This document provides details for an upcoming General Services Administration (GSA) Region 1 construction indefinite delivery, indefinite quantity (IDIQ) contract solicitation. The solicitation will provide construction services for repairs, alterations, and renovations to federally owned and leased facilities in Connecticut, Massachusetts, Rhode Island, Maine, New Hampshire, and Vermont. The procurement will be 100% set aside for small businesses with a total estimated price range of $100-125 million over the five-year base and option periods. Individual task orders are estimated to range from $250,000 to the annual prospectus limit. A pre-solicitation conference will be held on February 14, 2023, with registration due by February 10. Questions regarding the requirement are due by February 21. The anticipated award date is September 2023.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. General Services Administration
Public Buildings Service
New England Region
New England IDIQ Ordering Guide
Table of Contents Introduction
Roles and Responsibilities
New England IDIQ Contract Holders
North Zone Buildings
Boston Zone Buildings
South Zone Buildings
The Ordering Process
Step 1: Acquisition Planning
Step 2: Develop the Solicitation
Step 3: Issue the Solicitation
Step 4: Evaluate Proposals
Step 5 Award the Task Order
Step 6: Task Order Administration
Step: 7 Contract Closeout
Introduction
The Acquisition Management Division (AMD) in the General Services Administration
(GSA) Region 1 has issued X construction indefinite delivery, indefinite quantity (IDIQ) contracts to support the Repair and Alterations Program in the region. The Budget Activity 54 (BA54)
Program (Minor Repairs and Alterations), funds repair and alteration (R&A) projects that are not a part of a congressional appropriation line item. Typical non-Prospectus Level, i.e., BA54
Program projects include initial space alterations, repairs, remodeling, improvements, and other related changes to public buildings with a cost ranging from $250,000 to the annual prospectus limit. At the start of each fiscal year, the PBS “national office” or “headquarters” provides Region 1 with the BA54 Program budget. These Regional 1 IDIQ contracts are established on a geographic zonal basis and are for use by any space under GSA’s jurisdiction.
file:///C:/Users/adamlkatzman/Downloads/Copy%20of%20Ordering%20Guide%20docx.docx%23_Toc119864630 file:///C:/Users/adamlkatzman/Downloads/Copy%20of%20Ordering%20Guide%20docx.docx%23_Toc119864631 file:///C:/Users/adamlkatzman/Downloads/Copy%20of%20Ordering%20Guide%20docx.docx%23_Toc119864632
New England IDIQ
Ordering Guide 2
Who is the guide for?
This guide is written for Contracting Officers (COs) who may be issuing orders under the New
England Construction IDIQ contracts. In addition to this guide COs must adhere to the Federal
Acquisition Regulation (FAR) requirements, General Services Acquisition Manual / Regulation
(GSAM/R), and Region 1 internal policies.
Roles and Responsibilities
● Contracting Officers (CO’s) have the authority to solicit, award, and administer task orders against the Contract vehicle. The Contracting Officer is the apparent authority for the task order and can bind the government.
● Contracting Officer Representative (COR’s)- The Contracting Officer for each task order should designate a Contracting Officer’s Representative (COR) to perform specific administrative or technical functions. The Contracting Officer Representative Supervisor shall send the Contracting Officer a nomination letter, nominating the Contracting Officer
Representative. The specific authority, limitations, and responsibilities of the COR for each task order shall be described in an appointment letter, a copy of which should be provided to the contractor. Unless otherwise stated, a COR has no actual, apparent, or implied authority to bind the Government.
New England IDIQ Contract Holders
The PBS Governmentwide IDIQ contracts include three (3) multiple-award Geographic Zones.
The NAICS code is 236220, Commercial and Institutional Building Construction. All the
Construction IDIQ contracts have been set-aside for small businesses.
