov as Attachment 10 via Amendment 03.

Phasing Note 4 on

FX001

There is a discrepancy in phasing. Per Phasing Note 4 on FX001, we can only work in one half of one deck at a time. Per Spec Section 011000 paragraph 1.05, we can work in four half decks at a time as long as they are not adjacent. Please confirm.

AOC Response:

Follow spec section 011000, part 1.05. Up to four non-adjacent half decks can be worked at a time.

Additionally, phasing note 4 on FX001 shall be revised to indicate that "up to four non-adjacent half decks can be worked on simultaneously."

Spec Section 015000 paragraph 3.08

Per Spec Section 015000 paragraph 3.08 we are to provide temporary standpipes and hoses. It is assumed that the new standpipes that will be installed in Phase 1 will be used as the temporary standpipes. Please confirm. Also confirm the need for hoses. Standard Fire Department practice is they bring their own hoses into the building and will not use others hoses. If we are to provide hoses, please indicate size, length, and quantity that we are to provide.

AOC Response:

Temporary standpipes per Paragraph 3.08 are not required for this project.

35 Spec Section 211313

Spec Section 211313 calls for sch. 40 pipe with threaded fittings for pipe sizes 2 inch and smaller. Can sch. 10 pipe with grooved fittings be used for pipe sizes 2 inch and smaller? If no, can sch. 40 pipe with grooved fittings be used for pipe sizes 2 inch and smaller?

AOC Response:

Follow the spec requirements. Provide schedule 40 pipe with threaded fittings for pipe sizes 2" and smaller.

36 NA

Can the new sprinkler branch lines be installed in the same location as the existing branch lines? If yes, can the existing hanger brackets be reused?

AOC Response:

Branchlines can be installed at the same locations. Pipe hangers must be replaced with new.

37 NA

Please provide a few column line to column line dimensions so that the graphic scales can be confirmed.

AOC Response:

Between column grif lines 5 through 13, the typical column to column dimension is 14'-0".

38 NA

Hydraulic Calculation Reference Points are shown on some of the FX drawings. Please provide copies of all of the Hydraulic Calculations.

AOC Response:

Calculations will be provided upon award.

Drawing FX102A has

Keynote 5

Drawing FX102A has Keynote 5 listed, but that Keynote is not on the plan. Please advise

AOC Response:

Keynote 5 is inteded to be applied at 2-1/2" pipe serving sprinklers below storage space. See note on drawing 'TRANSITION FROM

EXISTING COPPER TO NEW 2-1/2" STEEL'.

Drawing FX102B has

Keynote 5

Drawing FX102B has Keynote 5 listed, but that Keynote is not on the plan. Please advise

AOC Response:

Keynote 5 is inteded to be applied at 2-1/2" pipe serving sprinklers below storage space. See note on drawing 'TRANSITION FROM

EXISTING COPPER TO NEW 2-1/2" STEEL'.

Drawing FX102D has

Keynotes 3 and 5

Drawing FX102D has Keynotes 3 and 5 listed, but those Keynotes are not on the plans. Please advise

AOC Response:

Keynote 5 is inteded to be applied at 2-1/2" pipe serving sprinklers below storage space. See note on drawing 'TRANSITION FROM

EXISTING COPPER TO NEW 2-1/2" STEEL'.

Keynote 3 is intended to be applied at riser locations next to the hose valve symbols.

Drawing FX401 has

Keynote 3

Drawing FX401 has Keynote 3 listed, but that Keynote is not on the plan.

Please advise

AOC Response:

Keynote 3 is intended to be applied next to Keynote 4 (Detail 8, Deck 2)

Drawing FX402 has

Keynote 3

Drawing FX402 has Keynote 3 listed, but that Keynote is not on the plan.

Please advise.

AOC Response:

Keynote 3 is intedned to be applied on Detail 4, Deck 2, at pipe connecting to the existing supply.

Attachment 4 Bid Pricing Schedule

Unit Price 1

What piping size are we to base our price for the Unit Price No. 1? Also, please confirm that unit of measure should be LF not Each.

AOC Response:

Asbestos containing pipe insulation unit of measurement is linear feet (LF). The general size of the asbestos containing pips insulation on deck is 6" - 8" OD insulation.

Drawing sheets H101 thru H112 General note

Drawing sheets H101 thru H112 General note 3 - please clarify what other hazardous materials that may be disturbed as part of the project include.

Please define any additional items that are outside the unit prices to be included.

AOC Response:

The other Hazardous Materials include lead containing paints (listed on drawings) and fluorescent light fixtures (MVL and PCB ballasts).

46 NA

Advise how much terracotta attic stock is available and does it contain lead / asbestos

AOC Response:

Lead was found within the glaze of the terra cotta block not the block itself. Attic stock is limited; as per project details, reasonable care shall be taken with the removal of the terra cotta blocks for reuse.

