About this file

This is Amendment #1 to Invitation to Bid (ITB) #40100-13904 issued by the Tennessee Department of Transportation (TDOT) for McNairy Manhole Repairs. The amendment addresses questions and clarifications regarding the project scope, timeline, and bonding requirements. The original procurement encompasses junction box and manhole cover repair and replacement services at 15 locations along State Route 15 in McNairy County, with bid opening scheduled for May 8, 2026 at 1:00 PM CDT and closing on June 10, 2026 at 1:00 PM CDT. The amendment clarifies that new manhole lids do not require covers, as depicted in project photographs, and that high-early strength concrete should be used for all lid fabrication as solid covers. Significantly, the amendment permits contractors to request an extended timeline of 160 calendar days rather than the original 45 days to account for setup time, material ordering, and concrete cure time, though TDOT is not holding contractors to standard cure time protocols and lids may be transported and set when the contractor deems safe without damage. The written questions and comments deadline was May 15, 2026 at 1:00 PM CT, with a bidders list to be posted during the Open File Period following the Intent to Award notification.

The amendment adds two critical bonding requirements to the Terms and Conditions: Performance Bond language in Section 8.5 and Payment Bond language in Section 8.6. Certified payroll submissions are not required. Bidders must submit a single line item price on an F.O.B. destination basis inclusive of all taxes, fees, overhead, and costs, with the contract awarded to the lowest cost responsive bidder. Contractors must maintain workers' compensation and employer liability insurance of at least $1,000,000, commercial general liability insurance with combined single limits of $1,000,000 per occurrence and $2,000,000 aggregate, and automobile liability insurance of $1,000,000 per occurrence. The estimated budget for this procurement is $264,700.00. All bids must be submitted through the State's EDISON Supplier Portal, and the procurement contact is Kristine Mitchell at (615) 770-1015 or Kristine.mitchell@tn.gov.

View the file

Other files

File Type Posted
Event_40100-13904_Clarification.pdf PDF
Amendment__1-40100-13904-Questions_and_Comments-1.pdf PDF
Example_Images.docx DOCX document
40100-0000588622_13904-TC.docx DOCX document
ADA_Specifications_McNairy_Manholes.docx DOCX document
40100_-_McNairy_Manhole_Cover_Repair.pdf PDF
ADA_Specifications_McNairy_Manholes.docx DOCX document
40100_-_McNairy_Manhole_Cover_Repair.pdf PDF
Example_Images.docx DOCX document
40100-0000588622_13904-TC.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB # 40100-13904– Questions & Comments Page 1 of 1

STATE OF TENNESSEE

DEPARTMENT OF TRANSPORTATION

INVITATION TO BID (ITB) # 40100-13904

AMENDMENT #1 FOR MCNAIRY MANHOLE REPAIRS

DATE: 05/20/2026

ITB # 40100-13904 IS AMENDED AS FOLLOWS:

1. State responses to questions and comments in the table below amend and clarify this ITB.

Any restatement of ITB text in the Question/Comment column shall NOT be construed as a change in the actual wording of the ITB document.

Comments, Questions and Answers # ITB Section Question/Comment Answer 1 Terms &

Conditions Is there a bond required?

Please reference below Summary of Changes for the added language into the Terms and Conditions.

2 Terms & Conditions

Certified payroll?

Certified payrolls are not required to be submitted.

3 Specifications New lids have manhole covers left out as depicted in photo’s?

That is correct. No lids necessary.

4 Specifications The project time would need to be 160 days instead of 45 days due to set up time, ordering materials and there is a time frame of 105 days for cure time.

TDOT is not holding the contractor to the normal cure times or waiting for 7 or 28 day breaks. The lids can be transported and set when the contractor is confident in doing so without damage. In the Specifications Scope of Work Section d.ii. states “use hi-early strength concrete for all lid fabrication as solid covers”.

5 General Will there also be a bidders list posted?

Yes, it will be available during the Open File Period in the procurement file after the Intent to Award is sent out.

2. Summary of Changes.

Performance Bond language has been added to the Terms and Conditions, Section 8.5.

Payment Bond language has been added to the Terms and Conditions, Section 8.6.