The Geographic zones include
• North Geographic Zone (see page 3)
• Boston Geographic Zone (see page 4)
• South Geographic Zone (see page 5)
Ordering Guide 3
North Zone Buildings
Vermont New Hampshire Maine
Land Ports of Entry
Route 5
Derby Line, VT 05830
Interstate Route 91
Derby Line, VT 05830
743 VT Route 243
North Troy, VT
807 VT Route 243
North Troy, VT
State Route 114
Norton, VT
U.S. Post Office and Courthouse
11 Elmwood Avenue
Burlington, VT 05401
State Street
Montpelier, VT 05602
Rutland, VT
50 South Main Street
St. Albans, VT 05478
SSA Trust Fund
Building
School Street
Montpelier, VT 05602
58 Pearl Street
Burlington, VT 05401
Winston Prouty
Federal Building
11 Lincoln Street
Essex Junction, VT
05452
U.S. Border Stations
Vermont Rt. 225
Alburgh, VT 05440
2812 Alburgh Springs
Road
Alburgh Springs, VT
05440
Main Street
Beebe Plain, VT
05823
State Route 102
Beecher Falls, VT
05902
U.S. State Route 102
Canaan, VT 05903
482 Welcome Center
Rd
Highgate Springs, VT
State Rte 118
West Berkshire, VT
807/743 Vermont Rt.
North Troy, VT
357 Glen Sutton Road
Richford, VT 05476
705 Province Street
Richford, VT 05476
U.S. Border Patrol
Sector
Headquarters
155 Grand Avenue, Rte 7
Swanton, VT 05488
James C. Cleveland Federal
53 Pleasant Street
Concord, NH 03301
Warren B. Rudman U.S.
Courthouse
55 Pleasant Street
Concord, NH 03301
Norris Cotton Federal Building
275 Chestnut Street
Manchester, NH 03101
Thomas J. McIntyre Federal
80 Daniel Street
Portsmouth, NH 03801
SSA Trust Fund Building
177 Main Street
Littleton, NH 03561
Land Ports of Entry
180 International
Ave.
Calais, ME 04619
Interboundary Line, State Rt. 6
Jackman, ME 04945
U.S. Border Patrol Houlton Section
Headquarters
96 Calais Road, Rt. 1
Hodgdon, ME 04730
SSA Trust Fund
365 Main Street
Presque Isle, ME
04769
Edmund S. Muskie
Federal Building 40 Western Avenue
Augusta, ME 04330
Margaret Chase
Smith
Federal Building
U.S. Post Office and
Courthouse
202 Harlow Street
Bangor, ME 04401
Edward T. Gignoux U.S. Courthouse
156 Federal Street
Portland, ME 04101
U.S. Customhouse 312 Fore Street
Portland, ME 04101
U.S. Border
Stations
Ferry Point
3 Customs Street
Calais, ME 04619
Milltown
534 North Street
Calais, ME 04619
Boundary Line Road
Fort Fairfield, ME
04742
U.S. Route 1
Fort Kent, ME 04743
Interstate 95
Houlton, ME 04530
Route 229
Limestone, ME 04750
Bridge Road
Madawaska, ME
04756
U.S. Route 1
Orient, ME 04471
St. Pamphile
Saint Francis, ME
04774
173 Acadian Way
Van Buren, ME 04785
Route 6, Water Street
Vanceboro, ME 04491
Ordering Guide 4
Boston Zone Buildings
Boston Metro Boston
Captain John F. Williams Coast Guard Building
408 Atlantic Avenue
Boston, MA
02110
John W. McCormack U.S. Post Office and Courthouse
5 Post Office Square
02109
John J. Moakley U.S. Courthouse
One Courthouse Way
02210
John F. Kennedy Federal Building
15 New Sudbury Street
02203
Thomas P. O’Neill, Jr. Federal Building
10 Causeway Street
Boston, MA 02222
Fredrick C. Murphy Federal Center
380 Trapelo Road
Waltham, MA
02452
Social Security Admin District Office
Main & Fountain Streets
Haverhill, MA
01830
IRS Center
310 Lowell Street
Andover, MA
05501
Ordering Guide 5
South Zone Buildings
Connecticut Western Massachusetts
Brien McMahon Federal Building and U.S. Courthouse
915 Lafayette Boulevard
Bridgeport, CT 06604
Abraham A. Ribicoff Federal Building and U.S. Courthouse
450 Main Street
Hartford, CT 06103
William R. Cotter Federal Building
135 High Street
Hartford, CT 06103
Robert N. Giaimo Federal Building
150 Court Street
New Haven, CT 06510
Richard C. Lee
Church and Court Streets
New Haven, CT 06471
Social Security Administration
147 Litchfield Street
Torrington, CT 06790
Southern Massachusetts
Social Security Administration
400 North Main Street
Fall River, MA 02720
U.S. Custom House
37 North Second Street