A102B (Should be labeled sheet AD102B) Demo/ Existing Deck

02 _ Area B

A102B (Should be labeled sheet AD102B) Demo/ Existing Deck 02 _ Area B - confirm keynote 4 is to demolish shelving - please provide a description or photo of this area for the bidders.

48 NA

Confirm there is no concrete topping in the stack areas - just steel plate and flooring

AOC Response:

No known concrete topping in the stacks area; assumed to be just steel plate and flooring.

AD103D

Keynote 4

Please provide location where bookshelf that is tagged to be relocated on deck 4 is to be moved?

AOC Response:

Bookshelf on Deck 4 is to be relocated in the same location on Deck 3.

A501

Detail 4

Terra cotta blocks in stairwells 1, 4, 5 and 8 at locations above deck 12 are lead containing as described in H112 and the Hazmat Report. Because of the lead, these blocks will need to be removed by an abatement subcontractor, not a masonry subcontractor who has expertise in the salvaging of existing material. Because these are to be ‘salvaged for reuse’, and considering the means/methods of how these will be removed due to the hazmat element, they are likely to be damaged in the process.

Would the AOC consider having the contractor plan on using attic stock at these locations in lieu of salvaged block – and should the existing block be able to be removed without damage, it could then can be reused.

AOC Response:

Per project details, the general contractor shall make all reasonable efforts to salvage the exisiting terra cotta block. There is limited attic stock available, therefore care must be taken in the removal of existing blocks so they may be reused to the greatest extent feasible. In the event a block is damaged, attick stock can be used.

A501

Keynote 3

Keynote 3 states new linoleum tile is to be a compatible color and thickness to existing. Please confirm existing linoleum tile thickness is

0.10 inches (2.5mm) as specified in spec section 096543 2.01 C.

AOC Response:

Linoleum tile can range from 0.10 to 0.125 inches. If there is a price difference between the two thicknesses, assume the more expensive thickness.

52 Spec 011000 1.04

Specification 011000 1.04 describes the scope of work for this project as including selective demolition and patching/repair of concrete and terrazzo floors, cork composite floor tile, painted gypsum wallboard and glazed terra cotta block walls. Locations for selective demo and repair of terrazzo floors and terra cotta block walls are identified in the drawings;

however concrete, cork composite floor tile and painted gypsum wallboard locations are not identified. Please clarify.

AOC Response:

All the floors of the control room and book stacks have cork composition tile or vinyl composition tile on the steel deck. Book conveyor elevators have been removed in the control rooms and concrete floors were installed in their place; the floors are covered in vinyl composition tile. Painted gypsum wallboard locations are at some areas around stairwells that flank the control rooms, and at some areas around the corner stairs.

53 NA

Please provide dimensions and weight capacity of freight elevator that is to be made available by AOC for contractor use. In addition, during the prebid site walk it was stated by the AOC that the freight elevator is currently out of service and being repaired. Please confirm freight elevator will be available for use the entire duration of the project.

AOC Response:

Freight elevator capacity is 4,000# with interior cab dimensions: 8'- 6.5" (front to back) x 6'-5.33" (side to side, 74" inside rail to inside rail) x 7'-10.75" high. Freight elevator will be available for use during the entire duration of the project.

54 Spec 096623

Please provide product information and mix design for existing terrazzo flooring in stairwells so contractor can match existing for repairs. Please verify if controlled sample will be provided to offeror after award.

AOC Response:

No information on the terrazzo mix is in the Building Preservation Guide. Contractor will need to develop samples for review by AOC to match existing terrazzo mix as close as possible. The matrix color is off-white with aggregate black and burgany-gray/ brown in color.

55 Spec 013100

Please confirm that the Project Manager, Project Superintendent and Quality Control Manager should be assigned full time to the project. Also, per specification 13000, 1.07.D, please confirm the Safety Officer must also be assigned to the project per requirements of D.5.

AOC Response:

Project Manager, Project Superintendent, and Quality Control Manager shall be assigned full time to the project and not be working simultaneously on another project.

See revision for clarified Safety Officer criteria in Specification 13000.1.07.D.1.

56 Spec 013591

Specification "Section 013591 3.01 A.1. states "Protect existing historic materials with temporary protections and construction. Do not remove existing materials until all work that may damage the historic materials is complete." It is our understanding that these areas are to be available to staff next day. Please confirm that Offerors are to include in their pricing the installation and removal of this temporary protection each day and it will not be permitted to stay in place over the duration of the project until work is complete.

AOC Response:

Refer to Specifications 01 35 91- Protection

57 Spec 028313 1.04 P Please confirm the General Contractor is responsible for providing the Certified Industrial Hygienist.

AOC Response:

Confirmed. General contractor is responsible for providing Certified Industrial Hygienist. In section 1.04 P of the lead specification, it states that the “CIH shall be hired by the GC, not the abatement contractor. If there is no GC, the removal contractor shall hire the CIH and they will report directly to the Architect. #1:

The Architect reserves the right to provide the CIH. The Contractor shall verify who is responsible for hiring the CIH at the time of Bidding”.

