Amendment A RFP Activity Calendar 88N-19.pdf
PDF 81 KB Posted
- Solicitation number
- BD-19-1206-40000-40000-38457
- Issued by
- Massachusetts
About this file
This document is an amendment to the Request for Proposals (RFP) No. 88N-19 issued by the Massachusetts Bay Transportation Authority (MBTA) for a Fuel Management System for their buses and non-revenue vehicles. The amendment updates the RFP Activity Calendar, including the pre-bid conference date, pre-bid site visits, deadline for submitting proposer questions, publication of official answers, response due date, in-person presentations, contract execution, and service start date. The RFP is seeking a provider for a Fuel Management System to support the MBTA's fleet of buses and non-revenue vehicles.
The amendment requires acknowledgment of the changes in the proposal submission. The contract award is estimated to be executed on August 26, 2019, with the service start date estimated to be September 19, 2019. The RFP does not provide any additional details regarding pricing terms, set-asides, incumbent contractors, funding requirements, or other salient information.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MBTA Logo, Charles D. Baker, Governor, Karyn E. Polito, Lieutenant Governor, Stephanie Pollack, MassDOT Secretary & CEO, Luis Manuel Ramírez, General Manager & CEO, MassDOT logo
Massachusetts Bay Transportation Authority
Ten Park Plaza, Boston, MA 02116 www.mbta.com
June 26, 2019
SUBJECT: RFP No. 88N-19
MBTA Fuel Management System
Amendment A
RFP Activity Calendar
Dear Sir/Madam:
GENERAL CLARIFICATION
Pursuant to the policies and guidelines set forth in RFP-88N-19, Amendment A, is issued regarding changes to the RFP Activity Calendar.
RFP issued 6/13/2019
Dial-in Pre-bid conference 6/20/2019
Pre-Bid Site Visits (estimated) 7/11/2019 locations & times TBD
Deadline for submission of
Proposer questions via
COMMBUYS
7/16/2019 2:00PM
Official Answers of Q&A published on COMMBUYS
7/19/2019 2:00PM
Response Due Date 7/31/2019 2:00PM
In-person presentations at MBTA (estimated) 8/13/2019
Contract Execution (estimated) 8/26/2019
Service Start Date (estimated) 9/19/2019
Acknowledgement of this Amendment must be confirmed in your proposal.
ALL ELSE REMAINS AS PREVIOUSLY STATED IN THE RFP.
Sincerely, Rob Weiner
Office of Procurement and Logistics