New Bedford, MA 02740
Hastings Keith Federal Building
53 North Sixth Street
New Bedford, MA 02740
Rhode Island
Federal Building and
1 Exchange Terrace
Providence, RI John O. Pastore Federal Building
And U.S. Post Office
2 Exchange Terrace
Providence, RI 02903
Philip J. Philbin Federal Building
881 Main Street
Fitchburg, MA 01420
Silvio O. Conte Federal Building
78 Center Street
Pittsfield, MA 01201
310 State Street
Springfield, MA 01105
Harold D. Donohue Federal Building
595 Main Street
Worcester, MA 01608
Ordering Guide 6
The Ordering Process
The New England Construction IDIQs are multiple-award indefinite delivery, indefinite quantity contracts. When using the New England Construction IDIQ contracts. The Contracting Officer must follow FAR 16.505 ordering procedures.
Step 1: Acquisition Planning
Acquisition Planning should begin as soon as the agency need is identified. The Acquisition team should meet to ensure that the New England Construction IDIQ vehicle is the correct contract method for the project. The Contracting Officer should work with the Contracting Officer Representative to create an acquisition plan. The regional BA54 and BA80 Subsidiary Acquisition Plan (Subsidiary Plan) can be used if price is the only evaluation factor. The Subsidiary Plan should be signed prior to issuing the RFP. A full acquisition plan is needed if price is not the only evaluation factor.
Determining which Geographic Zone to Use The Contracting Officer shall determine which geographic zone to utilize. Competition of Task Order solicitations will be exclusive to the IDIQ contracts awarded within a Geographic Zone
Task Order Contract Type All task orders under the New England Construction IDIQ contracts will be awarded as a firm-fixed price task order.
Order Limitations The maximum order against all contracts is $125 million. The individual Task Orders to be placed under the IDIQ contracts range in dollar value from approximately from the simplified acquisition threshold (currently $250,000) up to the prospectus level (currently $3,613,000).
Contractors are not required to respond to Request for Proposals outside of this range.
Task Order Duration The period of performance for each task order awarded under the New England Construction IDIQ contract shall be specified in the task order in accordance with FAR 16.505(c).
Task orders shall be solicited and awarded prior to the expiration of the applicable IDIQ contract’s period of performance. Task orders should not be extended after the expiration of the IDIQ base contracts. After the contracts expire, they will remain active for administration purposes only.
Fair Opportunity Fair Opportunity must be given to each IDIQ contract holder. Request for Proposals must be sent to each on-boarded IDIQ Contractor in the applicable geographic zone.
Ordering Guide 7
Brand Name Specifications In accordance with FAR 16.505(a)(4), the Contracting Officer must document justification for brand name justification. A template for the justification can be found in the contract shell under tab 4 on the Acquisition Management Division Insite website.
Multiple Locations If a requirement is for multiple locations, a Consolidation Analysis is required. This Analysis must be approved at the Senior Procurement Executive level.
Step 2: Develop the Solicitation
The Contracting Officer shall work with the Contracting Officer Representative to ensure that all documents are received for a complete package.
Price Estimating and Developing the Independent Government Estimate (IGE)
The Contracting officer shall ensure that an independent Government estimate (IGE) is prepared at the earliest practicable time for each proposed task order. The IGE must be signed and received from the technical staff no later than issuance of the solicitation.