58 NA

There are several conflicting PoPs stated in the documents. Please confirm the Period of Performance we are to assume is 1,016 calendar days as identified on form 1442.

AOC Response: The contract period of performance is 1,002 calendar days.

59 Spec 15 50 00

Please confirm the temporary secure perimeter fence for the compound as outlined in 15 50 00 does not have to be a secure fence (i.e. containing security devices, cameras, electronic hardware, etc.).

AOC Response:

Temporay secure perimeter shall be secured in accordance with project specifications (015000). Installation of security devices and camera hardware are not anticipated at this time.

FX001, FX601, &

FX102

General Note #30

Sprinkler General Note #30 on Drawing FX001 indicates the requirement to provide a temporary fire pump capable of 1,500 gpm at 200 psi for standpipe testing. Per the Riser Diagram (Drawing FX601) & FX102D, the building is already equipped with an existing fire pump. Per standard industry practice in accordance with NFPA 14, 20 & 25, please confirm that the existing fire pump can be utilized for the required standpipe flow testing.

AOC Response:

General contractor must provide adequate means to test standpipe system at demands necessary to meet NFPA 14. Existing fire pump satisfies sprinkler demans only and does not have adequate rating to meet standpipe demands.

61 NA

The spec consistently references “lead containing materials’, and not “lead-based paint” nor does it provide a definition of “lead based paint” or “lead containing materials”. Please confirm disturbance of components with any concentration of lead, regardless of being “lead based” or “lead containing”, must be handled in accordance with OSHA Lead in Construction requirements.

AOC Response:

The specification does not give a specific definition of Lead- Containing Material, but this term means any component or material containing a measureable amount of lead. A lead containing paint (LCP) and surface coating screening was performed by AMA for the project. Please refer to the Hazardous Materials report generated for this project by AMA in January 2021 for more information converning LCP. The report is attached to specification section 028213.

This is not a lead abatement project; lead-based paint levels are not of concern. Lead containing paint is any paint that contains a measurable amount of lead. These paints must be handled in accordance with the project specification and the OSHA Lead in Construction Standard (29 CFR 1926.62).

62 Spec 028313

The lead sampling plan as outlined in specifications includes mention of wipe sampling. Please confirm wipe sampling is required. If so, what is the clearance criteria? Do background samples need to be collected?

AOC Response:

The sampling plan is for locations where the general contractor decides to remove lead containing paint. Follow any local regulatory criteria for clearance.

63 NA

Would the AOC consider an extension of the bid date to Friday, 4-October to allow adequate time for the subcontracting market to review and provide complete quotes given the timing of end of fiscal year?

AOC Repsonse: The propsoal due was extened to October 3, 2024 per Amendment 03.

64 NA

Please confirm any library collateral that requires to be moved to allow for work to be completed will be the responsibility of AOC and/or the Library; e.g. Books, Library Carts, etc.).

AOC Response:

Confirmed. All library collateral will be moved by the Government to allow for the general contractor access to permit the work.

65 NA

Please provide photos of the interior of the storage room that was not viewable during both site walks?

66 NA

Please confirm that Contractor trailer compound can be located on the street in lieu of the location shown on the drawings, to not disturb any landscaping areas. Please confirm that a permit is not required in order to locate the compound and trailer to the street.

AOC Response:

No, contractor trailer compound is not permitted to be located on the street. Suggest following location as identified in the drawings.

Applicable permits will apply.

67 NA

Please confirm if the attic stock of the terra cotta block that are to be used are also lead containing? Also, please confirm quantity of attic stock.

AOC Response:

Lead was found within the glaze of the terra cotta block not the block itself. Attic stock is limited; as per project details, reasonable care shall be taken with the removal of the terra cotta blocks for reuse.

68 NA

Section L, Item L.1.A.4 refers to "… paragraph C below". There is not paragraph C - please advise on what is being referred too.

AOC Response: Attachment 1 Sections L & M has been revised with red text to update this clerical error, and uploaded to SAM.gov for reference.

69 NA

Please confirm incidental disturbance of lead containing or lead based materials required to complete the work/tasks can be handled in accordance with OSHA Lead in Construction requirements.

AOC Response:

Yes, confirmed

70 NA

Sheet FA001, under Fire Alarm General Notes, Note #4, states "Contractor shall provide all equipment, software, programming, accessories whether mentioned or not. Including addressable interfaces, terminal, cabinet, conduit, wire junction boxes, fasteners, hangers, etc. " Regarding "whether mentioned or not", given the offerors are to price the plans and specs, please confirm that the Government would consider an item that is not mentioned or shown as a change.

AOC Response:

No, fire alarm is a delegated design and required to meet the project specifications and drawings. General contractor shall provide a fully functional system that meets the design intent of the project specifications and drawings.