Solicitation All task order solicitations shall provide the following information at a minimum:
• Task Order Statement of Work
• Evaluation Factors
• Selection Methodology
• Period of Performance
• Place of Performance
• Solicitation Questions Due Date
• Proposal Due Date
• Proposal and Submittal Instructions
Project Magnitude Contracting Officers shall include the disclosure of magnitude in the RFP pursuant to FAR
36.204 and GSAR 536.204. The Contracting Officer shall not disclose the government estimate.
Pre-Proposal Conferences & Site Visits The Contracting Officer should coordinate with the Contracting Officer Representative arrangements for the Site-Visit. The Contracting Officer should try to attend the site-visit.
Notice of intent to attend should be provided to the Contracting Officer in accordance with the task order instructions. If attendance is not practicable, a separate pre-proposal conference should be scheduled to inform the contractors information relevant to the solicitation.
Ordering Guide 8
Liquidated Damages Liquidated damages are determined at the task order level. Liquidated damages should be dictated in accordance with FAR 11.502, FAR 36.206, and FAR 52.211-12.
Task Order Pricing Pricing has been established at the IDIQ base contract level for several labor categories, general requirements, overhead, profit, and bonding. Unless the CO specifies another format, Task Order price proposals shall use the task order pricing sheet (Attachment 1) when submitting proposals. The line items established in the IDIQ contract cannot exceed the prices established in the IDIQ base contract but can be lower than the agreed upon price in the IDIQ contract. It is the Contracting Officer’s responsibility to ensure that pricing proposed aligns with these policies and in conjunction with the Contracting Officer Representative ensure that the price proposed is fair and reasonable.
Construction Wage Rate Requirements
The Contracting Officer shall provide the contractors the applicable wage determination rates at the task order level. The wage determination rates can be found at www.Sam.Gov. Prior to award, the Contractor Officer shall perform a wage determination check to confirm that the wage determination had not changed from the solicitation. If the wage determination has changed, the updated wage determination shall be sent as an amendment to the appropriate contractors.
Bid Guarantees Contracting Officers shall indicate in the RFP if a bid Guarantee, and or performance and payment bonds are required. Pursuant to FAR 52.228-1, Bid Guarantee should be incorporated into task order solicitations expected to exceed $150,000. And in accordance with FAR 28.102-1 COs shall indicate requirements for performance and payment bonds in task order solicitations when the task order is expected to exceed $150,000.
Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment Provision FAR 52.204-24, Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment shall be incorporated in all task order solicitations.
Step 3: Issue the Solicitation
Task Order solicitations should be emailed to the respective zone contractors. A google drive folder should be set-up to share secure documents with the contractor’s GACA email addresses.
Contractors should be notified of any amendments via email. Contractors are not obligated to propose on all Task Orders; however, they are required to notify the CO that they do not plan http://www.sam.gov/
Ordering Guide 9 to provide a proposal. Failure to provide this notification may impact future consideration of the contractor for Task Orders and the exercise of any option.
Step 4: Evaluate Proposals
The Contracting Officer should send the proposal to the Contracting Officer Representative for technical evaluation. Proposals shall be evaluated based upon the criteria set forth in the solicitation. The contract file should document the rationale for placing the order as well as the determination of fair and reasonableness. The Contracting Officer Representative shall send the Contracting Officer a signed technical evaluation which accurately depicts if the proposal demonstrates technical acceptance. The Contracting Officer shall ensure that the price proposed is aligned with the rates agreed upon in the base contract.
Step 5 Award the Task Order
Task Order Award Form Contracting Officers must sign awards using the GSA Form 300. Awards should be signed in
EASI.
Performance and Payment Bonds for Task Orders
In accordance with FAR 52.228-15 both performance and payment bonds must be received and accepted prior to issuing Notice to Proceed (NTP) for task orders over $150,000. Bonds should be submitted within ten (10) calendar days after the Task Order is executed.
Reporting Task Orders The task order shall be reported in FPDS. Additionally, the task order shall be updated in Acquisition Gateway and OFCP shall be notified of the award. The Contracting Officer shall also fill out the CIW form and send the form via email to Zone A at zonea-hspd12@gsa.gov. The Contracting Officer should be sure to send the contractor the COR Appointment letter with the executed GSA 300 form. It is also important for the Contracting Officer to register the CPARS via the regional CPARS registration form.
Step 6: Task Order Administration
Modifications All modifications shall be executed in EASI. Similarly, all modifications must be reported in FPDS. Modifications should be well documented and all relevant documentation shall be uploaded into EASI.
Prompt Payments Payments shall be made in accordance with the FAR 52.232-27, Prompt Payment for Construction Contracts (JAN 2017) and supplemented by GSAR 552.232-5. Payments should be https://hallways.cap.gsa.gov/app/ https://www.optcore.net/ofnp-ofnr-ofng-ofcg-ofcp-how-to-choose/
Ordering Guide 10 made within 14 days. The contractor shall submit a pencil req to the Contracting Officer Representative and Contracting Officer. Upon approval, the Contracting Officer Representative shall create a receiving report in EASI for the Contracting Officer to review and approve in the system.
Payrolls and Labor Compliance The Contracting Officer is responsible for reviewing and payroll statements. The contractor must submit for the contractor and each subcontractor, copies of weekly payrolls applicable to the contract prior to invoicing.
Step: 7 Contract Closeout
Performance Evaluation Each CO is responsible for ensuring the contractor’s performance on each order is reported in the CPARS system pursuant to FAR 42.15. Task orders valued at $750,000 require a performance evaluation.
Task Order Closeout Contracting Officers are responsible for closing out their task orders. Contracting Officers should reference the regional contract closeout policies and ensure that all the appropriate documentation is filed in EASI including, Contractor Completion letter, Contract Completion
Statement, Release of Claims, and if applicable the CPARS evaluation.
IDIQ Administration
The New England Construction IDIQs are multiple-award indefinite delivery, indefinite quantity contracts. Administrative matters will be handled by the IDIQ Contracting Officer, Contract Specialists, and Contracting Officer’s Representatives.
Ordering Guide 2
Biannual Review Meetings
The Contracting Officer, Contract Specialist, and Contracting Officer’s Representative shall meet twice a year (every six months) with representatives from each IDIQ contractor. In these meetings, the following topics should be discussed:
- Contractor performance on task orders
- Contractor responsiveness to RFP’s issued under the IDIQ
- Contractor’s competitiveness in task order solicitations
- Contractor’s risk of being off-boarded from the vehicle
- Contractor’s risk of not having an option exercised.
Topics, concerns, and impressions discussed in these meetings should be reflected in the contractor’s CPARS ratings and option exercising decisions.
Option Exercising Process
The IDIQ vehicles are award with one base year and four option year periods. These options should be evaluated and exercised in accordance with FAR 52.217-9.
| Introduction |
| Roles and Responsibilities |
| New England IDIQ Contract Holders |
| North Zone Buildings |
| Boston Zone Buildings |
| South Zone Buildings |
| The Ordering Process |
| Step 1: Acquisition Planning |
| Step 2: Develop the Solicitation |
| Step 3: Issue the Solicitation |
| Step 4: Evaluate Proposals |
| Step 5 Award the Task Order |
| Step 6: Task Order Administration |
| Step: 7 Contract Closeout |
| IDIQ Administration |
| Biannual Review Meetings |
| The Contracting Officer, Contract Specialist, and Contracting Officer’s Representative shall meet twice a year (every six months) with representatives from each IDIQ contractor. In these meetings, the following topics should be discussed: |
| - Contractor performance on task orders |
| - Contractor responsiveness to RFP’s issued under the IDIQ |
| - Contractor’s competitiveness in task order solicitations |
| - Contractor’s risk of being off-boarded from the vehicle |
| - Contractor’s risk of not having an option exercised. |
| Topics, concerns, and impressions discussed in these meetings should be reflected in the contractor’s CPARS ratings and option exercising decisions. |
| Option Exercising Process |
| The IDIQ vehicles are award with one base year and four option year periods. These options should be evaluated and exercised in accordance with FAR 52.217-9. |